R5‑253700 Agenda - opening session WG Chairman agenda Information
1.1Welcoming brief by the host
Yes
YesThe RAN5 Chair openend the meeting. TSDSI welcomed on behalf of the host all delegates to the RAN5#108 meeting in Bangalore and presented the practicalities. Then the RAN5 Chair reminded: Reminder for IPR declaration "The attention of the delegates to the meeting of this Technical Specification Group was drawn to the fact that 3GPP Individual Members have the obligation under the IPR Policies of their respective Organizational Partners to inform their respective Organizational Partners of Essential IPRs they become aware of. The delegates were asked to take note that they were thereby invited: to investigate whether their organization or any other organization owns IPRs which were, or were likely to become Essential in respect of the work of 3GPP. to notify their respective Organizational Partners of all potential IPRs, e.g., for ETSI, by means of the IPR Information Statement and the Licensing declaration forms " Antitrust Guidance "The attention of the delegates to the meeting was drawn to the fact that 3GPP activities were subject to all applicable antitrust and competition laws and that compliance with said laws was therefore required by any participant of the meeting, including the Chair and Vice-Chairs and were invited to seek any clarification needed with their legal counsel. The leadership would conduct the present meeting with impartiality and in the interests of 3GPP. Delegates were reminded that timely submission of work items in advance of TSG/WG/SWG meetings was important to allow for full and fair consideration of such matters." Consensus principle reminder “The attention of the delegates to the meeting is drawn to the fact that 3GPP endeavours to reach consensus on all decisions and therefore depends on a cooperative spirit of the Individual Members. In particular, Individual Members are encouraged to seek a consensus-based solution and only to sustain objections as a very last resort, and where absolutely necessary and well justified. The leadership will conduct the present meeting in a manner whereby informal methods of reaching consensus are encouraged, whilst ensuring that well justified concerns are taken into account.” Then new delegates from Nokia India and CICT introduced themselves. The election for the RAN5 Chair was then carried out. Mr Jacob John from Motorola was elected as a RAN5 Chair for another term, being the only candidate. The election for the RAN5 Vice Chair was then carried out. Mr Xiaozhong Chen from CATT was elected as a RAN5 Vice Chair for another term, being the only candidate.
noted No    
R5‑253701 Agenda - midweek session WG Chairman agenda Information
4.5.1Agenda for mid-week session
Yes
Yes
noted No    
R5‑253702 Agenda - closing session WG Chairman agenda Information
7.1Agenda for closing session
Yes
Yes
noted No    
R5‑253703 RAN5#108 Session Programme WG Chairman agenda Information
1.1Welcoming brief by the host
Yes
Yes
noted No    
R5‑253704 RAN5 Leadership Team WG Chairman other Information
2.1Live Reports
Yes
Yes#107
revised No R5‑254899  
R5‑253705 RAN5#107 WG Minutes ETSI Secretariat report Approval
2.1Live Reports
Yes
Yes
approved No    
R5‑253706 RAN5#107 WG Action Points ETSI Secretariat report Information
2.1Live Reports
Yes
Yesthe joint AP 05.02 was closed at the last meeting RAN5#107.
noted No    
R5‑253707 Latest RAN Plenary notes WG Chairman report Information
2.1Live Reports
Yes
Yes
noted No    
R5‑253708 Latest RAN Plenary draft Report WG Chairman report Information
2.1Live Reports
Yes
Yes
noted No    
R5‑253709 Post Plenary Active Work Item update ETSI Secretariat other Information
2.1Live Reports
Yes
Yes
noted No    
R5‑253710 RAN5 SR to RP#108 WG Chairman report Information
2.2General Reports for information
Yes
Yes
noted No    
R5‑253711 TF160 SR to RP#108 WG Chairman report Information
2.2General Reports for information
Yes
Yes
noted No    
R5‑253712 RAN5#108 LS Template WG Chairman other Information
4.3RAN5 PRDs/Templates
Yes
Yes
noted No    
R5‑253713 Meeting schedule for 2025-26 WG Chairman other Information
4.4Meeting schedule for 2025-26
Yes
Yes
noted No    
R5‑253714 WI Progress and Target Completion Date Review WG Chairman other Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
No
Yes3 WIs completed.
noted No    
R5‑253715 Review deadlines for next quarter WG Chairman other Information
7.7Confirmation of Future RAN5 Matters
Yes
Yes
noted No    
R5‑253716 LS on E-UTRA uplink configurations for intra-band ENDC MSD TSG WG RAN4 LS in Information
5.2Review incoming LS (fm A.I. 3) & new subject discussion papers
Yes
Yesmoved to RF
noted No    
R5‑253717 LS on requesting test Specification and procedures for NR-NR DC between FR1-FR2 devices in 3GPP 38.521-3 GCF SG LS in Action
3Incoming Liaison Statements
Yes
Yespresented by Verizon. RAN5 Chair: is already concluded. Technically is seems to be not feasible. Vodafone & DOCOMO supported that LS in GCF, but no contribution in RAN5. RAN5 Vice Chair RF: it has been an issue of non-testability. There seems nothing to be missing in the RF specs. The LS response should point to PRD.21. ->Response LS together with CMCC.
revised No R5‑254907  
R5‑253718 Addition of TT analysis for E-UTRAN event-triggered TC 6.6.25.1, 6.6.25.2 and 6.6.25.3 MediaTek Inc. CR Agreement
5.3.32.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑253719 Update E-UTRAN event-triggered TC 6.6.25.1, 6.6.25.2 and 6.6.25.3 including TTs MediaTek Inc. CR Agreement
5.3.32.4TS 38.533
Yes
Yes
agreed No    
R5‑253720 Update Annex F for E-UTRAN event-triggered TC 6.6.25.1, 6.6.25.2 and 6.6.25.3 including TTs MediaTek Inc. CR Agreement
5.3.32.4TS 38.533
Yes
Yes
agreed No    
R5‑253721 Update test procedure for IoT NTN TC 13.4.1.2 and 13.4.1.3 MediaTek Inc., ROHDE & SCHWARZ CR Agreement
5.5.1.4TS 36.521-3
Yes
Yes
agreed No    
R5‑253722 SR for UE Conformance - Access Traffic Steering, Switch and Splitting support in the 5G system architecture; Phase 3 China Telecom WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253723 WP for UE Conformance - Access Traffic Steering, Switch and Splitting support in the 5G system architecture; Phase 3 China Telecom Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253724 SR for UE Conformance MPS when access to EPC5GC is WLAN China Telecom WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253725 WP for UE Conformance MPS when access to EPC5GC is WLAN China Telecom Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253726 Update applicability for test cases 7.1, 7.2, 7.5, 7.7, 7.9 and 7.10 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yesword filename r1
revised No R5‑254965  
R5‑253727 Update applicability for test cases 7.4a, 7.6a, 7.8, 7.12, 7.13, 7.18 and 7.19 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yesword filename r1
revised No R5‑254966  
R5‑253728 Update applicability for test cases 7.24, 7.24a, 7.24b, 7.25, 7.27, 7.28, 7.30, 7.31, 7.32 and 7.34 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yesword filename r1
revised No R5‑254967  
R5‑253729 Addition of TT analysis for NR NTN TC 14.2.2.2.1 and 14.2.2.2.2 MediaTek Beijing Inc.,Qualcomm Technologies International, Ltd CR Agreement
5.3.4.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑253730 Update NR NTN RA TCs including TT MediaTek Beijing Inc.,Qualcomm Technologies International, Ltd CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑253731 Update Test applicability for NR NTN RA TCs MediaTek Beijing Inc.,Qualcomm Technologies International, Ltd CR Agreement
5.3.4.5TS 38.522
Yes
Yes
agreed No    
R5‑253732 Addition of new test case 14.2.3 and 14.2.4 for NR NTN MediaTek Beijing Inc.,Qualcomm Technologies International, Ltd CR Agreement
5.3.30.6TS 38.533
Yes
Yes
agreed No    
R5‑253733 Update A-MPR test case for NS 202 Ericsson CR Agreement
5.3.42.1.1Tx Requirements (Clause 6)
Yes
Yes
withdrawn Yes    
R5‑253734 Update A-MPR test case for CA NS 202 Ericsson CR Agreement
5.3.42.1.1Tx Requirements (Clause 6)
Yes
Yes
withdrawn Yes    
R5‑253735 Update additional spurious emission for CA NS 202 Ericsson CR Agreement
5.3.42.1.1Tx Requirements (Clause 6)
Yes
Yes
withdrawn Yes    
R5‑253736 Update additional spurious emission for new CA NS 205 Ericsson CR Agreement
5.3.42.1.1Tx Requirements (Clause 6)
Yes
Yes
withdrawn Yes    
R5‑253737 Update applicability for test cases 7.11 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No    
R5‑253738 Update applicability for test cases 7.11 Ericsson CR Agreement
6.6.6.2TS 34.229-2
No
Yes
withdrawn Yes    
R5‑253739 Update applicability for test cases 7.26 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No    
R5‑253740 Update applicability for test cases 7.29 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
revised No R5‑254968  
R5‑253741 Update applicability for test cases 7.33 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No    
R5‑253742 New WID on UE Conformance - Introduction of another IoT-NTN S-band (MSS band 2000-2020 MHz UL and 2180-2200 MHz DL) MediaTek Inc., China Telecom, EchoStar WID new Endorsement
4.1New Work Item proposals - for intro only
Yes
Yespresented by China Telecom
revised No R5‑254908  
R5‑253743 WP UE Conformance - Further NR mobility enhancements MediaTek Inc., Apple, China Telecom Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253744 SR UE Conformance - Further NR mobility enhancements MediaTek Inc., Apple, China Telecom WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253745 WP UE Conformance - Further enhancements on NR and MR-DC measurement gaps and measurements without gaps MediaTek Inc., Huawei Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253746 SR UE Conformance - Further enhancements on NR and MR-DC measurement gaps and measurements without gaps MediaTek Inc., Huawei WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253747 Update to the applicability of NES RRM TC 6.3.3.6 and 6.3.3.7 MediaTek Inc. CR Agreement
5.3.20.4TS 38.522
Yes
Yes
agreed No    
R5‑253748 Correction to applicability conditions MediaTek Inc. CR Agreement
5.4.9TS 38.522
Yes
YesTo solve the overlap issue with R5-253900.
withdrawn Yes    
R5‑253749 Update to default SIB4 message for NR channel BW less than 5MHz for FR1 MediaTek Inc., Nokia CR Agreement
6.3.8.1TS 38.508-1
Yes
Yesr1
revised No R5‑254993  
R5‑253750 Update to Idle mode TC for NR channel BW less than 5MHz for FR1 MediaTek Inc., Nokia CR Agreement
6.3.8.3TS 38.523-1
Yes
Yesr1
revised No R5‑254994  
R5‑253751 Update to default SIB24 message for NR channel BW less than 5MHz for FR1 MediaTek Inc., Nokia CR Agreement
6.3.8.6TS 36.508
Yes
Yesr1
revised No R5‑254995  
R5‑253752 Update to TC 8.5.4.1 for Further measurement gap enhancements MediaTek Inc. CR Agreement
6.3.27.4TS 36.523-1
Yes
Yesr1
revised No R5‑255037  
R5‑253753 Addition of PICS for Further measurement gap enhancements MediaTek Inc. CR Agreement
6.3.27.5TS 36.523-2
Yes
Yesr1
revised No R5‑255038  
R5‑253754 Addition of EPC IMS DC TC 8.18 MediaTek Inc. CR Agreement
6.3.28.5TS 34.229-1
Yes
Yesr1
revised No R5‑254981  
R5‑253755 Addition of 5GC IMS DC TC 6.11 MediaTek Inc. CR Agreement
6.3.28.8TS 34.229-5
Yes
Yes
agreed No    
R5‑253756 Addition of PICS for ATSSS Phase 3 MediaTek Inc. CR Agreement
6.3.32.2TS 38.508-2
Yes
Yesmeeting questioned whether the new pcs proposed duplicartion of same pics defined in 36.523-2 for EPC over non-3GPP access network. Is it the correct table to add this pics? AP 108.01
agreed No    
R5‑253757 Addition of ATSSS Phase 3 TC 11.9.5 MediaTek Inc. CR Agreement
6.3.32.3TS 38.523-1
Yes
Yesr2
revised No R5‑255047  
R5‑253758 Addition of ATSSS Phase 3 TC 11.9.6 MediaTek Inc. CR Agreement
6.3.32.3TS 38.523-1
Yes
Yesr2
revised No R5‑255048  
R5‑253759 Addition of ATSSS Phase 3 TC 11.9.7 MediaTek Inc. CR Agreement
6.3.32.3TS 38.523-1
Yes
Yesr2 RAN5 Chair: there is no HO in the test procedure!
revised No R5‑255049  
R5‑253760 Addition of ATSSS Phase 3 TC 11.9.8 MediaTek Inc. CR Agreement
6.3.32.3TS 38.523-1
Yes
Yesr2
revised No R5‑255050  
R5‑253761 Addition of applicability for ATSSS Phase 3 TC MediaTek Inc. CR Agreement
6.3.32.4TS 38.523-2
Yes
Yes
agreed No    
R5‑253762 Correction to NB-IoT Generic procedure 8.1.5.2 MediaTek Inc. CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
Yes
agreed No    
R5‑253763 Correction to PICS used in NB-IoT TC MediaTek Inc. CR Agreement
6.5.3.11Others (TS 36.523-1 clauses not covered by other AIs under AI 6.5.3, e.g. eMBMS, Home (e)NB, MBMS in LTE, D2D, SC-PTM, NB-IoT, CIoT...)
Yes
Yes
agreed No    
R5‑253764 Editorial correction to PICS in TC 9.2.2.1.3 MediaTek Inc. CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yespresented by R&S
agreed No    
R5‑253765 Correction to the title of NB-IoT NTN TC 22.1.3 MediaTek Inc. CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yespresented by R&S Title doesn't reflect the changes. Shall be merged into other CR.
withdrawn Yes    
R5‑253766 Editorial modification to 6.2A.3.0.4.5 Ericsson CR Agreement
5.3.42.1.1Tx Requirements (Clause 6)
Yes
Yes
withdrawn Yes    
R5‑253767 Correction to applicability of TC 7.1.1.4.2.4 MediaTek Inc. CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No    
R5‑253768 Correction to applicability of MAC test cases MediaTek Inc. CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No    
R5‑253769 Correction to applicability conditions MediaTek Inc. CR Agreement
6.4.5TS 38.523-2
Yes
Yesr1
revised No R5‑254940  
R5‑253770 Update to random access test cases for IoT NTN test MediaTek Beijing Inc.,Rohde & Schwarz CR Agreement
5.5.1.4TS 36.521-3
Yes
YesWIC was inverted
agreed No    
R5‑253771 Update to location-based cell reselection for IoT NTN enhancement MediaTek Beijing Inc.,CMCC CR Agreement
5.3.25.3TS 36.521-3
Yes
Yes"RAN4 dependent on R4-2509216 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑253772 Update description of Common test environment and NB-IoT Common contents of system information MediaTek Beijing Inc.,CMCC CR Agreement
5.3.25.1TS 36.508
Yes
Yesr1
revised No R5‑255281  
R5‑253773 Update test applicability for IoT NTN enh TCs MediaTek Beijing Inc.,CMCC CR Agreement
5.3.25.4TS 36.521-2
No
Yes
withdrawn Yes    
R5‑253774 Update IoT NTN enh TCs including TT MediaTek Beijing Inc.,CMCC CR Agreement
5.3.25.3TS 36.521-3
Yes
Yes
agreed No    
R5‑253775 Update of initial condition to IoT NTN multi cell TCs MediaTek Beijing Inc.,CMCC CR Agreement
5.3.25.3TS 36.521-3
No
Yes
withdrawn Yes    
R5‑253776 Editorial corrections to the EN in clause 4.3.1.1.3 MediaTek Inc. CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑253777 Addition of test frequencies for R16 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.1.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑253778 Editorial correction to testcase 7.1.1.14.2.1 Nokia CR Agreement
6.3.13.3TS 38.523-1
No
Yes
withdrawn Yes    
R5‑253779 Corrections to testcase 7.1.1.3.20 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yesr1
revised No R5‑255027  
R5‑253780 Corrections to testcase 7.1.1.3.20a Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yesr1
revised No R5‑255028  
R5‑253781 Editorial correction to testcase 7.1.1.3.21 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yesr1
revised No R5‑255029  
R5‑253782 Corrections to testcase 7.1.1.5.7 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yesr1
revised No R5‑255031  
R5‑253783 Corrections to testcase 7.1.1.5.8 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yesr1
revised No R5‑255032  
R5‑253784 New testcase 7.1.1.5.9 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yesr1
revised No R5‑255033  
R5‑253785 Applicability declaration of testcase 7.1.1.5.9 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yes
agreed No    
R5‑253786 Corrections to testcase 7.1.1.6.9 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yes
agreed No    
R5‑253787 WP UE Conformance - XR (eXtended Reality) enhancements for NR plus CT1 aspects Nokia Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253788 SR UE Conformance - XR (eXtended Reality) enhancements for NR plus CT1 aspects Nokia WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253789 Addition of test frequencies for R15 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑253790 Addition of UE capability for R16 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.1.2TS 38.508-2
Yes
Yes
agreed No    
R5‑253791 Addition of UE capability for R15 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.4.2TS 38.508-2
Yes
Yes
agreed No    
R5‑253792 Addition of RF baseline implementation capabilities for new PC2 R18 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.10.2TS 38.508-2
Yes
Yesr1
revised No R5‑255210  
R5‑253793 Update to SOR-CMCI PICS MediaTek Inc. CR Agreement
6.4.2TS 38.508-2
Yes
Yesr1
revised No R5‑254932  
R5‑253794 Applicability update to SOR-CMCI TC MediaTek Inc. CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No    
R5‑253795 Correction of LTM test case 7.1.1.1.28 MediaTek Inc.,MCC TF160 CR Agreement
6.3.23.3TS 38.523-1
Yes
Yes
agreed No    
R5‑253796 Correction of test case 10.6 MediaTek Inc., StarPoint CR Agreement
6.6.6.5TS 34.229-5
Yes
Yes+5GS r2
revised No R5‑254964  
R5‑253797 Addition of reference sensitivity TP analysis for new EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.10.6TR 38.905 (NR Test Points Radio Transmission and Reception )
Yes
Yesr1
revised No R5‑255218  
R5‑253798 Addition of reference sensitivity for new PC2 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.10.4.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255217  
R5‑253799 FR2 MU - PC6 MU definition for spherical tests in 38.903 Keysight Technologies UK Ltd CR Agreement
5.3.5.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑253800 FR2 MU - PC6 spherical Tx test update in 38.521-2 Keysight Technologies UK Ltd CR Agreement
5.3.5.3.1Tx Requirements (Clause 6)
Yes
Yes"Discussion in R5-254048 Discussion in R5-254048 8/25: Moderator (Apple) - No comments received as of 08/25 PM coffee break on the associated discussion paper in R5-254048 or this CR. This CR will be marked OK to agree in 08/25 FR2 MU Update if no further comments/concerns received."" 8/26 Moderator (Apple) No comments received. This CR can be agreed."
agreed No    
R5‑253801 FR2 MU - PC6 spherical Rx test update in 38.521-2 Keysight Technologies UK Ltd CR Agreement
5.3.5.3.2Rx Requirements (Clause 7)
Yes
Yes"Discussion in R5-254048 8/25: Moderator (Apple) - No comments received as of 08/25 PM coffee break on the associated discussion paper in R5-254048 or this CR. This CR will be marked OK to agree in 08/25 FR2 MU Update if no further comments/concerns received."""
agreed No    
R5‑253802 FR2 MU - PC6 annexes update in 38.521-2 Keysight Technologies UK Ltd CR Agreement
5.3.5.3.3Clauses 1-5, Annexes
Yes
Yes"Discussion in R5-254048 8/25: Moderator (Apple) - No comments received as of 08/25 PM coffee break on the associated discussion paper in R5-254048 or this CR. This CR will be marked OK to agree in 08/25 FR2 MU Update if no further comments/concerns received. 8/26 Moderator (Apple) No comments received. This CR can be agreed."
agreed No    
R5‑253803 FR2 MU - PC6 editor notes updates in 38.521-3 Keysight Technologies UK Ltd CR Agreement
5.4.6.1Tx Requirements (Clause 6)
Yes
Yes"Moderator (Apple) - No comments received as of 08/25 PM coffee break for this CR. This CR will be marked OK to agree in 08/25 FR2 MU Update if no further comments/concerns received. 8/26 Moderator (Apple) - No comments received. This CR can be agreed."
agreed No    
R5‑253804 FR2 MU - PC3 analysis for OBW UL MIMO test Keysight Technologies UK Ltd discussion Endorsement
5.4.20Discussion Papers, Work Plan, TC lists
Yes
Yes"Moderator (Apple) - NTT Docomo has concerns on Prop2 - under Japanese regulations, the FR2 OBW may have been tested with UL MIMO.And there is a possibility that testing is conducted with MIMO. Proposals 1 will be suggested to be endorsed in 08/26 FR2 MU status Update if no further comments/concerns received. 8/26 Moderator (Apple) - Discussion paper can be noted and Proposal 1 can be endorsed"
noted No    
R5‑253805 FR2 MU - PC3 update for OBW UL MIMO test in 38.903 Keysight Technologies UK Ltd CR Agreement
5.4.18TR 38.903 (NR MU & TT analyses)
Yes
Yesr1
revised No R5‑255298  
R5‑253806 FR2 MU - PC3 update for OBW UL MIMO test in 38.521-2 Keysight Technologies UK Ltd CR Agreement
5.4.5.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255296  
R5‑253807 FR2 MU - PC3 MU update for OBW UL MIMO test in 38.521-2 Annex F Keysight Technologies UK Ltd CR Agreement
5.4.5.3Clauses 1-5, Annexes
Yes
Yesr1
revised No R5‑255297  
R5‑253808 FR2 MU - Missing entries in 38-521-3 Annex F Keysight Technologies UK Ltd CR Agreement
5.4.6.3Clauses 1-5, Annexes
Yes
Yes"Moderator (Apple) - No comments received as of 08/25 PM coffee break for this CR. This CR will be marked OK to agree in 08/25 FR2 MU Update if no further comments/concerns received. 8/26 Moderator (Apple) - No comments received. This CR can be agreed."
agreed No    
R5‑253809 Update applicability for test cases 7.35 and 7.36 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No    
R5‑253810 Addition of reference sensitivity for new R15 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑253811 Addition of reference sensitivity TP analysis for new R15 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.4.19TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
revised No R5‑255238  
R5‑253812 Addition of delta TIBc for new R16 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.1.5.1Tx Requirements (Clause 6)
No
Yes
withdrawn Yes    
R5‑253813 Addition of reference sensitivity for new R16 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.1.5.2Rx Requirements (Clause 7)
Yes
YesTable 7.3B.2.0.3.5.2-1: R5-254319: We are going to discuss with ZTE. r2
revised No R5‑255278  
R5‑253814 Update applicability for test cases 7.37, 7.38, 7.39, 7.40, 7.41 and 7.42 Ericsson CR Agreement
6.3.28.6TS 34.229-2
Yes
Yes
agreed No    
R5‑253815 Correct the MTSI media capability for data channel Ericsson CR Agreement
6.3.28.6TS 34.229-2
Yes
Yesr2
revised No R5‑254986  
R5‑253816 Correction to NR-NTN Test Case SS-RSRP 14.6.1.1 Including TT Rohde & Schwarz CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑253817 Correction to NR-NTN SS-RSRP Test Case 14.6.1.2 Including TT Rohde & Schwarz CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑253818 Correction to NR-NTN SS-RSRQ Test Case 14.6.2.1 Including TT Rohde & Schwarz CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑253819 Correction to NR-NTN SS-RSRQ Test Case 14.6.2.2 Including TT Rohde & Schwarz CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑253820 Annex F Correction for NR-NTN Measurement Accuracy Test Cases Including TT Rohde & Schwarz CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑253821 Test Tolerance for RRM NR NTN SS-RSRP Test Case 14.6.1.1 Rohde & Schwarz CR Agreement
5.3.4.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑253822 Test Tolerance for RRM NR NTN SS-RSRP Test Case 14.6.1.2 Rohde & Schwarz CR Agreement
5.3.4.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑253823 Test Tolerance for RRM NR NTN SS-RSRQ Test Case 14.6.2.1 Rohde & Schwarz CR Agreement
5.3.4.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑253824 Test Tolerance for RRM NR NTN SS-RSRQ Test Case 14.6.2.2 Rohde & Schwarz CR Agreement
5.3.4.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑253825 Update to RRM Intra-frequency distance-based conditional Handover from FR1 to FR1 for ATG including TT Sporton International INC. CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑253826 Test Tolerance analysis for RRM Intra-frequency distance-based conditional Handover from FR1 to FR1 for ATG Sporton International INC. CR Agreement
5.3.13.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑253827 Update to RRM Inter-frequency distance-based conditional Handover from FR1 to FR1 for ATG including TT Sporton International INC. CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑253828 Test Tolerance analysis for RRM Inter-frequency distance-based conditional Handover from FR1 to FR1 for ATG Sporton International INC. CR Agreement
5.3.13.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑253829 Update to RRM Intra-frequency RRC Re-establishment in FR1 for ATG including TT Sporton International INC. CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑253830 Test Tolerance analysis for RRM Intra-frequency RRC Re-establishment in FR1 for ATG Sporton International INC. CR Agreement
5.3.13.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑253831 Update to RRM Inter-frequency RRC Re-establishment in FR1 for ATG including TT Sporton International INC. CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑253832 Test Tolerance analysis for RRM Inter-frequency RRC Re-establishment in FR1 for ATG Sporton International INC. CR Agreement
5.3.13.7TR 38.903 (NR MU & TT analyses)
Yes
Yesr1
revised No R5‑255325  
R5‑253833 Test Tolerance Update in Annex F for RRM Intra-Frequency and Inter-Frequency test case in FR1 for ATG Sporton International INC. CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑253834 Addition of EVM equalizer spectrum flatness for CA (3UL & 4UL CA) Sporton International INC. CR Agreement
5.4.5.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑253835 Addition of EVM equalizer spectrum flatness for CA (5UL to 8UL CA) Sporton International INC. CR Agreement
5.4.5.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255353  
R5‑253836 Addition of Applicability for EVM equalizer spectrum flatness for FR2 CA Sporton International INC. CR Agreement
5.4.9TS 38.522
Yes
Yes
agreed No    
R5‑253837 Correction to FR1 SSB based L1-RSRP measurement for Satellite Access including TT Anritsu CR Agreement
5.3.4.6TS 38.533
Yes
No"Depends on RAN4 CR: R4-2509125, R4-2509126 Associated CR for TR 38.903: R5-253838 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑253838 Introduction of Test Tolerance analysis for 14.5.3.1 NR SA FR1 SSB based L1-RSRP measurement for Satellite Access Anritsu CR Agreement
5.3.4.7TR 38.903 (NR MU & TT analyses)
Yes
Yes"Depends on RAN4 CR: R4-2509125, R4-2509126 Associated CR for TS 38.533: R5-253837 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑253839 Corrections to testcase 7.1.1.14.2.1 Nokia Corporation CR Agreement
6.3.13.3TS 38.523-1
Yes
Yesr1
revised No R5‑255058  
R5‑253840 Addition of R16 EN-DC combos into clause 5 KDDI Corporation CR Agreement
5.3.1.5.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑253841 Addition of R15 EN-DC combos into clause 5 KDDI Corporation CR Agreement
5.4.6.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑253842 Addition of SIB23 and related scheduling information for SLPP test cases CATT CR Agreement
6.3.22.1TS 38.508-1
Yes
Yesr2
revised No R5‑255007  
R5‑253843 Addition of default SL-PRS resource pool configuration CATT CR Agreement
6.3.22.1TS 38.508-1
Yes
Yesr1
revised No R5‑255008  
R5‑253844 Addition of SLPP default message contents and test condition CATT CR Agreement
6.3.22.2TS 37.571-2
Yes
Yesr1
revised No R5‑255009  
R5‑253845 Addition of new SLPP abort procedure test cases CATT CR Agreement
6.3.22.2TS 37.571-2
Yes
Yesr2
revised No R5‑255010  
R5‑253846 Addition of new SLPP error handling procedure test cases CATT CR Agreement
6.3.22.2TS 37.571-2
Yes
Yesr3
revised No R5‑255011  
R5‑253847 Addition of test applicabilities for new SLPP abort and error handling procedure test cases CATT CR Agreement
6.3.22.3TS 37.571-3
Yes
Yesr1
revised No R5‑255012  
R5‑253848 Addition of sidelink positioning related information and assistance data CATT CR Agreement
6.3.22.5TS 37.571-5
Yes
Yesr1
revised No R5‑255013  
R5‑253849 Addition of new UE Rx-Tx time difference reporting delay test case 15.2.11 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253850 Addition of new UE Rx-Tx time difference reporting delay test case 15.2.12 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253851 Addition of new UE Rx-Tx time difference reporting delay test case 15.2.13 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253852 Addition of new UE Rx-Tx time difference reporting delay test case 15.2.14 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253853 Addition of new UE Rx-Tx time difference reporting delay test case 15.2.15 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253854 Addition of new UE Rx-Tx time difference reporting delay test case 15.2.16 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes..851 r1
revised No R5‑255332  
R5‑253855 Addition of new UE Rx-Tx time difference accuracy test case 15.3.7 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253856 Addition of new UE Rx-Tx time difference accuracy test case 15.3.8 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253857 Addition of new UE Rx-Tx time difference accuracy test case 15.3.9 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253858 Addition of new UE Rx-Tx time difference accuracy test case 15.3.10 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253859 Addition of new UE Rx-Tx time difference accuracy test case 15.3.11 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253860 Addition of new UE Rx-Tx time difference accuracy test case 15.3.12 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253861 Addition of release 18 Multi-RTT test conditions CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑253862 Addition of test applicabilities for NR RSTD and UE Rx-Tx time difference test cases CATT CR Agreement
5.3.27.3TS 37.571-3
Yes
Yesr1
revised No R5‑255335  
R5‑253863 Work plan: UE Conformance Test Aspects - Expanded and improved NR positioning CATT Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253864 SR UE Conformance Test Aspects - Expanded and improved NR positioning CATT WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253865 Revised WID on UE Conformance Test Aspects - Expanded and improved NR positioning CATT WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yesr2
revised No R5‑255101  
R5‑253866 WP UE Conformance – Introduction of 900 MHz LTE band in the US Nokia Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253867 SR UE Conformance – Introduction of 900 MHz LTE band in the US Nokia WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253868 Addition of test point analysis for NS_UAV_44, NS_UAV_46 and NS_UAV_70 Nokia CR Agreement
5.3.33.6TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
YesEricsson offline comment r1
revised No R5‑255237  
R5‑253869 Addition of Aerial UE A-MPR and additional spurious emissions test requirements Nokia CR Agreement
5.3.33.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑253870 Update to R18 IoT NTN test cases applicability CMCC CR Agreement
5.5.1.6TS 36.521-2
Yes
Yes
withdrawn Yes    
R5‑253871 SR Rel-18 IoT NTN enh after RAN5#108 CMCC WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253872 WP Rel-18 IoT NTN enh after RAN5#108 CMCC Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253873 Update to R18 IoT NTN enh RRM TCs applicability CMCC, MediaTek Beijing Inc. CR Agreement
5.3.25.4TS 36.521-2
Yes
Yes
agreed No    
R5‑253874 SR Rel-18 ATG for NR after RAN5#108 CMCC WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253875 WP Rel-18 ATG for NR after RAN5#108 CMCC Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253876 Update to TP analysis for ATG TCs CMCC CR Agreement
5.3.13.8TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑253877 Introduction of General description of Transmit modulation quality for ATG UE CMCC CR Agreement
5.3.13.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑253878 Introduction of General ON/OFF time mask for ATG UE CMCC CR Agreement
5.3.13.3.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255240  
R5‑253879 Update to Annex F MUTT for ATG UE CMCC CR Agreement
5.3.13.3.3Clauses 1-5, Annexes
Yes
Yesr1
revised No R5‑255254  
R5‑253880 Introduction of PUSCH-PUCCH and PUSCH-SRS time masks for ATG UE CMCC CR Agreement
5.3.13.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑253881 Editorial Correction to FR1 ATG Tx TCs CMCC CR Agreement
5.3.13.3.1Tx Requirements (Clause 6)
Yes
YesOverlap with R5-254069 (Keysight) Both CRs correct the same editroial errors in ATG NR Tx TCs and modify the same Tx TC. R5-253881 (CMCC) is going to be withdrawn to solve the overlap
withdrawn Yes    
R5‑253882 Update to applicability of 5G ATG TCs CMCC, QUALCOMM Europe Inc. - Spain, ZTE Corporation, Ericsson, Keysight, Huawei, HiSilicon CR Agreement
5.3.13.5TS 38.522
Yes
Yesr1
revised No R5‑255341  
R5‑253883 Update to Abbreviations for ATG SIG TCs CMCC CR Agreement
6.3.7.3TS 38.523-1
Yes
Yes
agreed No    
R5‑253884 Update to Abbreviations for ATG Demod TCs CMCC CR Agreement
5.3.13.4.4Clauses 1-4, Annexes
Yes
Yes
agreed No    
R5‑253885 Introduction of Applicability of requirements for ATG CMCC CR Agreement
5.3.13.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No    
R5‑253886 Update to Abbreviations for ATG RRM TCs CMCC CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑253887 Update of Measurement Performance requirements for ATG CMCC CR Agreement
5.3.13.6TS 38.533
Yes
Yesr1
revised No R5‑255350  
R5‑253888 Introduction of Minimum conformance requirements of RRC_IDLE state mobility for ATG CMCC CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑253889 Editorial Correction to RRM cell configuration mapping for ATG TCs CMCC CR Agreement
5.3.13.6TS 38.533
Yes
YesOverlap with R5-254550 (Huawei) Both CRs correct editroial errors in ATG cell configuration mapping. R5-253889 (CMCC) is going to be withdrawn to solve the overlap
withdrawn Yes    
R5‑253890 SR NR_Rel-16_CA_DC after RAN5#108 CMCC WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253891 WP NR_Rel-16_CA_DC after RAN5#108 CMCC Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
No
No
reserved No    
R5‑253892 Update to test frequency for CA_n40A-n41A CMCC CR Agreement
5.3.1.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑253893 Update to REF SENSE TP analysis for CA_n40A-n41A CMCC CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑253894 Update to FR1 RF common parts for CA_n40A-n41A CMCC CR Agreement
5.4.4.3Clauses 1-5, Annexes
No
Yes
withdrawn Yes    
R5‑253895 Update to FR1 Tx TCs for config CA_n40A-n41A CMCC CR Agreement
5.3.1.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑253896 PRD21 CDS NR PC3 CA_n40A-n41A CMCC other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
Yes
Yes
noted No    
R5‑253897 Update to R16 NR CADC configuration test cases applicability CMCC CR Agreement
5.3.1.7TS 38.522
Yes
Yes
withdrawn Yes    
R5‑253898 Update to R17 NR CADC configuration test cases applicability CMCC CR Agreement
5.3.2.7TS 38.522
Yes
Yes
withdrawn Yes    
R5‑253899 Update to R18 NR CADC configuration test cases applicability CMCC CR Agreement
5.3.12.7TS 38.522
Yes
Yes
withdrawn Yes    
R5‑253900 Update to applicability of 5G TCs CMCC, MediaTek CR Agreement
5.4.9TS 38.522
Yes
YesOverlap with R5-254473 (Huawei) and R5-253748 (MediaTek) All these three CRs correct editroial errors in Table 4.0-1 and Table 4.0-2. R5-253748 (MediaTek) is going to be withdrawn and the content in R5-253748 will be merged into R5-253900r1 (CMCC) to solve the overlap. MediaTek will be added as co-source company in R5-253900r1 (CMCC). R5-254473 (Huawei) is going to undo the changes to solve the overlap. r1
revised No R5‑255338  
R5‑253901 SR Rel-19 PC2 40MHz n28 after RAN5#108 CMCC WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253902 WP Rel-19 PC2 40MHz n28 after RAN5#108 CMCC Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253903 Update to MOP TC for n28 PC2 40MHz CMCC CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑253904 Update to MOP UL MIMO TC for n28 PC2 40MHz CMCC, Huawei, HiSilicon CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
YesOverlap with R5-254779 (Huawei) Both CRs add new TCs for MOP UL MIMO of n28 PC2 40MHz. R5-254779 (Huawei) is going to be withdrawn to solve the overlap. Huawei will be added as co-source company in R5-253904r1 (CMCC). r1
revised No R5‑255264  
R5‑253905 Update to MPR UL MIMO TC for n28 PC2 40MHz CMCC, Huawei, HiSilicon CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
YesOverlap with R5-254779 (Huawei) Both CRs add new TCs for MPR UL MIMO of n28 PC2 40MHz. R5-254779 (Huawei) is going to be withdrawn to solve the overlap. Huawei will be added as co-source company in R5-253905r1 (CMCC). r1
revised No R5‑255265  
R5‑253906 Update to MOP TxD TC for n28 PC2 40MHz CMCC, Huawei, HiSilicon CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
YesOverlap with R5-254780 (Huawei) Both CRs add new TCs for MOP TxD of n28 PC2 40MHz. R5-254780 (Huawei) is going to be withdrawn to solve the overlap. Huawei will be added as co-source company in R5-253906r1 (CMCC). r1
revised No R5‑255266  
R5‑253907 Update to PICS for n28 PC2 40MHz CMCC CR Agreement
5.3.34.2TS 38.508-2
Yes
Yes
agreed No    
R5‑253908 SR Rel-19 HPUE single band after RAN5#108 CMCC WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253909 WP Rel-19 HPUE single band after RAN5#108 CMCC Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253910 Revised WID on UE Conformance - Rel-19 High power UE (power class 1.5 and 2) for NR FR1 TDD/FDD single band for handheld/FWA UEs, and high power UE operation (power class 2, 1.5 and 1) for FWVM (fixed-wireless/vehicle-mounted) use cases in a single NR ban CMCC WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yesis endorsed
agreed No    
R5‑253911 Update to PICS for n104 PC1.5 CMCC CR Agreement
5.3.36.2TS 38.508-2
Yes
Yes
agreed No    
R5‑253912 Update to MOP TC for n104 PC1.5 CMCC CR Agreement
5.3.36.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑253913 Update to MOP TxD TC for n104 PC1.5 CMCC CR Agreement
5.3.36.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑253914 Update to MPR TxD TC for n104 PC1.5 CMCC CR Agreement
5.3.36.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑253915 PRD21 on NR bands and 5G NR CADC config handling v1.14.0 CMCC other Approval
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
Yesfor email agreement
for email agreement No    
R5‑253916 Update NR band and CADC configs status in ICS Annex B CMCC CR Agreement
5.4.2TS 38.508-2
Yes
Yes
agreed No    
R5‑253917 SR Rel-18 NR_IDC_enh-UEConTest after RAN5#108 CMCC WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253918 WP Rel-18 NR_IDC_enh-UEConTest after RAN5#108 CMCC Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253919 Addition of new test 8.1.5.10.11 for R18 IDC enhancement CMCC CR Agreement
6.3.20.4TS 38.523-1
Yes
Yesr3
revised No R5‑255017  
R5‑253920 Addition of applicability for new NR IDC TC 8.1.5.10.11 and 8.1.5.10.12 CMCC CR Agreement
6.3.20.5TS 38.523-2
Yes
Yesr1
revised No R5‑255019  
R5‑253921 Addition of new test 8.1.5.10.12 for R18 IDC enhancement CMCC CR Agreement
6.3.20.4TS 38.523-1
Yes
Yesr3
revised No R5‑255018  
R5‑253922 Update of TC 8.2.6.5.1 for R18 IDC enhancement CMCC CR Agreement
6.3.20.4TS 38.523-1
Yes
Yes
agreed No    
R5‑253923 Update of test case 8.1.6.1.2.14 for SON_MDT CMCC CR Agreement
6.4.4.4.1.6RRC SON and MDT support for NR (clause 8.1.6)
Yes
Yesr2
revised No R5‑255014  
R5‑253924 Addition of new test case 8.1.6.1.2.14A for SONMDT CMCC CR Agreement
6.4.4.4.1.6RRC SON and MDT support for NR (clause 8.1.6)
Yes
Yesr1
revised Yes R5‑255015  
R5‑253925 Addition of applicability for new SONMDT TC 8.1.6.1.2.14A CMCC CR Agreement
6.4.5TS 38.523-2
Yes
Yesreplaced by R5-254949 r1
revised Yes R5‑255016  
R5‑253926 Update on AI/ML Progress in 3GPP Core Groups CMCC, Lenovo discussion Endorsement
4.2.3AI/ML Testability & Interoperability
Yes
YesKeysight Spain: RAN2 is agreeing running CRs.
noted No    
R5‑253927 Discussion of A-IoT Device Conformance Testing CMCC, Huawei discussion Endorsement
4.2.15GS
Yes
Yesr1
revised No R5‑255095  
R5‑253928 New WID on Conformance - Solutions for Ambient IoT (Internet of Things) in NR CMCC, Huawei WID new Information
7.5.1Final version of Work Item Proposals
Yes
Yesr2
revised No R5‑255098  
R5‑253929 Update applicability for test cases 8.3 and 8.6 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No    
R5‑253930 Update applicability for test cases 8.8 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No    
R5‑253931 Update applicability for test cases 8.26 and 8.28 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No    
R5‑253932 Update applicability for test cases 8.31 and 8.32 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No    
R5‑253933 Update applicability for test cases 8.36, 8.37, 8.38 and 8.41 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No    
R5‑253934 Updates of transmit part for PC2 n2 and PC2 n66 Verizon CR Agreement
5.3.9.3.1Tx Requirements (Clause 6)
Yes
Yesmonth r1
revised No R5‑255247  
R5‑253935 Updates of transmit part for PC2 n5 Verizon Finland CR Agreement
5.3.36.3.1Tx Requirements (Clause 6)
Yes
Yesmonth r1
revised No R5‑255252  
R5‑253936 Updates of Reference Sensitivity requirements for PC2 n2 Verizon CR Agreement
5.3.9.3.2Rx Requirements (Clause 7)
Yes
Yesmonth r1
revised No R5‑255248  
R5‑253937 Updates of Reference Sensitivity requirements for PC2 n5 Verizon Finland CR Agreement
5.3.36.3.2Rx Requirements (Clause 7)
Yes
Yesmonth r1
revised No R5‑255253  
R5‑253938 Updates for PC2 n5 Verizon CR Agreement
5.3.36.2TS 38.508-2
Yes
Yesmonth r1
revised No R5‑255212  
R5‑253939 PRD21 CDS: PC2 single band n2 n66 n5 Verizon Finland other  
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
No
reserved No    
R5‑253940 Updates for UL n77 high power support on a few 3 TDD DL combos Verizon CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yesmonth +NR_PC2_CA_R17_2BDL_2BUL-UEConTest?? r1
revised No R5‑255268  
R5‑253941 Updates for some combos with UL high power support on n77 Verizon Finland CR Agreement
5.3.10.3.3Clauses 1-5, Annexes
Yes
Yesmonth r1
revised No R5‑255250  
R5‑253942 Updates for a few three band combos with UL CA with PC2 n77 Verizon Finland CR Agreement
5.3.10.2TS 38.508-2
Yes
Yesmonth r1
revised No R5‑255211  
R5‑253943 PRD21 CDS: n77 PC2 PC1.5 missing combos Verizon Finland other  
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
No
reserved No    
R5‑253944 Updates for a few four band combos Verizon CR Agreement
5.3.35.2TS 38.508-2
Yes
Yesmonth r1
revised No R5‑255213  
R5‑253945 Updates for CA_n48(A-B) Verizon Finland CR Agreement
5.3.2.2TS 38.508-2
Yes
Yesmonth r1
revised No R5‑255215  
R5‑253946 PRD21 CDS: Rel-19 BCS4 and 5 combos Verizon Finland other  
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
No
reserved No    
R5‑253947 PRD21 CDS: 4T related combos mixed BCS mixed release Verizon Finland other  
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
No
reserved No    
R5‑253948 Confirmation of the 38.306 IE for the number of Tx ports capabiliy required in PMI test cases in 38.521-4 CAICT CR Agreement
5.4.2TS 38.508-2
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r1
revised No R5‑255405  
R5‑253949 Introduction of new test case 6.3.1.1.2 1Rx FDD Single PMI with 4TX TypeI-SinglePanel Codebook for eRedCap CAICT CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r2
revised No R5‑2055386  
R5‑253950 Introduction of new test case 6.3.1.2.2 1Rx TDD Single PMI with 4TX TypeI-SinglePanel Codebook for eRedCap CAICT CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r1
revised No R5‑255301  
R5‑253951 Introduction of new test case 6.3.2.1.10 2Rx FDD Single PMI with 4TX TypeI-SinglePanel Codebook for eRedCap CAICT CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r1
revised No R5‑255302  
R5‑253952 Introduction of new test case 6.3.2.2.10 2Rx TDD Single PMI with 4TX TypeI-SinglePanel Codebook for eRedCap CAICT CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r1
revised No R5‑255303  
R5‑253953 Introduction of measurement uncertainty and test tolerance for eRedCap PMI test cases CAICT CR Agreement
5.3.15.4.4Clauses 1-4, Annexes
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r1
revised No R5‑255304  
R5‑253954 Correction of RedCap PMI test cases CAICT CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r1
revised No R5‑255307  
R5‑253955 Correction of SA and NSA 2Rx PMI with 4TX test cases CAICT CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r1
revised No R5‑255308  
R5‑253956 Introduction of Applicabilities for eRedCap PMI test cases CAICT CR Agreement
5.3.15.5TS 38.522
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r1
revised No R5‑255305  
R5‑253957 Confirmation of Applicability for PMI test cases CAICT CR Agreement
5.4.9TS 38.522
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r1
revised No R5‑255406  
R5‑253958 Introduction of MU and TT for test case 19.2.3.3.1 NR SA FR1-FR1 RRC connection release with Redirection CAICT CR Agreement
5.3.13.6TS 38.533
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r1
revised No R5‑255324  
R5‑253959 TT analysis for new test case 19.2.3.3.1 NR SA FR1-FR1 RRC connection release with Redirection CAICT CR Agreement
5.3.13.7TR 38.903 (NR MU & TT analyses)
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set r1
revised No R5‑255326  
R5‑253960 New WID on UE Conformance - Channel raster enhancement China Telecom, Huawei WID new Endorsement
4.1New Work Item proposals - for intro only
Yes
Yes
revised No R5‑254909  
R5‑253961 Correction of test frequencies for Band n254 China Telecom CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
Yes
YesR&S is OK with the CR , delegate not present
agreed No    
R5‑253962 Addition of new test case 6.5.3.12 SNPN Selection in Manual Mode / Automatically Selecting equivalent SNPN China Telecom CR Agreement
6.3.21.3TS 38.523-1
Yes
Yesr2
revised No R5‑255001  
R5‑253963 Addition of new test case 6.3.3.16 Steering of Roaming in SNPN / After registration / Security check successful / Access for localized services in SNPN China Telecom CR Agreement
6.3.21.3TS 38.523-1
Yes
YesTC .16?? r2
revised No R5‑255002  
R5‑253964 WP UE Conformance – Rel-18 High Power UE for NR CA and DC; and NR and LTE DC Configurations China Telecom Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253965 SR UE Conformance – Rel-18 High Power UE for NR CA and DC; and NR and LTE DC Configurations China Telecom WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253966 WP on UE Conformance – Enhanced support of Non-Public Networks Phase 2 China Telecom Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253967 SR on UE Conformance – Enhanced support of Non-Public Networks Phase 2 China Telecom WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253968 WP on UE Conformance – Rel-18 LTE CA Configurations China Telecom Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes->WP!
noted No    
R5‑253969 SR on UE Conformance – Rel-18 LTE CA Configurations China Telecom WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑253970 Correction to NR NTN Test Case 7.1.2.2.5a Anritsu EMEA Ltd CR Agreement
6.3.3.4TS 38.523-1
Yes
Yes
agreed No    
R5‑253971 MCC TF160 Status Report MCC TF160 report Approval
2.1Live Reports
Yes
Yes
revised No R5‑254906  
R5‑253972 Corrections to XR Enh test case 7.1.1.3.18 MCC TF160 CR Agreement
6.3.10.4TS 38.523-1
Yes
Yes
agreed No    
R5‑253973 Corrections to XR Enh test case 7.1.1.3.19 MCC TF160 CR Agreement
6.3.10.4TS 38.523-1
Yes
Yes
agreed No    
R5‑253974 LTE Band 106: Test Model updates MCC TF160 CR Agreement
6.3.11.4TS 36.523-3
Yes
Yes
agreed No    
R5‑253975 Corrections to NES test case 6.1.2.28 MCC TF160 CR Agreement
6.3.13.3TS 38.523-1
Yes
Yes
agreed No    
R5‑253976 NR POS enh. Phase2: Initial Test Model MCC TF160 CR Agreement
6.3.22.4TS 37.571-4
Yes
Yes
agreed No    
R5‑253977 Editorial correction of clause 5.4.4.3 MCC TF160 CR Agreement
6.3.24.1TS 37.579-1
Yes
Yesblock agreed on Thu
agreed No    
R5‑253978 Correction of test case 11.13 MCC TF160 CR Agreement
6.3.29.13TS 34.229-5
Yes
Yesdeferred. r2
revised No R5‑255087  
R5‑253979 Correction of test case 11.14 MCC TF160 CR Agreement
6.3.29.13TS 34.229-5
Yes
YesDeferred.
postponed No    
R5‑253980 Correction of test case 11.18 MCC TF160 CR Agreement
6.3.29.13TS 34.229-5
Yes
Yesclashing with R5-254183. Deferred. r2
revised No R5‑255088  
R5‑253981 Correction to NR NTN TC 6.7.1.2 MCC TF160 CR Agreement
6.3.3.4TS 38.523-1
Yes
Yes
agreed No    
R5‑253982 NR ATG: Initial Test Model MCC TF160 CR Agreement
6.3.7.5TS 38.523-3
Yes
Yes
agreed No    
R5‑253983 NR FR1 less than 5MHz BW: Test Model updates MCC TF160 CR Agreement
6.3.8.5TS 38.523-3
Yes
Yes
agreed No    
R5‑253984 Corrections for SIP registration MCC TF160 CR Agreement
6.4.1.1Generic Procedures and Test Procedures (Clauses 4.5, 4.5A & 4.9)
Yes
Yes
agreed No    
R5‑253985 Corrections to clause 4.4A Test states MCC TF160 CR Agreement
6.4.1.5Other clauses, Annexes
Yes
Yes
agreed No    
R5‑253986 Renaming mnemonic of SRS partial sounding PICS MCC TF160 CR Agreement
6.4.2TS 38.508-2
Yes
Yes
agreed No    
R5‑253987 Updates to NR RRC test case 8.1.5.1.1 MCC TF160 CR Agreement
6.4.4.4.1.5RRC Others (clause 8.1.5)
Yes
Yesdeferred. r1
revised No R5‑255069  
R5‑253988 Updates to EN-DC RRC test case 8.2.1.1.1 MCC TF160 CR Agreement
6.4.4.4.2.1RRC UE Capability / Others (clause 8.2.1)
Yes
Yesr1
revised No R5‑255070  
R5‑253989 Updates to NE-DC RRC test case 8.2.1.1.2 MCC TF160 CR Agreement
6.4.4.4.2.1RRC UE Capability / Others (clause 8.2.1)
Yes
Yesr1
revised No R5‑255071  
R5‑253990 Editorial corrections to 5GMM initial registration test cases MCC TF160 CR Agreement
6.4.4.5.3MM Registration & De-registration (clauses 9.1.5 & 9.1.6)
Yes
Yes
agreed No    
R5‑253991 Corrections to references in Table 4.2-1 for NR NTN enhancements MCC TF160 CR Agreement
6.3.25.5TS 38.523-2
Yes
Yes
agreed No    
R5‑253992 Routine maintenance for TS 38.523-3 MCC TF160, Nokia CR Agreement
6.4.6TS 38.523-3
Yes
Yesr2
revised No R5‑255056  
R5‑253993 Correction of reference packet filters in clause 6.6.2 MCC TF160 CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
Yes
agreed No    
R5‑253994 Correction to RRCEarlyDataComplete-NB message MCC TF160 CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
Yes
agreed No    
R5‑253995 Corrections for SIP registration MCC TF160 CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
Yes
agreed No    
R5‑253996 Corrections to NB-IoT CP PUR test case 22.1.5 MCC TF160 CR Agreement
6.5.3.11Others (TS 36.523-1 clauses not covered by other AIs under AI 6.5.3, e.g. eMBMS, Home (e)NB, MBMS in LTE, D2D, SC-PTM, NB-IoT, CIoT...)
Yes
Yesfirst agreed, then deferred. r1
revised No R5‑255053  
R5‑253997 Corrections to NB-IoT UP PUR test case 22.1.6 MCC TF 160 CR Agreement
6.5.3.11Others (TS 36.523-1 clauses not covered by other AIs under AI 6.5.3, e.g. eMBMS, Home (e)NB, MBMS in LTE, D2D, SC-PTM, NB-IoT, CIoT...)
Yes
Yescl. aff. r1
revised No R5‑254929  
R5‑253998 Correction to NB-IoT ECR capability MCC TF160 CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yesr1
revised No R5‑255063  
R5‑253999 Corrections to references in Table 4-1a MCC TF160 CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yeschanges to be merged into a revision of R5-254504.
withdrawn Yes    
R5‑254000 Routine maintenance for TS 36.523-3 MCC TF160 CR Agreement
6.5.5Routine Maintenance for TS 36.523-3
Yes
Yesr1
revised No R5‑255057  
R5‑254001 Correction of A.3.1 MCC TF160 CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
agreed No    
R5‑254002 Correction of test case 17.19 MCC TF160 CR Agreement
6.6.6.1TS 34.229-1
Yes
Yesworking assumption is that red/1000 is not mandated in the 1st SDP offer from the UE for RTT. SA4 spec is ambiguous on this so RAN5 must allow the additional behaviour. Deferred. r3
revised No R5‑255080  
R5‑254003 Correction of test case 17.20 MCC TF160 CR Agreement
6.6.6.1TS 34.229-1
Yes
Yesfirst agreed, then revised. r1
revised No R5‑255079  
R5‑254004 Correction of test case 19.1.7 MCC TF160 CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
withdrawn Yes    
R5‑254005 Correction of test case 19.1.8 MCC TF160 CR Agreement
6.6.6.1TS 34.229-1
Yes
YesDeferred. r2
revised No R5‑255081  
R5‑254006 Correction of C.44 MCC TF160 CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
agreed No    
R5‑254007 Correction of C.45 MCC TF160 CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
agreed No    
R5‑254008 Extension and correction of feature tags in default message contents MCC TF160, Ericsson, Qualcomm CR Agreement
6.6.6.1TS 34.229-1
Yes
Yesclashes with many other CRs. r2
revised No R5‑255082  
R5‑254009 Correction of procedure A.15.1a MCC TF160 CR Agreement
6.6.6.5TS 34.229-5
Yes
Yes
agreed No    
R5‑254010 Correction of test case 10.17 MCC TF160 CR Agreement
6.6.6.5TS 34.229-5
Yes
YesETSI MCC: maybe better not reuse voided test steps. Ericsson: Annex A.29? r2
revised No R5‑255084  
R5‑254011 Correction of test case 7.20 MCC TF160 CR Agreement
6.6.6.5TS 34.229-5
Yes
Yes
agreed No    
R5‑254012 Correction of test case 7.21 MCC TF160 CR Agreement
6.6.6.5TS 34.229-5
Yes
Yes
agreed No    
R5‑254013 Correction of test case 7.22 MCC TF160 CR Agreement
6.6.6.5TS 34.229-5
Yes
Yes
agreed No    
R5‑254014 Correction of test case 7.35 MCC TF160 CR Agreement
6.6.6.5TS 34.229-5
Yes
Yesr1
revised No R5‑255085  
R5‑254015 Correction of test case 7.36 MCC TF160 CR Agreement
6.6.6.5TS 34.229-5
Yes
YesDeferred. r1
revised No R5‑255086  
R5‑254016 Correction of clause 5.3.36 MCC TF160 CR Agreement
6.6.9.1TS 37.579-1
Yes
Yesblock agreed on Thu
agreed No    
R5‑254017 Correction of MCS configuration management documents in 5.5.8 MCC TF160 CR Agreement
6.6.9.1TS 37.579-1
Yes
Yesblock agreed on Thu
agreed No    
R5‑254018 Misc. updates to test case applicability tables MCC TF160 CR Agreement
6.6.9.3TS 37.579-4
Yes
Yesblock agreed on Thu
agreed No    
R5‑254019 Routine maintenance for TS 37.579-5 MCC TF160 CR Agreement
6.6.9.4TS 37.579-5
Yes
Yesblock agreed on Thu
agreed No    
R5‑254020 Editorial corrections of MCVideo test cases MCC TF160 CR Agreement
6.6.9.5TS 37.579-6
Yes
Yesblock agreed on Thu
agreed No    
R5‑254021 Correction to NR NTN Test Case 6.7.1.1 Anritsu EMEA Ltd CR Agreement
6.3.3.4TS 38.523-1
Yes
Yes
agreed No    
R5‑254022 Update of UE position requirements for ATG testing ZTE Corporation, CMCC, MCC TF160 CR Agreement
6.3.7.1TS 38.508-1
Yes
Yes
agreed No    
R5‑254023 Corrections to ATG related system information combination ZTE Corporation, CMCC, MCC TF160 CR Agreement
6.3.7.1TS 38.508-1
Yes
Yes
agreed No    
R5‑254024 Update to the IE ReferenceLocation ZTE Corporation, CMCC, MCC TF160, QUALCOMM JAPAN LLC. CR Agreement
6.3.7.1TS 38.508-1
Yes
Yesr1 contains also merged part for NR_NTN_enh_plus_CT-UEConTest r3
revised No R5‑254988  
R5‑254025 Corrections to ATG TC 8.1.4.4.8 ZTE Corporation, CMCC, MCC TF160 CR Agreement
6.3.7.3TS 38.523-1
Yes
Yesr1
revised No R5‑254989  
R5‑254026 Corrections to ATG TC 7.1.1.10.5 ZTE Corporation, CMCC, MCC TF160 CR Agreement
6.3.7.3TS 38.523-1
Yes
Yesr1
revised No R5‑254990  
R5‑254027 Corrections to ATG TCs 6.8.1.x ZTE Corporation, CMCC, MCC TF160 CR Agreement
6.3.7.3TS 38.523-1
Yes
Yes
agreed No    
R5‑254028 Addition of new ATG TC 8.1.4.4.10 ZTE Corporation, Tejet, SRTC CR Agreement
6.3.7.3TS 38.523-1
Yes
Yes
agreed No    
R5‑254029 Addition of applicability for new ATG TC ZTE Corporation, Tejet, SRTC CR Agreement
6.3.7.4TS 38.523-2
Yes
Yes
agreed No    
R5‑254030 Correction to RRC NR NTN test cases 8.1.5.14.1 Anritsu EMEA Ltd CR Agreement
6.3.3.4TS 38.523-1
Yes
Yesr1
revised No R5‑255092  
R5‑254031 New testcase - 10.6.1.2 Nokia CR Agreement
6.3.32.3TS 38.523-1
Yes
YesCR coversheet: Addition of MA PDU session establishment / ATSSS / UE establishing a PDN connection over untrusted non-3GPP access network as a user-plane resource of an already established MA PDU session test case ---- Clauses affected ----: CR cover sheet: None of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set for TS 38.523-1" r1
revised No R5‑255051  
R5‑254032 Applicability of testcase -10.6.1.2 Nokia CR Agreement
6.3.32.4TS 38.523-2
Yes
YesNone of the CR impact tick boxes for UICC apps, ME, RAN or CN shall be set for TS 38.523-2 r1
revised No R5‑255052  
R5‑254033 Void applicability for test case 11.1.1 Ericsson CR Agreement
6.4.5TS 38.523-2
Yes
Yes
withdrawn Yes    
R5‑254034 Void applicability for test case 11.1.2 Ericsson CR Agreement
6.4.5TS 38.523-2
Yes
Yes
withdrawn Yes    
R5‑254035 Void applicability for test case 11.1.3 Ericsson CR Agreement
6.4.5TS 38.523-2
Yes
Yes
withdrawn Yes    
R5‑254036 Void applicability for test case 11.1.5 Ericsson CR Agreement
6.4.5TS 38.523-2
Yes
Yes
withdrawn Yes    
R5‑254037 Void applicability for test case 11.1.6 Ericsson CR Agreement
6.4.5TS 38.523-2
Yes
Yes
withdrawn Yes    
R5‑254038 Correction to MAC test case 7.1.1.6.8 for 3MHz Bandwidth Anritsu EMEA Ltd CR Agreement
6.3.8.3TS 38.523-1
Yes
Yesthis TC belongs to the open WI "NR_XR_enh_plus_CT1-UEConTest" cl. aff. R5! r2
revised No R5‑254991  
R5‑254039 Correction to LTE DRX testcase 7.1.6.2 for CAT-M1 Anritsu EMEA Ltd CR Agreement
6.5.3.2.1MAC
Yes
YesTF160 manager: where is the statement in the core spec? r1
revised No R5‑255054  
R5‑254040 Correction to MAC test case 7.1.1.6.7 for 3MHz Bandwidth Anritsu EMEA Ltd CR Agreement
6.3.8.3TS 38.523-1
Yes
Yes
withdrawn Yes    
R5‑254041 Correction to MAC test case 7.1.1.6.6 for 3MHz Bandwidth Anritsu EMEA Ltd CR Agreement
6.3.8.3TS 38.523-1
Yes
Yesthis TC belongs to the open WI "NR_XR_enh_plus_CT1-UEConTest" r1
revised No R5‑254992  
R5‑254042 Correction to MAC test case 7.1.1.6.2 for 3MHz Bandwidth Anritsu EMEA Ltd CR Agreement
6.3.8.3TS 38.523-1
Yes
Yesr2
revised No R5‑254996  
R5‑254043 UE Conformance - core and perf requirements for IoT NTN TDD mode Iridium Satellite LLC WID new Endorsement
4.1New Work Item proposals - for intro only
Yes
YesRAN5 Chair: % is not yet enough. Why 36.509 NTN is needed? Qualcomm: TS 36.521-1 shall not be applicable. But -4!
revised No R5‑254914  
R5‑254044 On Re-Positioning Concept for 3 AoA FR2 RRM TCs Keysight Technologies UK Ltd discussion Endorsement
5.4.20Discussion Papers, Work Plan, TC lists
Yes
Yes"CR to 38.903 in R5-254045 8/25: Moderator (Apple) - Concerns raised by R&S that proposals might be premature. Keysight indicated generally OK to defer Proposals for now. Discussion ongoing. Discussion paper will be suggested to be noted in 08/26 FR2 MU status update pending progress in discussion. 8/26 Moderator (Apple) - Discussion paper can be noted. Proposals 1 and 2 NOT endorsed."
noted No    
R5‑254045 Clarification on the applicability of re-positioning approach for QoQZ MU Keysight Technologies UK Ltd CR Agreement
5.4.18TR 38.903 (NR MU & TT analyses)
Yes
Yesr1
revised No R5‑255345  
R5‑254046 CR to update acronyms and symbols Keysight Technologies UK Ltd CR Agreement
5.4.18TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254047 Correction of Antenna Assumptions in Annex M Keysight Technologies UK Ltd CR Agreement
5.4.5.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254048 On Spherical Coverage Test Case for PC6 UEs (HST) Keysight Technologies UK Ltd discussion Endorsement
5.4.20Discussion Papers, Work Plan, TC lists
Yes
Yes"8/25: Moderator (Apple) - No comments received as of 08/25 PM coffee break. Proposals 1-4 will be suggested to be endorsed in 08/26 FR2 MU status Update if no further comments/concerns received. 8/26 Moderator (Apple) - Discussion paper can be noted and Proposal 1,2,3,4 can be endorsed"
noted No    
R5‑254049 Correction of Test Equipment Reference Keysight Technologies UK Ltd, Spirent Communications, ETS-Lindgren CR Agreement
5.6.15TS 37.544
Yes
Yes*.doc->x r2
revised No R5‑255349  
R5‑254050 Correction of Test Equipment Reference Keysight Technologies UK Ltd, Spirent Communications, ETS-Lindgren CR Agreement
5.4.11TS 38.551
Yes
Yes
agreed No    
R5‑254051 Updates for BCS4 and 5 introduced additional ref sense requirements Verizon Finland CR Agreement
5.3.35.3.2Rx Requirements (Clause 7)
Yes
Yesmonth r2
revised No R5‑255236  
R5‑254052 Test points updates for BCS4 and 5 introduced additional ref sense requirements Verizon CR Agreement
5.3.35.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yesmonth r1
revised No R5‑255235  
R5‑254053 Addition of ATG random access test case 19.2.3.2.1 ZTE Corporation CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254054 Addition of ATG random access test case 19.2.3.2.2 ZTE Corporation CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254055 Addition of ATG random access test case 19.2.3.2.3 ZTE Corporation CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254056 Addition of ATG random access test case 19.2.3.2.4 ZTE Corporation CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254057 Addition of ATG transmit timing test case 19.3.1.1 ZTE Corporation CR Agreement
5.3.13.6TS 38.533
Yes
Yesr1
revised No R5‑255312  
R5‑254058 Addition of ATG timing advance test case 19.3.3.1 ZTE Corporation CR Agreement
5.3.13.6TS 38.533
Yes
Yesr1
revised No R5‑255313  
R5‑254059 Addition of cell configuration for ATG RRM test cases ZTE Corporation CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254060 Update to RRC IEs for Further NR mobility enhancements MediaTek Inc. CR Agreement
6.3.23.1TS 38.508-1
Yes
Yesr1
revised No R5‑255034  
R5‑254061 NR NTN power control test cases definition Keysight Technologies UK Ltd CR Agreement
5.3.4.4TS 38.521-5
Yes
Yes
withdrawn Yes    
R5‑254062 IoT NTN - Test frequencies definition update for bands 254 and bands 255 Keysight Technologies UK Ltd CR Agreement
5.5.1.1TS 36.508
Yes
Yesr1
revised No R5‑255282  
R5‑254063 Editorial correction in clause 5.2B Keysight Technologies UK Ltd CR Agreement
5.5.1.5TS 36.521-4
Yes
Yes
agreed No    
R5‑254064 On Out-of-Band Blocking test optimization Keysight Technologies UK Ltd discussion Endorsement
5.4.20Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No    
R5‑254065 Discussion on FR1 MUs for 4Tx test cases Keysight Technologies UK Ltd discussion Endorsement
5.3.19.10Discussion Papers, Work Plan, TC lists
Yes
Yesnoted all prop except 9 and 13 are implemented as is in cr's
noted No    
R5‑254066 MU corrections for 2Tx tests Keysight Technologies UK Ltd CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254067 Discussion on MU and TT for ATG RF testing Keysight Technologies UK Ltd discussion Endorsement
5.3.13.9Discussion Papers, Work Plan, TC lists
Yes
Yes"prop9 implemented in 4068 prop1-8 implemented in CR4069/70"
noted No    
R5‑254068 ATG manufacturer declaration on antenna ports Keysight Technologies UK Ltd CR Agreement
5.3.13.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254069 ATG Tx Tests - Corrections and updates Keysight Technologies UK Ltd, CMCC CR Agreement
5.3.13.3.1Tx Requirements (Clause 6)
Yes
Yesresolve overlap with R5-253881 (CMCC) that has been withdrawn. r1
revised No R5‑255243  
R5‑254070 ATG Tests - MU and TT updates in Annex F Keysight Technologies UK Ltd CR Agreement
5.3.13.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254071 Discussion on FR1 MUs up to 7.125GHz Keysight Technologies UK Ltd discussion Endorsement
5.4.20Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No    
R5‑254072 FR1 MUs up to 7.125GHz - RF single carrier UL SISO Tx tests update Keysight Technologies UK Ltd CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255378  
R5‑254073 FR1 MUs up to 7.125GHz - RF single carrier UL SISO Rx tests update Keysight Technologies UK Ltd CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255379  
R5‑254074 FR1 MUs up to 7.125GHz - RF single carrier UL SISO tests - MU and TT update in annex F Keysight Technologies UK Ltd CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yesr1
revised No R5‑255380  
R5‑254075 Clarifications for ULFPTx in UL MIMO UTRA ACLR test Keysight Technologies UK Ltd CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
withdrawn Yes    
R5‑254076 3CC intraband non-contiguous updates Keysight Technologies UK Ltd CR Agreement
5.3.2.3.2Rx Requirements (Clause 7)
Yes
Yesresolve overlap with R5-254382 (R&S) by removing in this revision the changes in sections 7.6A.4.2.5.x and 7.8A.2.2.5.x. r2
revised No R5‑255377  
R5‑254077 Corrected applicability for CA_n71A-n77A Test ID 1 in test 7.3A.1_1 Keysight Technologies UK Ltd CR Agreement
5.3.2.3.2Rx Requirements (Clause 7)
Yes
Yes
withdrawn Yes    
R5‑254078 REFSENS SA - PC2 test points corrections for CA_n3A-n78A Keysight Technologies UK Ltd CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yes
withdrawn Yes    
R5‑254079 FR1 ACS CA tests - exceptions for combos including both n48A and n77A Keysight Technologies UK Ltd CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254080 Frequency error CA tests - optimization for intra-band contiguous Keysight Technologies UK Ltd CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254081 Test case 6.3C.3.2 update according to TP analysis update Keysight Technologies UK Ltd CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255352  
R5‑254082 TP analysis update for test case 6.3C.3.2 Keysight Technologies UK Ltd CR Agreement
5.4.19TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254083 REFSENS NSA - Test points corrections for DC_3A_n77A and DC_3A_n78A Keysight Technologies UK Ltd CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yes
withdrawn Yes    
R5‑254084 Editorial - References corrections in test case 7.6B.3.3 Keysight Technologies UK Ltd CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254085 PRD21 CDS: NR FR1 FDD bands n110 Nokia WI summary Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
Yeslack of Rel-19 in CDS template
withdrawn Yes    
R5‑254086 Addition of A-MPR test point analysis for band n110 NS_06 Nokia CR Agreement
5.3.40.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254087 Introduction of test channel bandwidths and test frequencies for band n110 Nokia CR Agreement
5.3.40.1.1Test frequencies (Clause 4.3.1)
Yes
Yesr2
revised No R5‑255372  
R5‑254088 Signalling test frequencies for band n110 Nokia CR Agreement
6.3.35.1TS 38.508-1
Yes
Yes
agreed No    
R5‑254089 Demodulation test frequencies for band n110 Nokia CR Agreement
5.3.40.1.2Test environment for RF (Clauses 5)
Yes
Yesr2
revised No R5‑255373  
R5‑254090 Introduction of band n110 for physical layer baseline implementation capabilities Nokia CR Agreement
5.3.40.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254091 Introduction of band n110 to NR band group for FR1 Nokia CR Agreement
5.3.40.7TS 38.533
Yes
Yes
agreed No    
R5‑254092 Adding transmitter requirements for band n110 Nokia CR Agreement
5.3.40.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254093 Adding receiver requirements for band n110 Nokia CR Agreement
5.3.40.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254094 Addition of protocol test execution guideline for band n110 Nokia CR Agreement
6.3.35.3TS 38.523-3
Yes
YesContent of this CR is merged into R5-253992r1 from MCC TF160.
withdrawn Yes    
R5‑254095 Void EPS fallback test case 11.1.1 Ericsson CR Agreement
6.4.4.11.1EPS Fallback (clause 11.1)
Yes
Yes
withdrawn Yes    
R5‑254096 Void EPS fallback test case 11.1.2 Ericsson CR Agreement
6.4.4.11.1EPS Fallback (clause 11.1)
Yes
Yes
withdrawn Yes    
R5‑254097 Void EPS fallback test case 11.1.3 Ericsson CR Agreement
6.4.4.11.1EPS Fallback (clause 11.1)
Yes
Yes
withdrawn Yes    
R5‑254098 Void EPS fallback test case 11.1.5 Ericsson CR Agreement
6.4.4.11.1EPS Fallback (clause 11.1)
Yes
YesTdoc# r1
revised No R5‑254937  
R5‑254099 Void EPS fallback test case 11.1.6 Ericsson CR Agreement
6.4.4.11.1EPS Fallback (clause 11.1)
Yes
Yes
withdrawn Yes    
R5‑254100 Correction to MAC test case 7.1.1.8.1 for 3MHz Bandwidth Anritsu EMEA Ltd CR Agreement
6.3.8.3TS 38.523-1
Yes
Yesr1
revised No R5‑254997  
R5‑254101 NG.114 and 5GS voice applicability Ericsson discussion Endorsement
6.6.6.6Discussion Papers, Work Plan, TC lists
Yes
YesDiscussion with Qualcomm. Conclusion: proposal to align 5GS voice call TCs with NG.114 accepted in principle. Proposal to void TCs 11.1.1. and 11.1.3 not accepted. RAN5 will wait for the adoption of equivalent NG.114 compliant TCs to be considered by certification organizations. Prpopsal to void .2 .5 .6 not accepted as commercial deplayment without N.26 interface support is a requirement now (EU operators). RAN5 will consider this as deviation from NG.114.
noted No    
R5‑254102 SON/MDT IDC test for band n41 CMCC discussion Endorsement
6.4.7Discussion Papers, Work Plan, TC lists
Yes
YesCATT: the signalling procedures are the same, even if the triggers are different. Noted, proposal is accepted. Wait for corresponding CRs.
noted No    
R5‑254103 Adding test applicability for new 4Tx test cases Huawei, HiSilicon CR Agreement
5.3.19.6TS 38.522
Yes
Yesr1
revised No R5‑255336  
R5‑254104 Update USIM configuration Huawei, HiSilicon CR Agreement
6.4.1.4Test environment for SIG (Clause 6)
Yes
YesQualcomm: this should rather go into the default.
agreed No    
R5‑254105 Editorial updates on 36523 draft IETF reference - 15.11 and 15.12 Huawei, HiSilicon CR Agreement
6.5.3.11Others (TS 36.523-1 clauses not covered by other AIs under AI 6.5.3, e.g. eMBMS, Home (e)NB, MBMS in LTE, D2D, SC-PTM, NB-IoT, CIoT...)
Yes
Yes
agreed No    
R5‑254106 Update the feMIMO test case 7.1.1.3.17.X - Multi-TRP Huawei, HiSilicon CR Agreement
6.4.4.3.1.2MAC
Yes
Yesr1
revised No R5‑254934  
R5‑254107 Adding additional information of applicability for feMIMO test case 7.1.1.3.17.X - Multi-TRP Huawei, HiSilicon CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No    
R5‑254108 Update IDLE mode test case 6.1.2.3a to test eRedCap UE Huawei, HiSilicon, China Unicom CR Agreement
6.3.9.3TS 38.523-1
Yes
YesQualcomm: there was no consensus to submit such test cases. We need a discussion paper first. TF160 manager: China Unicom asked operators to collect data about the deployment.
not pursued No    
R5‑254109 Update MAC test case 7.1.1.3.4 and 7.1.1.9.1 to test eRedCap UE Huawei, HiSilicon, China Unicom CR Agreement
6.3.9.3TS 38.523-1
Yes
Yes
not pursued No    
R5‑254110 Update PDCP test case 7.1.3.4.1 and 7.1.3.5.4 to test eRedCap UE Huawei, HiSilicon, China Unicom CR Agreement
6.3.9.3TS 38.523-1
Yes
Yes
not pursued No    
R5‑254111 Update RLC test case 7.1.2.3.x to test eRedCap UE Huawei, HiSilicon, China Unicom CR Agreement
6.3.9.3TS 38.523-1
Yes
Yes
not pursued No    
R5‑254112 Update RRC test case 8.1.5.8.1 and 8.1.5.2.2 to test eRedCap UE Huawei, HiSilicon, China Unicom CR Agreement
6.3.9.3TS 38.523-1
Yes
Yes
not pursued No    
R5‑254113 Update TBsize test case 7.1.1.4.x.x to test eRedCap UE Huawei, HiSilicon, China Unicom CR Agreement
6.3.9.3TS 38.523-1
Yes
Yes
not pursued No    
R5‑254114 Update eRedCap UE Test applicability for Legacy test cases Huawei, HiSilicon, China Unicom CR Agreement
6.3.3.1TS 38.508-1
Yes
Yesr1
revised No R5‑254951  
R5‑254115 Addition of new LTE IMS data channel test case 12.36 - MO Video call with precondition and BDC failure Huawei, HiSilicon CR Agreement
6.3.28.5TS 34.229-1
Yes
Yesr2
revised No R5‑254982  
R5‑254116 Addition of new LTE IMS data channel test case 12.37 - MO Video call with precondition and BDC success Huawei, HiSilicon CR Agreement
6.3.28.5TS 34.229-1
Yes
Yesr1
revised No R5‑254983  
R5‑254117 Addition of new LTE IMS data channel test case 12.38 - MT Video call with precondition and BDC success Huawei, HiSilicon CR Agreement
6.3.28.5TS 34.229-1
Yes
Yes
agreed No    
R5‑254118 Addition of new NR IMS data channel test case 7.43 - MO Video call with precondition and BDC failure Huawei, HiSilicon CR Agreement
6.3.28.8TS 34.229-5
Yes
Yesr1
revised No R5‑254984  
R5‑254119 Addition of new NR IMS data channel test case 7.44 - MO Video call with precondition and BDC success Huawei, HiSilicon CR Agreement
6.3.28.8TS 34.229-5
Yes
YesETSI MCC: table renumbering needed
revised No R5‑254985  
R5‑254120 Addition of new NR IMS data channel test case 7.45 - MO Video call with precondition and BDC success Huawei, HiSilicon CR Agreement
6.3.28.8TS 34.229-5
Yes
Yesreissued as R5-254903 because of title change MO->MT
withdrawn Yes    
R5‑254121 Update NR IMS data channel test case 7.37 - 7.42 Huawei, HiSilicon CR Agreement
6.3.28.8TS 34.229-5
Yes
Yes
agreed No    
R5‑254122 Adding test applicability for new LTE IMS data channel test cases Huawei, HiSilicon, MediaTek Inc. CR Agreement
6.3.28.6TS 34.229-2
Yes
Yes
agreed No    
R5‑254123 Adding test applicability for new NR IMS data channel test cases Huawei, HiSilicon, MediaTek Inc. CR Agreement
6.3.28.6TS 34.229-2
Yes
Yes
agreed No    
R5‑254124 SR of UE Conformance - IMS Data Channel test Huawei, HiSilicon WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254125 WP of UE Conformance - IMS Data Channel test Huawei, HiSilicon Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254126 TS 38.523-1 Tracker status before RAN5-108 Huawei, HiSilicon other Information
6.4.7Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No    
R5‑254127 TS 36.523-1 Tracker status before RAN5-108 Huawei, HiSilicon other Information
6.5.6Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No    
R5‑254128 TS 38.523-1 Tracker status after RAN5-108 Huawei, HiSilicon other Information
7.6Docs still needing agreement/endorsement/approval (e.g. Outgoing LS, Reports, New Specs, Info for certification bodies etc.)
No
Yes
noted No    
R5‑254129 TS 36.523-1 Tracker status after RAN5-108 Huawei, HiSilicon other Information
7.6Docs still needing agreement/endorsement/approval (e.g. Outgoing LS, Reports, New Specs, Info for certification bodies etc.)
No
Yes
noted No    
R5‑254130 New WID on UE Conformance -Low-power wake-up signal and receiver for NR vivo, Apple WID new Endorsement
4.1New Work Item proposals - for intro only
Yes
Yesspec dates need to be fixes r1
revised No R5‑254910  
R5‑254131 Addition of UE maximum output power for new R15 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.4.6.1Tx Requirements (Clause 6)
No
Yes
withdrawn Yes    
R5‑254132 Addition of UE maximum output power for new EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.10.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254133 General updates of TS 38.521-1 clause 5 for R16 CA configurations China Unicom, Keysight Technologies, CMCC, NTT DOCOMO INC., KDDI CR Agreement
5.3.1.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254134 General updates of TS 38.521-1 clause 5 for R17 CA configurations China Unicom, Verizon, Huawei, NTT DOCOMO INC., KDDI CR Agreement
5.3.2.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254135 General updates of TS 38.521-1 clause 5 for R18 CA configurations China Unicom,Verizon,NTT DOCOMO INC. CR Agreement
5.3.12.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254136 General updates of TS 38.521-1 clause 5 for R19 CA configurations China Unicom,Verizon,Huawei CR Agreement
5.3.35.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254137 General updates of clause 5 for R19 new CBW configurations China Unicom,Nokia CR Agreement
5.3.40.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254138 Updated the Test case 14.1.11 in TS 38.533 China Unicom CR Agreement
5.3.30.6TS 38.533
Yes
Yesr1
revised No R5‑255403  
R5‑254139 Updated the Test case 14.1.12 in TS 38.533 China Unicom CR Agreement
5.3.30.6TS 38.533
Yes
Yesr1
revised No R5‑255404  
R5‑254140 Updated Annex E for NR-NTN TC 14.1.11 and TC 14.1.12 in TS 38.533 China Unicom CR Agreement
5.3.30.6TS 38.533
Yes
Yes
agreed No    
R5‑254141 Additional of applicability of RRM TC 14.1.11 and TC 14.1.12 in TS 38.522 China Unicom CR Agreement
5.3.30.5TS 38.522
Yes
Yesr1
revised No R5‑255295  
R5‑254142 Corrections to IoT-NTN RRM test cases Rohde & Schwarz CR Agreement
5.5.1.4TS 36.521-3
Yes
Yes+NTN!! r1
revised No R5‑255361  
R5‑254143 Addition of reference sensitivity TP analysis for new R16 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
withdrawn Yes    
R5‑254144 Correction to PLMN-IdentityInfoList ROHDE & SCHWARZ, MCC TF160 CR Agreement
6.3.3.1TS 38.508-1
Yes
Yes
agreed No    
R5‑254145 Correction to NR5GC RRC testcase 8.1.1.1a.1 ROHDE & SCHWARZ, MediaTek CR Agreement
6.4.4.4.1.1RRC Connection Management Procedures (clause 8.1.1)
Yes
Yes
agreed No    
R5‑254146 Correction to DownlinkConfigCommonSIB ROHDE & SCHWARZ, MediaTek CR Agreement
6.4.1.2Default NG-RAN RRC messages and IEs (Clause 4.6)
Yes
Yes
agreed No    
R5‑254147 Correction to NR5GC RRC testcase 8.1.1.1a.2 ROHDE & SCHWARZ, MediaTek CR Agreement
6.4.4.4.1.1RRC Connection Management Procedures (clause 8.1.1)
Yes
Yes
agreed No    
R5‑254148 Correction to NR5GC eCall over IMS testcase 11.5.4 ROHDE & SCHWARZ, Anritsu Ltd CR Agreement
6.4.4.11.5eCall over IMS (clause 11.5)
Yes
Yes
agreed No    
R5‑254149 Correction to NBIOT testcase 22.1.1 ROHDE & SCHWARZ CR Agreement
6.5.3.11Others (TS 36.523-1 clauses not covered by other AIs under AI 6.5.3, e.g. eMBMS, Home (e)NB, MBMS in LTE, D2D, SC-PTM, NB-IoT, CIoT...)
Yes
YesTF160 manager: Note size shall be unified!
agreed No    
R5‑254150 Correction to NBIOT testcase 22.4.23 ROHDE & SCHWARZ CR Agreement
6.5.3.11Others (TS 36.523-1 clauses not covered by other AIs under AI 6.5.3, e.g. eMBMS, Home (e)NB, MBMS in LTE, D2D, SC-PTM, NB-IoT, CIoT...)
Yes
Yes
agreed No    
R5‑254151 Correction to NR5GC testcase 9.1.14.1 ROHDE & SCHWARZ, MediaTek CR Agreement
6.4.4.5.10MM Paging Early Indication (clause 9.1.14)
Yes
Yes
agreed No    
R5‑254152 Correction to NR5GC testcase 6.5.1.2 ROHDE & SCHWARZ CR Agreement
6.4.4.2Idle Mode (Clause 6)
Yes
Yes
agreed No    
R5‑254153 Correction to NR5GC testcase 11.3.6a ROHDE & SCHWARZ CR Agreement
6.4.4.11.3Unified Access Control (UAC) (clause 11.3)
Yes
Yes
agreed No    
R5‑254154 Add generic test procedure for Emergency call and RTT Ericsson CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
YesLenovo: resolve .n
revised No R5‑254917  
R5‑254155 Core Spec alignment for PRS Resource slot offset of PRS-RSRPP test cases Rohde & Schwarz CR Agreement
5.4.15TS 37.571-1
Yes
Yes
agreed No    
R5‑254156 Correction of p-max for FR2 default message contents Rohde & Schwarz CR Agreement
5.4.1.4Other clauses, Annexes
Yes
Yessolve overlap with R5-254060. r1
revised No R5‑255209  
R5‑254157 Editorial corrections for sections headers Rohde & Schwarz CR Agreement
5.4.10.4NR Standalone in FR1 (Clause 6)
Yes
Yesoverlap with R5-254685 r1
revised No R5‑255322  
R5‑254158 Correction to Initial test environment conditions for RRM NTN tests Rohde & Schwarz CR Agreement
5.3.4.6TS 38.533
Yes
Yes
withdrawn Yes    
R5‑254159 Core spec alignment for RRM NR NTN tests for measurement accuracy Rohde & Schwarz CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑254160 Add generic procedure for emergency speech call and RTT Ericsson CR Agreement
6.6.6.1TS 34.229-1
Yes
Yesr1
revised No R5‑255083  
R5‑254161 Update NG.114 versions Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No    
R5‑254162 Updates to NR NTN related default message contents MCC TF160 CR Agreement
6.3.3.1TS 38.508-1
Yes
Yes
agreed No    
R5‑254163 Correction to NR RLC test case 7.1.2.3.11 Keysight Technologies UK CR Agreement
6.4.4.3.1.3RLC
Yes
Yes
agreed No    
R5‑254164 LTE based 5G broadcast RF test cases added Qualcomm Technologies Ireland CR Agreement
6.3.26New bands and bandwidth allocation for LTE based 5G terrestrial broadcast (UID-1050131) LTE_terr_bcast_bands_part2-UEConTest
No
Yes
withdrawn Yes    
R5‑254165 Corrected incorrect RB allocations for additional MOP TC Qualcomm Technologies Ireland CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yesis Rel-19! reissued as R5-254894
withdrawn Yes    
R5‑254166 Corrected incorrect K2 value for Tx on off test case Qualcomm Technologies Ireland CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yesis Rel-19! reissued as R5-254894
withdrawn Yes    
R5‑254167 WP UE Conformance - Further NR coverage enhancements China Telecom Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254168 SR UE Conformance - Further NR coverage enhancements China Telecom WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254169 WP UE Conformance - NR channel BW less than 5MHz for FR1 Phase 2 China Telecom Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254170 SR UE Conformance - NR channel BW less than 5MHz for FR1 Phase 2 China Telecom WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254171 Revised WID on UE Conformance - NR channel BW less than 5MHz for FR1 Phase 2 China Telecom WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yesis endorsed
agreed No    
R5‑254172 Addition of new test case 6.6.3 FirstNet, Ericsson, Element, Samsung R&D Institute UK CR Agreement
6.3.24.5TS 37.579-6
Yes
Yesblock agreed on Thu r1
revised No R5‑255078  
R5‑254173 Addition of new LTM Test Case 7.1.1.3.29 for LTM cell switch 4 step contention free random access procedure Qualcomm Sweden CR Agreement
6.3.23.3TS 38.523-1
Yes
Yesr1
revised No R5‑255035  
R5‑254174 Addition of Applicability of new LTM Test Cases Qualcomm Sweden CR Agreement
6.3.23.4TS 38.523-2
Yes
Yes19.1.0->2 revision mark some changes
revised No R5‑255036  
R5‑254175 Correction to LTM Test Case DRX operation 7.1.1.5.11 Qualcomm Sweden CR Agreement
6.3.23.3TS 38.523-1
Yes
Yes
agreed No    
R5‑254176 Editorial correction to test purpose in Aerial UE Test Case Qualcomm Sweden CR Agreement
6.5.3.3.3RRC Part 3 (clause 8.3)
Yes
Yes
withdrawn Yes    
R5‑254177 Duplicate conditions and their usage in test case selection expression Qualcomm Sweden discussion Discussion
6.4.7Discussion Papers, Work Plan, TC lists
Yes
YesConclusion: noted, proposals are accepted.
noted No    
R5‑254178 Addition of eCall test case 11.17 for CEN alignments Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yesr1
revised No R5‑254972  
R5‑254179 Addition of eCall test case 11.19 for CEN alignments Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yesr1
revised No R5‑254973  
R5‑254180 Corrrection to eCALL test case 11.13 Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yesr1 merged into R5-253978
revised No R5‑254974  
R5‑254181 Corrrection to eCALL test case 11.15 Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yesr1
revised No R5‑254975  
R5‑254182 Corrrection to eCALL test case 11.16 Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yesr1
revised No R5‑254976  
R5‑254183 Corrrection to eCALL test case 11.18 Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yesr1 Deferred.
revised No R5‑254977  
R5‑254184 Addition of applicablity for new NR NGeCall CEN alignment Test Cases Qualcomm Sweden CR Agreement
6.3.29.11TS 34.229-2
Yes
Yesr1
revised No R5‑254980  
R5‑254185 SR UE Conformance Test Aspects - Rel-18 NR small data transmissions in INACTIVE state Qualcomm Sweden WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254186 WP UE Conformance Test Aspects - Rel-18 NR small data transmissions in INACTIVE state Qualcomm Sweden Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254187 SR UE Conformance Test Aspects - Alignment of eCall over IMS with CEN Qualcomm Sweden WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254188 WP UE Conformance Test Aspects - Alignment of eCall over IMS with CEN Qualcomm Sweden Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254189 Revised WID on UE Conformance - Alignment of eCall over IMS with CEN Qualcomm Sweden WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
YesWP->rev. WID!
revised No R5‑254902  
R5‑254190 Addition of new test case 6.10.4 FirstNet, Ericsson, Element, Samsung R&D Institute UK CR Agreement
6.3.24.5TS 37.579-6
Yes
Yesblock agreed on Thu r1
revised No R5‑255075  
R5‑254191 Addition of new test case 6.9.4 FirstNet, Ericsson, Element, Samsung R&D Institute UK CR Agreement
6.3.24.6TS 37.579-7
Yes
Yesblock agreed on Thu r1
revised No R5‑255076  
R5‑254192 Correction for TT analysis for TC 6.3.3.5 Xiaomi CR Agreement
5.3.28.4TS 38.533
Yes
Yes
agreed No    
R5‑254193 Correction for TT analysis for RRM TC 6.5.12.1 Xiaomi CR Agreement
5.3.28.4TS 38.533
Yes
Yes" Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254194 Correction for TT analysis for RRM TC 6.5.12.2 Xiaomi CR Agreement
5.3.28.4TS 38.533
Yes
Yes" Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254195 TT analysis for new test case 6.3.3.5 Xiaomi CR Agreement
5.3.28.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254196 TT analysis for new test case 6.5.12.1 Xiaomi CR Agreement
5.3.28.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254197 TT analysis for new test case 6.5.12.2 Xiaomi CR Agreement
5.3.28.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254198 Correction for 38523-1 TC 6.3.1.7 Xiaomi CR Agreement
6.4.4.2Idle Mode (Clause 6)
Yes
YesTEIx r1 TEI16->5_Test, +5GS_NR_LTE-UEConTest". r2 coversheet still wrong. Deferred. r3
revised No R5‑255067  
R5‑254199 New WID on UE Conformance - Enhanced requirements and conductive test methodology for NR NTN and IoT NTN Xiaomi, China Unicom, Samsung WID new Endorsement
4.1New Work Item proposals - for intro only
Yes
Yesr1 RAN5 Chair: there was an agreement that no eMTC NTN test coverage is provided.
revised No R5‑254911  
R5‑254200 Correction to RRC test case 8.5.4.1 Keysight Technologies UK CR Agreement
6.5.3.3.1RRC Part 1 (clauses 8.1 and 8.5)
Yes
Yesoffline comments from TF160 r1
revised No R5‑255055  
R5‑254201 Correction to EMM test case 9.2.3.3.1 Keysight Technologies UK CR Agreement
6.5.3.4EPS Mobility Management
Yes
Yescoverpage
revised No R5‑254928  
R5‑254202 Implementation of RRM NR Intra-band Contiguous CA procedure in FR2 Keysight Technologies CR Agreement
5.4.1.4Other clauses, Annexes
Yes
Yes
agreed No    
R5‑254203 Addition of new test case 9.3.1.7 related to Inter-system mobility registration update / Rejected / No suitable cells in tracking area / 5GC to EPC NTT DOCOMO, INC CR Agreement
6.4.4.75GS Inter-system Mobility (clause 9.3)
Yes
Yes"TEI15_Test, 5GS_NR_LTE-UEConTest" cannot be used for a brand new test case r1 RAN5 Chair: cannot have 2 TCs with same TP. Only TP1. TF160 manager: editorial r2
revised No R5‑254936  
R5‑254204 Applicability update to Inter-system mobility registration update / Rejected / No suitable cells in tracking area / 5GC to EPC test case NTT DOCOMO, INC CR Agreement
6.4.5TS 38.523-2
Yes
Yesr1 -5GS
revised No R5‑255072  
R5‑254205 Addition of RRM NR Intra-band Contiguous CA configurations in FR2 Keysight Technologies CR Agreement
5.4.1.3Test environment for RRM (Clause 7)
Yes
Yes
agreed No    
R5‑254206 Correction of test case 9.1.5.1.13 NTT DOCOMO, INC CR Agreement
6.4.4.5.3MM Registration & De-registration (clauses 9.1.5 & 9.1.6)
Yes
Yes
withdrawn Yes    
R5‑254207 Modification of the references for the RRM FR2 intra-band contiguous tables in Annex E Keysight Technologies UK Ltd CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
No
Yes
withdrawn Yes    
R5‑254208 Proposal for new test case related to UE mobility in inter-system upon receiving the 5GMM cause value #15 in the REGISTRATION REJECT message NTT DOCOMO INC. discussion Endorsement
6.4.7Discussion Papers, Work Plan, TC lists
Yes
Yesr1 Motorola Mobility: Proposal 1 may be better way to go.
revised No R5‑254930  
R5‑254209 Modification of the references for the RRM FR2 intra-band contiguous tables in Annex E Keysight Technologies UK Ltd CR Agreement
5.4.1.4Other clauses, Annexes
No
Yes
withdrawn Yes    
R5‑254210 Modification of the references for the RRM FR2 intra-band contiguous tables Keysight Technologies CR Agreement
5.4.1.4Other clauses, Annexes
Yes
Yes
agreed No    
R5‑254211 Add parameters of enhanced receiver type 2 for TDD 4Rx SGS Wireless CR Agreement
5.3.26.1.2Test environment for RF (Clauses 5)
Yes
Yes
agreed No    
R5‑254212 Update of Beam correspondence for PC6 in clause 6.6.1.3.5 SGS Wireless CR Agreement
5.3.5.3.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255274  
R5‑254213 Missing mTT for eRedCap Keysight Technologies CR Agreement
5.3.15.4.4Clauses 1-4, Annexes
Yes
Yes
agreed No    
R5‑254214 Addition of Es value to the common test parameters in 5.5A.1.1 Keysight Technologies CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yesr1
revised No R5‑255309  
R5‑254215 Addition of Es value to the common test parameters in 9.4B.1.1 Keysight Technologies CR Agreement
5.4.7.3Interworking Demod Performance and CSI Reporting Requirements (Clauses 9&10)
Yes
Yes
agreed No    
R5‑254216 Corrections to ATSSS SM test cases MCC TF160 CR Agreement
6.4.4.105GS Non-3GPP Access & ATSS Session Management (clauses 10.3, 10.4 & 10.5)
Yes
Yes
agreed No    
R5‑254217 Corrections to ATSSS_Ph2 SM test cases MCC TF160 CR Agreement
6.4.4.105GS Non-3GPP Access & ATSS Session Management (clauses 10.3, 10.4 & 10.5)
Yes
Yes
agreed No    
R5‑254218 Corrections to ATSSS_Ph2 Inter-system test cases MCC TF160 CR Agreement
6.4.4.11.9Inter-system mobility with established MA PDU session in 5GS (clause 11.9)
Yes
Yes
agreed No    
R5‑254219 WP on UE Conformance – Enhanced support of reduced capability NR devices China Unicom Work Plan  
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254220 Corrections to N3Access MM test cases MCC TF160 CR Agreement
6.4.4.65GS Non-3GPP Access Mobility Management (clause 9.2)
Yes
YesMotorola Mobility: fix the step numbering.
revised No R5‑254935  
R5‑254221 Corrections to N3Access SM test cases MCC TF160 CR Agreement
6.4.4.105GS Non-3GPP Access & ATSS Session Management (clauses 10.3, 10.4 & 10.5)
Yes
Yes
agreed No    
R5‑254222 Addition of RF baseline implementation capabilities for new PC2 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.41.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254223 Addition of reference sensitivity for new PC2 R19 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.41.3.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255277  
R5‑254224 SR on UE Conformance – Enhanced support of reduced capability NR devices China Unicom WI status report  
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254225 Addition of reference sensitivity TP analysis for new PC2 R19 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.41.5TR 38.905 (NR Test Points Radio Transmission and Reception)
No
Yes
withdrawn Yes    
R5‑254226 PRD21 CDS: PC3 EN-DC R16 combos KDDI Corporation other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
Yes
Yes
noted No    
R5‑254227 PRD21 CDS: PC3 EN-DC R15 combos KDDI Corporation other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
Yes
Yes
noted No    
R5‑254228 PRD21 CDS: PC2 EN-DC R18 combos KDDI Corporation other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
Yes
Yes
noted No    
R5‑254229 PRD21 CDS: PC2 EN-DC R19 combos KDDI Corporation other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
Yes
withdrawn Yes    
R5‑254230 WP on UE Conformance - NR Support for UAV (Uncrewed Aerial Vehicles) plus CT1 aspects China Unicom Work Plan  
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254231 SR on UE Conformance - NR Support for UAV (Uncrewed Aerial Vehicles) plus CT1 aspects China Unicom WI status report  
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254232 Missing DL RMC for eRedCap FDD test case Keysight Technologies CR Agreement
5.3.15.4.4Clauses 1-4, Annexes
Yes
Yesdouble implementation of the same from R&S and Keysight.
withdrawn Yes    
R5‑254233 RMC update in CQI CA test cases Keysight Technologies CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No    
R5‑254234 Update references in PMI test cases with codebook typeII and eTypeII Keysight Technologies CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
YesTEI16_Test, NR_eMIMO-UEConTest, NR_perf_enh-UEConTest was inverted in 3GU.
agreed No    
R5‑254235 Updates in Annex G.4 for mTT for 0.001% BLER Keysight Technologies CR Agreement
5.4.7.4Clauses 1-4, Annexes
Yes
Yesdoc: % r1
revised No R5‑255410  
R5‑254236 Testability Aspects for AI/ML Based Beam Management Nokia discussion Endorsement
4.2.3AI/ML Testability & Interoperability
Yes
YesQualcomm: it may be too early to have a discussion about a test function.
noted No    
R5‑254237 Updates for CQI reporting with Table 3 test cases Keysight Technologies CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No    
R5‑254238 Correction of NRU SS-RSRQ Test Case 11.6.2.4 Including TT Rohde & Schwarz CR Agreement
5.4.10.9NR Standalone Tests with NR PCell under CCA and Other NR Cells in FR1 (Clause 11)
Yes
Yes"RRM TT. Depends on R4-2509740 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254239 Correction of NRU SS-SINR Test Case 11.6.3.4 Including TT Rohde & Schwarz CR Agreement
5.4.10.9NR Standalone Tests with NR PCell under CCA and Other NR Cells in FR1 (Clause 11)
Yes
Yes"RRM TT. Depends on R4-2509740 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254240 Annex F correction for NRU Inter-Frequency accuracy test cases Including TT Rohde & Schwarz CR Agreement
5.4.10.15Clauses 1-3, Annexes
Yes
Yes"RRM TT. Depends on R4-2509740 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254241 Test Tolerance for RRM NRU Test Case 11.6.2.4 Rohde & Schwarz CR Agreement
5.4.18TR 38.903 (NR MU & TT analyses)
Yes
Yes"RRM TT. Depends on R4-2509740 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254242 Test Tolerance for RRM NRU Test Case 11.6.3.4 Rohde & Schwarz CR Agreement
5.4.18TR 38.903 (NR MU & TT analyses)
Yes
Yes"RRM TT. Depends on R4-2509740 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254243 Corrections to RedCap BWP configurations Rohde & Schwarz CR Agreement
5.4.10.15Clauses 1-3, Annexes
Yes
Yes"Depends on R4-2509744 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254244 Addition of applicability for test case 5.3.1.2.1 Keysight Technologies, Ericsson CR Agreement
5.4.9TS 38.522
Yes
YesWIC was inverted r1
revised No R5‑255337  
R5‑254245 Addition of applicability for test case 9.4B.1.1A Keysight Technologies CR Agreement
5.4.9TS 38.522
Yes
Yes
agreed No    
R5‑254246 WP for variable Tx-Rx spacing conformance specs for IoT NTN bands EchoStar, Viasat, Boost Mobile Network Work Plan Information
5.5.1.13Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No    
R5‑254247 Addition of applicability for test case 14.2.2.3.1 Keysight Technologies CR Agreement
5.3.4.5TS 38.522
Yes
Yes
agreed No    
R5‑254248 WP for support of NB-IoT in-band operation in NR NTN bands EchoStar, Viasat, Boost Mobile Network Work Plan Information
6.5.6Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No    
R5‑254249 Addition of RF test frequencies and conditions for variable Tx-Rx spacing for NB-IoT for NTN bands 253, 254 and 255 EchoStar, Viasat CR Agreement
5.5.1.1TS 36.508
Yes
Yes..246! r1
revised No R5‑255283  
R5‑254250 Update on applicability of requirements for PMI 16 and 32 Tx Keysight Technologies CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes"Depends on RAN4 CR R4-2509830 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254251 Addition of signalling test frequencies and conditions for variable Tx-Rx spacing for NB-IoT for NTN band 253, 254 and 255 EchoStar, Viasat CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
Yesr1
revised No R5‑254918  
R5‑254252 Updates to complete the reference sensitivity test case with variable Tx-Rx spacing for NB-IoT for NTN bands EchoStar CR Agreement
5.5.1.5TS 36.521-4
Yes
Yes
agreed No    
R5‑254253 Core alignment to correct aggregation level and number of candidates for SDR Rel 15 test cases Keysight Technologies CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes"Depends on RAN4 CR R4-2509828. Core alignment. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254254 Core alignment to correct aggregation level and number of candidates for SDR Rel 16 test case Keysight Technologies CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes"Depends on RAN4 CR R4-2509828. Core alignment. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254255 Update to Enhanced TypeII codebook CSI Test Cases Rohde & Schwarz CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No    
R5‑254256 Update to TypeI and TypeII codebook CSI Test Cases Rohde & Schwarz CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No    
R5‑254257 Correction to Demod test frequencies for band n31 and n72 Rohde & Schwarz CR Agreement
5.4.1.2Test environment for RF (Clauses 5)
Yes
Yes
agreed No    
R5‑254258 Correction to Demod test frequencies for band n30 Rohde & Schwarz CR Agreement
5.4.1.2Test environment for RF (Clauses 5)
Yes
Yes
agreed No    
R5‑254259 Updates on PDSCH 0.001% BLER correlation matrix and CQI reporting with Table 3 Keysight Technologies CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes"Depends on RAN4 CR R4-2509825. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254260 Addition of test point analysis for the reference sensitivity test case for NB-IoT NTN with flexible Tx-Rx separation EchoStar CR Agreement
5.5.1.7.3TR 36.905 (E-UTRAN Test Points Radio Transmission and Reception )
Yes
Yes
agreed No    
R5‑254261 Corrections to default RF test frequencies for n256 and addition of RF test frequencies to verify RF aspects of variable Tx-Rx spacing for NR NTN bands n255 and n256 EchoStar, Viasat CR Agreement
5.3.4.1TS 38.508-1
Yes
Yesr1
revised No R5‑255294  
R5‑254262 Addition of SIG test frequencies to verify protocol aspects of flexible Tx-Rx separation for NR NTN bands n255 and n256 EchoStar, MCC TF160, Viasat CR Agreement
6.3.3.1TS 38.508-1
Yes
Yes
agreed No    
R5‑254263 Updates to complete the reference sensitivity test cases with variable Tx-Rx spacing for NR NTN bands EchoStar CR Agreement
5.3.4.4TS 38.521-5
Yes
Yes
agreed No    
R5‑254264 Update to applicability of the test case for variable Tx-Rx spacing for NR NTN bands EchoStar CR Agreement
5.3.4.5TS 38.522
Yes
Yes
withdrawn Yes    
R5‑254265 Updates pre-test conditions for the System Simulator for handover tests cases to verify protocol aspects of variable Tx-Rx spacing for NR NTN bands EchoStar, MCC TF160 CR Agreement
6.3.3.4TS 38.523-1
Yes
Yes
agreed No    
R5‑254266 Updates to applicability for protocol conformance testing of flexible Tx-Rx separation for NR NTN bands EchoStar, MCC TF160 CR Agreement
6.3.3.5TS 38.523-2
Yes
Yes
agreed No    
R5‑254267 Addition of PIXIT for testing of flexible Tx-Rx separation for NR NTN bands EchoStar, MCC TF160 CR Agreement
6.3.3.6TS 38.523-3
Yes
YesXXX! r1
revised No R5‑254942  
R5‑254268 Addition of test point analysis for the reference sensitivity test case for NR NTN with flexible Tx-Rx separation EchoStar CR Agreement
5.3.4.8TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254269 Addition of test frequencies and updates to support protocol test coverage for NB-IoT inband in NTN NR EchoStar, Viasat CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
Yesr2
revised No R5‑254919  
R5‑254270 Addition of applicability and PICS for protocol test coverage for NB-IoT inband in NTN NR EchoStar CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
YesXX
revised No R5‑254921  
R5‑254271 Adds a value to an existing PIXIT to accommodate emulation of a test environment for NB-IoT inband operation in NTN NR EchoStar CR Agreement
6.5.5Routine Maintenance for TS 36.523-3
Yes
Yes
agreed No    
R5‑254272 Fix wrong side condition for RRC Connection Release with Redirection for Satellite Access Keysight Technologies CR Agreement
5.3.4.6TS 38.533
Yes
No"Depends on RAN4 CR R4-2509846 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254273 Addressing incomplete sections in the test case 14.2.2.3.1 Keysight Technologies CR Agreement
5.3.4.6TS 38.533
Yes
No"Related CRs: R5-254247 and R5-254300 deferred pending rrm tt crs Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254274 Addition of new UAV Test Case 8.1.3.5.1 Test Case for event H1 reporting QUALCOMM JAPAN LLC. CR Agreement
6.3.31.3TS 38.523-1
Yes
Yesr1
revised No R5‑255041  
R5‑254275 Addition of new UAV Test Case 8.1.3.5.2 Test Case for event H2 reporting QUALCOMM JAPAN LLC. CR Agreement
6.3.31.3TS 38.523-1
Yes
Yesr2
revised No R5‑255042  
R5‑254276 Addition of new UAV Test Case 8.1.3.5.3 Test Case for event A3H1 reporting for Intra-Frequency Neighbour QUALCOMM JAPAN LLC. CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes#109! r3
revised No R5‑255043  
R5‑254277 Addition of new UAV Test Case 8.1.3.5.4 Test Case for event A3H1 reporting for Inter-Frequency Neighbour QUALCOMM JAPAN LLC. CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes#109! r1
revised No R5‑255044  
R5‑254278 Addition of new UAV Test Case 8.1.3.5.5 Test Case for event A3H1 reporting for Inter-Band Neighbour QUALCOMM JAPAN LLC. CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes#109! r1
revised No R5‑255045  
R5‑254279 Addition of applicability for new UAV test cases QUALCOMM JAPAN LLC., China Unicom CR Agreement
6.3.31.4TS 38.523-2
Yes
Yes#109! r2
revised No R5‑255090  
R5‑254280 Common configuration updates related to UAV QUALCOMM JAPAN LLC. CR Agreement
6.3.31.1TS 38.508-1
Yes
Yes#109! r1
revised No R5‑255040  
R5‑254281 Addition of new NR NTN enh 6.7.1.10 Test case for skipping TN measurements QUALCOMM JAPAN LLC. CR Agreement
6.3.25.4TS 38.523-1
Yes
Yes#109! r2
revised No R5‑254944  
R5‑254282 Typo Correction to NR NTN Enh TC 6.7.1.9 QUALCOMM JAPAN LLC. CR Agreement
6.3.25.4TS 38.523-1
Yes
Yes#109! r1
revised No R5‑254945  
R5‑254283 Updates to Test case 8.1.3.1.27 QUALCOMM JAPAN LLC. CR Agreement
6.3.25.4TS 38.523-1
Yes
Yes#109! r1
revised No R5‑254946  
R5‑254284 Addition of new System information config for NTN-TN scenarios QUALCOMM JAPAN LLC. CR Agreement
6.3.25.1TS 38.508-1
Yes
Yes#109! First withdrawn, then partly merged into 4024.
revised No R5‑254943  
R5‑254285 Addition of applicability for new NTN test cases QUALCOMM JAPAN LLC. CR Agreement
6.3.25.5TS 38.523-2
No
Yeslate doc
withdrawn Yes    
R5‑254286 GCF 3GPP TCL after GCF CAG#83 Ericsson report Information
2.2General Reports for information
Yes
Yes
noted No    
R5‑254287 RAN5#108 summary of changes to RAN5 test cases with potential impact on GCF and PTCRB Ericsson report Information
7.6Docs still needing agreement/endorsement/approval (e.g. Outgoing LS, Reports, New Specs, Info for certification bodies etc.)
No
Yes
noted No    
R5‑254288 SR on UE Conformance - Protocol enhancements for Mission Critical Services (MCPTT, MCVideo, MCData) for Rel-17 Ericsson, FirstNet, Element, Samsung R&D Institute UK WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254289 WP on UE Conformance - Protocol enhancements for Mission Critical Services (MCPTT, MCVideo, MCData) for Rel-17 Ericsson, FirstNet, Element, Samsung R&D Institute UK Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254290 Addition of MCData-Regroup details Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.1TS 37.579-1
Yes
Yesblock agreed on Thu
agreed No    
R5‑254291 Addition of new test case 6.1.1.22 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.2TS 37.579-2
Yes
Yesblock agreed on Thu r1
revised No R5‑255020  
R5‑254292 Addition of new test case 6.6.1 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.2TS 37.579-2
Yes
Yesblock agreed on Thu r1
revised No R5‑255021  
R5‑254293 Addition of new test case 6.6.2 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.2TS 37.579-2
Yes
Yesblock agreed on Thu r1
revised No R5‑255022  
R5‑254294 Addition of new test case 6.6.3 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.2TS 37.579-2
Yes
Yesblock agreed on Thu r1
revised No R5‑255023  
R5‑254295 Addition of new test case 6.6.4 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.2TS 37.579-2
Yes
Yesblock agreed on Thu
agreed No    
R5‑254296 Addition of applicabilities for new MCX test cases Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.3TS 37.579-4
Yes
Yesblock agreed on Thu
revised No R5‑255074  
R5‑254297 Addition of new PICs Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.3TS 37.579-4
Yes
Yesblock agreed on Thu r1
revised No R5‑255024  
R5‑254298 Addition of new test case 6.2.16 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.6TS 37.579-7
Yes
Yesblock agreed on Thu r1
revised No R5‑255025  
R5‑254299 Addition of TT analysis for NR-NTN test 14.2.2.3.1 Keysight Technologies UK Ltd CR Agreement
5.3.4.7TR 38.903 (NR MU & TT analyses)
Yes
Yesr3
revised No R5‑255376  
R5‑254300 Addition of TT for test case 14.2.2.3.1. Keysight Technologies CR Agreement
5.3.4.6TS 38.533
Yes
Yesr1
revised No R5‑255374  
R5‑254301 Update Annex F MU and TT for 14.2.2.3.1 Test case Keysight Technologies CR Agreement
5.3.4.6TS 38.533
Yes
Yesr1
revised No R5‑255375  
R5‑254302 Modification of the FR2 Intra-band contiguous carrier aggregation frequencies tables references Keysight Technologies CR Agreement
5.4.10.15Clauses 1-3, Annexes
Yes
Yes
agreed No    
R5‑254303 Update applicability for test case 11.1.4 Ericsson CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No    
R5‑254304 Update applicability for test case 11.1.8 Ericsson CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No    
R5‑254305 Update applicability for test case 11.1.9 Ericsson CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No    
R5‑254306 Update Annex B for PRD20 E-UTRA CA list v1c0 ZTE Corporation CR Agreement
5.3.39.3TS 36.521-2
Yes
Yes
agreed No    
R5‑254307 Corrections on suspended reference for ITU-R recommendation in 36.521-1 ZTE Corporation, Tejet, SRTC CR Agreement
5.3.39.2TS 36.521-1
Yes
Yes
agreed No    
R5‑254308 PRD21 CDS EN-DC FR1 PC2 DC_66A_n41A ZTE Corporation other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
Yes
Yes
noted No    
R5‑254309 PRD20 on E-UTRA CA configuration handling in RAN5 v1.c.0 ZTE Corporation other Approval
7.4.3PRD20: Status updates E-UTRA CA
No
Yesfor email agreement
for email agreement No    
R5‑254310 Simplification on test frequencies for EN-DC band combinations with more than three bands ZTE Corporation discussion Approval
5.3.1.11Discussion Papers, Work Plan, TC lists
Yes
Yes
agreed No    
R5‑254311 Updates on test freq for R16 EN-DC configuration with more than three bands ZTE Corporation CR Agreement
5.3.1.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254312 Updates on test freq for R17 EN-DC configuration with more than three bands ZTE Corporation CR Agreement
5.3.2.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254313 Updates on test freq for R18 EN-DC configuration with more than three bands ZTE Corporation CR Agreement
5.3.12.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254314 Updates on test freq for R15 EN-DC configuration with more than three bands ZTE Corporation CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254315 Addition of reference sensitivity for PC2 DC_66A_n41A ZTE Corporation CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255400  
R5‑254316 Updates on TP analysis for Refsens for PC2 DC_66A_n41A ZTE Corporation CR Agreement
5.4.19TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254317 Updates on Refsens test case for EN-DC configuration DC_1A-41A_n78A ZTE Corporation CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254318 Addition of reference sensitivity test point analysis for DC_1A-41A_n78A ZTE Corporation CR Agreement
5.4.19TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254319 Corrections on UL Fc frequency for R16 EN-DC configurations for MSD test points ZTE Corporation, Tejet, SRTC CR Agreement
5.3.1.5.2Rx Requirements (Clause 7)
Yes
Yesoverlapping issues with R5-253813. r1
revised No R5‑255279  
R5‑254320 Removal of R16 pending configurations for MSD test points for intermodulation interference ZTE Corporation CR Agreement
5.3.1.5.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254321 Corrections on reference sensitivity test cases for R16 3CC EN-DC configurations ZTE Corporation CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254322 Corrections on single uplink configurations for reference sensitivity test cases for R16 2CC EN-DC configurations ZTE Corporation CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254323 Corrections on single uplink configurations for reference sensitivity test cases for R17 2CC EN-DC configurations ZTE Corporation CR Agreement
5.3.2.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254324 Corrections on Annex D.1 for adding channel bandwidth description ZTE Corporation CR Agreement
5.3.14.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254325 Corrections on channel bandwidths for NTN satellite band in FR2-NTN and sync raster for band n254 ZTE Corporation CR Agreement
5.3.30.4TS 38.521-5
Yes
Yes
revised No R5‑255287  
R5‑254326 Addition of test freq for EN-DC configuration DC_1A-41A_n78A ZTE Corporation CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254327 Introduction of DC_1A-41A_n78A for physical layer baseline implementation capabilities ZTE Corporation CR Agreement
5.4.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254328 Corrections on suspended reference for ITU-R recommendation in 38.521-1 ZTE Corporation CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254329 Corrections on suspended reference for ITU-R recommendation in 38.521-2 ZTE Corporation CR Agreement
5.4.5.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254330 Corrections on test requirements for cross band isolation Refsens for DC_7A_n78A ZTE Corporation CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yesoverlap with R5-254754 (Anritsu).
withdrawn Yes    
R5‑254331 Corrections on UL Fc frequency for R15 EN-DC configurations for MSD test points ZTE Corporation, Tejet, SRTC CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254332 Removal of R15 pending configurations for MSD test points for intermodulation interference ZTE Corporation CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254333 Corrections on reference sensitivity test cases for R15 3CC EN-DC configurations ZTE Corporation CR Agreement
5.4.19TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254334 Corrections on single uplink configurations for reference sensitivity test cases for R15 2CC EN-DC configurations ZTE Corporation CR Agreement
5.4.19TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254335 Corrections on test requirements for LTE V2X UE co-existence in 36.521-1 ZTE Corporation CR Agreement
5.5.1.3.1Tx Requirements (Clause 6)
Yes
Yes
revised No R5‑255343  
R5‑254336 Corrections on cross band isolation Refsens test requirements for PC2 DC_7A_n78A ZTE Corporation CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yesoverlapping with R5-254754.
postponed No    
R5‑254337 New WID on UE Conformance – Additional NR bands for NR features in Rel-19 ZTE Corporation, Huawei, China Telecom WID new Endorsement
4.1New Work Item proposals - for intro only
Yes
Yesis a basket WI r1 AT&T asked to be added.
revised No R5‑254912  
R5‑254338 Discussion on spurious emission test cases for inter-band configurations ZTE Corporation discussion Approval
5.3.1.11Discussion Papers, Work Plan, TC lists
Yes
Yes
agreed No    
R5‑254339 Corrections on test point analysis for R16 NR CA configurations for CA_n1-nx and CA_n2-ny ZTE Corporation CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254340 Corrections on test point analysis for R16 NR CA configurations for CA_n3-nx and CA_n5-ny and CA_n20-nz ZTE Corporation CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254341 Corrections on test point analysis for R16 NR CA configurations for CA_n39-nx and CA_n48-ny and CA_n66-nz and CA_n70-nv ZTE Corporation CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254342 Corrections on test point analysis for R17 NR CA configurations for CA_n1-nx and CA_n2-ny and CA_n5-nz and CA_n14-nv ZTE Corporation CR Agreement
5.3.2.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254343 Corrections on test point analysis for R17 NR CA configurations for CA_n24-nx ZTE Corporation CR Agreement
5.3.2.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254344 Corrections on test point analysis for R17 NR CA configurations for CA_n25-nx ZTE Corporation CR Agreement
5.3.2.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254345 Corrections on test point analysis for R17 NR CA configurations for CA_n26-nx and CA_n28-ny and CA_n30-nz ZTE Corporation CR Agreement
5.3.2.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254346 Corrections on test point analysis for R17 NR CA configurations for CA_n48-nx and CA_n66-ny and CA_n71-nz ZTE Corporation CR Agreement
5.3.2.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254347 Corrections on symbols for NR carrier aggregation in 38.521-1 ZTE Corporation, Tejet, SRTC CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254348 Corrections on symbols for NR carrier aggregation in 38.521-2 ZTE Corporation, Tejet, SRTC CR Agreement
5.4.5.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254349 Completion of RLM IS non-DRX less than 5 MHz test case including TT Nokia CR Agreement
5.3.14.6TS 38.533
Yes
Yes
agreed No    
R5‑254350 Addition of test tolerance for RLM IS in non-DRX mode with less than 5M bandwidth test case Nokia CR Agreement
5.3.14.8TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254351 Addition of test tolerance and measurement uncertainty for less than 5 MHz test case 6.5.1.15 Nokia CR Agreement
5.3.14.6TS 38.533
Yes
Yes
agreed No    
R5‑254352 Addition of Beam Failure detection and link recovery test case for a UE operating on a cell with 3 MHz BW Nokia CR Agreement
5.3.14.6TS 38.533
Yes
Yes
agreed No    
R5‑254353 Updation of Test tolerance analysis of NR-DC SA FR1 CHO with Candidate SCG test case Nokia CR Agreement
5.3.28.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254354 Addition of Test tolerance analysis of NR-DC SA FR2 CHO with Target SCG test case Nokia CR Agreement
5.3.28.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254355 Completion of NR-DC SA FR1 CHO test case Nokia CR Agreement
5.3.28.4TS 38.533
Yes
Yes
agreed No    
R5‑254356 Update to NR-DC SA FR1 CHO with target MCG and candidate SCG test case including TT Nokia CR Agreement
5.3.28.4TS 38.533
Yes
Yes
agreed No    
R5‑254357 Update to NR-DC SA FR2 CHO and PSCell change test case including TT Nokia CR Agreement
5.3.28.4TS 38.533
Yes
Yes
agreed No    
R5‑254358 Addition of message content in NR-DC SA FR2 CHO with candidate SCG test case Nokia CR Agreement
5.3.28.4TS 38.533
Yes
Yes
agreed No    
R5‑254359 Annex F change to update the test tolerance values for NR-DC SA FR1 CHO test case Nokia CR Agreement
5.3.28.4TS 38.533
Yes
Yes
agreed No    
R5‑254360 Annex F change to add the test tolerance for the NR SA FR2 CHO test case Nokia CR Agreement
5.3.28.4TS 38.533
Yes
Yes
agreed No    
R5‑254361 Completion of intra-frequency HST FR2 cell re-selection test case including TT Nokia CR Agreement
5.3.5.6TS 38.533
Yes
Yes" Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254362 Annex F changes for intra-frequency HST FR2 cell re-selection test case Nokia CR Agreement
5.3.5.6TS 38.533
Yes
Yes" Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254363 Addition of test tolerance analysis for intra-frequency HST FR2 cell re-selection test case Nokia CR Agreement
5.3.5.7TR 38.903 (NR MU & TT analyses)
Yes
Yesr1
revised No R5‑255370  
R5‑254364 Completion of TRS based SSB-less SCell Activation test case including TT Nokia CR Agreement
5.3.20.5TS 38.533
Yes
Yes
agreed No    
R5‑254365 Correction to A-TRS based SSB-less SCell Activation test cases including TT Nokia CR Agreement
5.3.20.5TS 38.533
Yes
Yesr1
revised No R5‑255371  
R5‑254366 Update to SA FR1 A-TRS based SSB-less SCell Activation test cases including TT Nokia CR Agreement
5.3.20.5TS 38.533
Yes
Yes" Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254367 Annex F changes to include test tolerance for A-TRS and TRS based SSB-less SCell activation test cases Nokia CR Agreement
5.3.20.5TS 38.533
Yes
Yes" Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254368 Addition of test tolerances analysis for TRS based SSB-less SCell activation test case Nokia CR Agreement
5.3.20.6TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254369 Revised Test Tolerances analysis for A-TRS based SSB-less SCell activation test cases Nokia CR Agreement
5.3.20.6TR 38.903 (NR MU & TT analyses)
Yes
Yesr1
revised No R5‑255329  
R5‑254370 WP UE Conformance – NR support for dedicated spectrum less than 5MHz for FR1 Nokia Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254371 SR UE Conformance – NR support for dedicated spectrum less than 5MHz for FR1 Nokia WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254372 Correction of test frequencies for Band n256 ROHDE & SCHWARZ CR Agreement
5.3.4.1TS 38.508-1
Yes
Yes
withdrawn Yes    
R5‑254373 Correction of test frequencies for Band n99 ROHDE & SCHWARZ CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254374 Correction of test frequencies for Band n29 ROHDE & SCHWARZ CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254375 Correction of test frequencies for Band n75 and n76 ROHDE & SCHWARZ CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254376 Clean up of Tx, Rx and Px test cases ROHDE & SCHWARZ CR Agreement
5.3.4.4TS 38.521-5
Yes
Yes
agreed No    
R5‑254377 Update of scheduling request for NTN RF test cases ROHDE & SCHWARZ CR Agreement
5.3.4.1TS 38.508-1
Yes
Yes
agreed No    
R5‑254378 Split of power control test cases ROHDE & SCHWARZ, Keysight CR Agreement
5.3.4.4TS 38.521-5
Yes
Yesr1
revised No R5‑255288  
R5‑254379 Addition of NR NTN power control test cases ROHDE & SCHWARZ CR Agreement
5.3.4.5TS 38.522
Yes
Yes
agreed No    
R5‑254380 Addition of test point analysis for NR NTN power control ROHDE & SCHWARZ CR Agreement
5.3.4.8TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254381 Update of Rel-16 interferer CA test cases ROHDE & SCHWARZ CR Agreement
5.3.1.3.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255359  
R5‑254382 Update of Rel-15 interferer CA test cases ROHDE & SCHWARZ CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255360  
R5‑254383 Correction of A-MPR for UL MIMO test case ROHDE & SCHWARZ CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254384 Correction of UTRA ACLR for UL MIMO test case ROHDE & SCHWARZ CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yesoverlapping with - R5-254470. r1
revised No R5‑255272  
R5‑254385 Editorial correction in maximum input level test case ROHDE & SCHWARZ CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254386 Addition of RMC for eRedCap ROHDE & SCHWARZ, Keysight Technologies CR Agreement
5.3.15.4.4Clauses 1-4, Annexes
Yes
Yesr1
revised No R5‑255306  
R5‑254387 Correction of Rel-16 UL Tx switching test cases ROHDE & SCHWARZ CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255401  
R5‑254388 Correction of Tx test cases ROHDE & SCHWARZ CR Agreement
5.4.6.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254389 Editorial correction in Annex F ROHDE & SCHWARZ CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254390 Update of Annex F ROHDE & SCHWARZ CR Agreement
5.4.6.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254391 Update on SUL test scenario Keysight Technologies CR Agreement
5.4.10.4NR Standalone in FR1 (Clause 6)
Yes
Yesr2
revised No R5‑255407  
R5‑254392 Addition of test applicability statement for BFD and LR test case for a UE operating on a PCell with 3 MHz BW Nokia CR Agreement
5.3.14.5TS 38.522
Yes
Yes
agreed No    
R5‑254393 Correction on the Less than 5M Bandwidth capabilities Nokia CR Agreement
5.3.14.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254394 RTT workplan Vodafone GmbH Work Plan Presentation
7.5.3Work Plan updates of recently closed work items
No
No
reserved No    
R5‑254395 TP analyze 6.2.3 NS 18 PC2 and BW40 Ericsson CR Agreement
5.3.34.5TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yescl. aff. Covered by R5-254781
withdrawn Yes    
R5‑254396 Update to AMPR TC for n28 PC2 and 40MHz Ericsson CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
YesCovered by R5-254782
withdrawn Yes    
R5‑254397 Update to CSI-ReportPeriodicityAndOffset MCC TF160 CR Agreement
6.4.1.2Default NG-RAN RRC messages and IEs (Clause 4.6)
Yes
Yes
agreed No    
R5‑254398 WP on UE Conformance - mmWave in NR UE spurious emissions and EESS (Earth Exploration Satellite Service) protection China Unicom Work Plan  
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254399 SR on UE Conformance - mmWave in NR UE spurious emissions and EESS (Earth Exploration Satellite Service) protection China Unicom WI status report  
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254400 Editorial Correction to Clause numbers for Rx test cases TTA CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254401 WP on UE Conformance - Rel-19 High power UE (power class 1.5 or 2) for Dual Connectivity (DC) combinations of LTE band(s) and NR band(s) China Unicom Work Plan  
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254402 SR on UE Conformance - Rel-19 High power UE (power class 1.5 or 2) for Dual Connectivity (DC) combinations of LTE band(s) and NR band(s) China Unicom WI status report  
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254403 Editorial Correction to Clause headers for Tx test cases TTA CR Agreement
5.4.6.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254404 WP on UE Conformance - High power UE (power class 2) for NR FR1 FDD single band China Unicom Work Plan  
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254405 SR on UE Conformance - High power UE (power class 2) for NR FR1 FDD single band China Unicom WI status report  
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254406 Update of applicability for A-MPR, A-SEM and UTRA ACLR for UL MIMO ROHDE & SCHWARZ CR Agreement
5.4.9TS 38.522
Yes
Yes
agreed No    
R5‑254407 Correction of Rel-17 UL Tx switching test cases ROHDE & SCHWARZ CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254408 Addition of CEN alignment test case 21.29 Qualcomm Incorporated CR Agreement
6.3.29.10TS 34.229-1
Yes
Yes
agreed No    
R5‑254409 Correction to TC5.5.2.7 with TT analysis Apple CR Agreement
5.3.8.4TS 38.533
Yes
Yes
agreed No    
R5‑254410 TT analysis for TC5.5.2.7 Apple CR Agreement
5.3.8.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254411 Correction to TC5.5.2.8 with TT analysis Apple CR Agreement
5.3.8.4TS 38.533
Yes
Yes
agreed No    
R5‑254412 TT analysis for TC5.5.2.8 Apple CR Agreement
5.3.8.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254413 Correction to TC5.5.10.1 with TT analysis Apple CR Agreement
5.3.8.4TS 38.533
Yes
Yes
agreed No    
R5‑254414 Correction to TC7.5.10.1 with TT analysis Apple CR Agreement
5.3.8.4TS 38.533
Yes
Yes
agreed No    
R5‑254415 TT analysis for TC5.5.10.1 and TC7.5.10.1 Apple CR Agreement
5.3.8.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254416 Correction to TC5.6.5.1 with TT analysis Apple CR Agreement
5.3.8.4TS 38.533
Yes
Yesr1
revised No R5‑255387  
R5‑254417 TT analysis for TC5.6.5.1 Apple CR Agreement
5.3.8.5TR 38.903 (NR MU & TT analyses)
Yes
Yesr3
revised No R5‑255389  
R5‑254418 Correction to TC7.5.2.2 with TT analysis Apple CR Agreement
5.3.8.4TS 38.533
Yes
Yes
agreed No    
R5‑254419 TT analysis for TC7.5.2.2 Apple CR Agreement
5.3.8.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254420 Correction to TC7.6.2.9 with TT analysis Apple CR Agreement
5.3.8.4TS 38.533
Yes
Yes
withdrawn Yes    
R5‑254421 TT analysis for TC7.6.2.9 Apple CR Agreement
5.3.8.5TR 38.903 (NR MU & TT analyses)
Yes
Yesr1
revised No R5‑255390  
R5‑254422 Correction to TC7.6.5.1 with TT analysis Apple CR Agreement
5.3.8.4TS 38.533
Yes
Yes
withdrawn Yes    
R5‑254423 TT analysis for TC7.6.5.1 Apple CR Agreement
5.3.8.5TR 38.903 (NR MU & TT analyses)
Yes
Yesr1
revised No R5‑255391  
R5‑254424 Annex F modification for some TCs Apple CR Agreement
5.3.8.4TS 38.533
Yes
Yesr2
revised No R5‑255388  
R5‑254425 Correction to Table 6.6.2.2A.2_1.4.1-3 NS number Apple CR Agreement
5.5.1.3.1Tx Requirements (Clause 6)
Yes
Yes-s TEI-18 ->13 r1
revised No R5‑255284  
R5‑254426 Correction to Table 8.2.1.4.2_A.4.5-2 reference table number Apple CR Agreement
5.5.1.3.3Clauses 1-5, 8-10, Annexes
Yes
YesTEI- r1
revised No R5‑255285  
R5‑254427 Correction to N_RB_alloc numbers in Table 6.1A-1a Apple CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yesis Rel-19! reissued as R5-254896 TEI-
withdrawn Yes    
R5‑254428 Correction to clause 6.2A.3 Apple CR Agreement
5.4.5.1Tx Requirements (Clause 6)
Yes
YesTEI- r1
revised No R5‑255276  
R5‑254429 SR - UE Conformance Aspects - NR RRM enhancements Apple WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254430 WP - UE Conformance Aspects - NR RRM enhancements Apple Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254431 New WID on UE Conformance – FR1 TRP (Total Radiated Power), TRS (Total Radiated Sensitivity) and MIMO OTA (Over the Air) testing enhancement Phase 3 Apple Inc, Vivo WID new Endorsement
4.1New Work Item proposals - for intro only
Yes
Yesr1
revised No R5‑254913  
R5‑254432 LTE based 5G broadcast RF Rx test cases added Qualcomm Technologies Ireland CR Agreement
5.3.31.3TS 36.521-1
Yes
Yes
revised No R5‑255342  
R5‑254433 Spec alignment of n30 NS21 AMPR correction Qualcomm Technologies Ireland CR Agreement
5.4.4.1Tx Requirements (Clause 6)
No
YesWIC was inverted
withdrawn Yes    
R5‑254434 WP Rel-15 NR TX and RX Test Cases – Part 3: Range 1 and Range 2 Interworking operation with other radios (TS 38.521-3) Qualcomm Technologies Ireland Work Plan Information
7.5.3Work Plan updates of recently closed work items
Yes
Yes
noted No    
R5‑254435 Addition of reference sensitivity for CA_n3A-n28A-n77(2A) within FR1 KDDI Corporation (TTC) CR Agreement
5.3.1.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254436 Addition of test frequencies for CA_n3A_n28A-n77(2A) within FR1 KDDI Corporation (TTC) CR Agreement
5.3.1.1.1Test frequencies (Clause 4.3.1)
Yes
Yesr1
revised No R5‑255201  
R5‑254437 Addition of new test case 6.10.3 Element, Ericsson, FirstNet, Samsung R&D Institute UK CR Agreement
6.3.24.5TS 37.579-6
Yes
Yesmonth r1 block agreed on Thu
revised No R5‑255091  
R5‑254438 Addition of UE capability for CA_n3A-n28A-n77A(2A) within FR1 KDDI Corporation (TTC) CR Agreement
5.3.1.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254439 Addition of reference sensitivity TP analysis for CA_n3A-n28A -n77A(2A) within FR1 KDDI Corporation (TTC) CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254440 SR UE Conformance NR demodulation performance evolution RAN5#108 China Telecom WI status report Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254441 WP NR demodulation performance evolution RAN5#108 China Telecom Work Plan Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254442 Adding new test case NR RSTD measurement reporting delay for PRS aggregation in FR1 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑254443 Introducing new test case NR RSTD measurement reporting delay for PRS aggregation in FR2 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑254444 Adding new NR RSTD measurement accuracy test case for PRS aggregation in FR1 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑254445 Introducing new NR RSTD measurement accuracy test case for PRS aggregation in FR2 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yesr1
revised No R5‑255333  
R5‑254446 Introduce RSTD measurement requirements based on PRS aggregation CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑254447 Update of NR FR1 UL MIMO Capabilities Huawei, HiSilicon CR Agreement
5.3.19.2TS 38.508-2
Yes
Yes
noted No    
R5‑254448 Update of 6.2.1 Note for power class 1.5 Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254449 Addition of new test cases for configured transmitted power with 4Tx Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254450 Addition of new test cases for ON-OFF time mask and UTRA ACLR with 4Tx Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254451 Removal of Editor Note for 4Tx test cases Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254452 Addition of Annex F MU and TT for 4Tx test cases Huawei, HiSilicon CR Agreement
5.3.19.3.3Clauses 1-5, Annexes
Yes
Yesr2
revised No R5‑255351  
R5‑254453 New WID on UE Conformance - Evolution of NR duplex operation: Sub-band full duplex (SBFD) Huawei, HiSilicon, CMCC WID new Endorsement
4.1New Work Item proposals - for intro only
Yes
Yesr1 Nokia asked to be added. RAN5 Vice Chair RF: reson for Rel-19 WI is not clear.
revised No R5‑254915  
R5‑254454 Revised WID on UE Conformance - New Rel-19 NR licensed bands and extension of existing NR bands Huawei, HiSilicon, China Telecom WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yesr1
revised No R5‑255102  
R5‑254455 WP UE Conformance - New Rel-19 NR licensed bands and extension of existing NR bands Huawei, HiSilicon Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254456 SR UE Conformance - New Rel-19 NR licensed bands and extension of existing NR bands Huawei, HiSilicon WI status report Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254457 WP UE Conformance - Network energy savings for NR Huawei, HiSilicon Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254458 SR UE Conformance - Network energy savings for NR Huawei, HiSilicon WI status report Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254459 PRD-17 on Guidance to Work Item Codes (post RAN#109 version) Huawei, HiSilicon other Agreement
7.4.2PRD17: Guidance to using Work Item Codes with RAN5 test cases
No
Yesfor email agreement
for email agreement No    
R5‑254460 Addition of new test case 8.1.3.5.9 for NR UAV China Unicom CR Agreement
6.3.31.3TS 38.523-1
No
Yes
withdrawn Yes    
R5‑254461 Addition of test frequencies for new three bands NR CA and new four bands NRCA combos within FR1 KDDI Corporation (TTC) CR Agreement
5.3.2.1.1Test frequencies (Clause 4.3.1)
Yes
Yesr1
revised No R5‑255203  
R5‑254462 Update of SSB configuration for mTRP RRM test cases Huawei, HiSilicon CR Agreement
5.3.24.1.3Test environment for RRM (Clause 7)
Yes
Yes
agreed No    
R5‑254463 Addition of UE capability of RTD larger than CP Huawei, HiSilicon CR Agreement
5.3.24.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254464 Update of applicability condition for RRM tesr case 6.5.13.1 Huawei, HiSilicon CR Agreement
5.3.24.6TS 38.522
Yes
Yes
agreed No    
R5‑254465 Addition of message contents for uTCI mTRP test cases Huawei, HiSilicon CR Agreement
5.3.24.7TS 38.533
Yes
Yes
agreed No    
R5‑254466 Update of R18 MIMO uTCI mTRP test procedure and parameters Huawei, HiSilicon CR Agreement
5.3.24.7TS 38.533
Yes
Yes"RAN4 dependent R4-2510608 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254467 Introduction of TRS configurations and unified TCI state configurations Huawei, HiSilicon CR Agreement
5.3.24.7TS 38.533
Yes
Yes
agreed No    
R5‑254468 Update of Test Equipment diagrams for 2Tx tests Huawei, HiSilicon CR Agreement
5.4.1.4Other clauses, Annexes
Yes
Yesspec! r1
revised No R5‑255208  
R5‑254469 Addition of connection diagram for 2Tx TxD test cases Huawei, HiSilicon CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254470 Removal of ULFPTx from 6.5D.2.4.2 UTRA ACLR for UL MIMO Huawei, HiSilicon CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254471 Correction to MU and TT for EVM measurement for UL MIMO Huawei, HiSilicon CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254472 Update of CSI-RS message for 6.3.2.1.7 and 6.3.2.2.8 Huawei, HiSilicon CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yesr1
revised No R5‑255412  
R5‑254473 Correction to applicabilities related to 2-layer MIMO capabilities Huawei, HiSilicon CR Agreement
5.4.9TS 38.522
Yes
Yesoverlaps with R5-253900 r1
revised No R5‑255356  
R5‑254474 Addition of test frequency for Rel-16 n71 related EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.1.1.1Test frequencies (Clause 4.3.1)
Yes
Yesoffline comments from TF160 r1
revised No R5‑255202  
R5‑254475 Addition of physical capabilities for Rel-16 n71 related EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.1.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254476 Addition of Tx testing for Rel-16 n71 related EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.1.5.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254477 Addition of reference sensitivity for Rel-16 DC_1A-3A_n71A Huawei, HiSilicon CR Agreement
5.3.1.5.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254478 Addition of test point analysis for Rel-16 n71 related EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254479 Addition of test frequency for Rel-18 CA_8A-n77A Huawei, HiSilicon CR Agreement
5.3.12.1.1Test frequencies (Clause 4.3.1)
Yes
Yesoffline comments from TF160 r1
revised No R5‑255205  
R5‑254480 Addition of physical capability for Rel-18 CA_8A-n77A Huawei, HiSilicon CR Agreement
5.3.12.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254481 Addition of Tx testing for Rel-18 CA_n8A-n77A Huawei, HiSilicon CR Agreement
5.3.12.3.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255226  
R5‑254482 Addition of test point analysis for Rel-18 CA_n8A-n77A Huawei, HiSilicon CR Agreement
5.3.12.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yesr1
revised No R5‑255227  
R5‑254483 Addition of test frequency for Rel-19 NR CA and EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.35.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
revised No R5‑255206  
R5‑254484 Addition of physical capabilities for Rel-19 NR CA and EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.35.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254485 Addition of reference sensitivity for Rel-19 3DL and 4DL NR CA configurations Huawei, HiSilicon CR Agreement
5.3.35.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254486 Addition of Tx testing for Rel-19 n71 related EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.35.5.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254487 Addition of reference sensitivity for Rel-19 3CC and 4CC EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.35.5.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254488 Addition of test point analysis for Rel-19 NR CA and EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.35.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254489 Update to contents of A.1.1 Register Qualcomm Incorporated CR Agreement
6.6.6.1TS 34.229-1
Yes
Yesemergency services operate independently of the PS data off, hence feature tag must not be checked. TS 24.229 feature tag to be included in SIP messages.
not pursued No    
R5‑254490 Addition of event A4H1 configs for NR UAV in Table 4.6.3-142 China Unicom CR Agreement
5.3.33.1.1Test frequencies (Clause 4.3.1)
No
Yes
withdrawn Yes    
R5‑254491 Addition of test applicability for new R18 NPN test cases China Telecom Corporation Ltd. CR Agreement
6.3.21.4TS 38.523-2
Yes
Yes..941! r2
revised No R5‑255004  
R5‑254492 Addition of new test case 8.1.3.5.10 for NR UAV China Unicom CR Agreement
6.3.31.3TS 38.523-1
No
Yes
withdrawn Yes    
R5‑254493 Core sepc alignment for LTM test cases 6.3.4.1 and 6.3.4.2 MediaTek Inc., Keysight Technologies CR Agreement
5.3.28.4TS 38.533
Yes
Yesr1
revised No R5‑255315  
R5‑254494 Addition of new test case 8.1.3.5.11 for NR UAV China Unicom CR Agreement
6.3.31.3TS 38.523-1
No
Yes
withdrawn Yes    
R5‑254495 Correction of Inter-RAT cell reselection test case 6.2.3.6 Qualcomm Incorporated CR Agreement
6.5.3.1Idle Mode
Yes
Yes
revised No R5‑254922  
R5‑254496 Addition of CEN alignment test case 21.31 Qualcomm Incorporated CR Agreement
6.3.29.10TS 34.229-1
Yes
Yes
agreed No    
R5‑254497 Correction of logged MDT test case 8.6.3.4 Qualcomm Incorporated CR Agreement
6.5.3.3.5RRC LTE MDT (clause 8.6)
Yes
Yes
agreed No    
R5‑254498 Updates to eCall over IMS procedures Qualcomm Incorporated CR Agreement
6.3.29.10TS 34.229-1
Yes
Yesr1
revised No R5‑254971  
R5‑254499 Updates to NR eCall over IMS procedures Qualcomm Incorporated CR Agreement
6.3.29.13TS 34.229-5
Yes
Yesr1
revised No R5‑254978  
R5‑254500 Correction to A.2.19 Qualcomm Incorporated , Rohde & Schwarz CR Agreement
6.3.29.10TS 34.229-1
Yes
Yes
agreed No    
R5‑254501 Correction to P-Access-Network-Info header for RedCap UEs Qualcomm Incorporated, Keysight CR Agreement
6.6.6.1TS 34.229-1
Yes
YesWIC was inverted r2
revised No R5‑254960  
R5‑254502 Discussion on support of NR RedCap in P-Access-Network-Info header field Qualcomm India Pvt Ltd discussion Discussion
6.6.6.6Discussion Papers, Work Plan, TC lists
Yes
YesNoted, proposals accepted. Grace period until RAN5#110.
noted No    
R5‑254503 Applicability updates to EPS eCall test cases for CEN alignments Qualcomm Incorporated CR Agreement
6.3.29.11TS 34.229-2
Yes
Yes
agreed No    
R5‑254504 Correction to applicability of interRAT test cases Qualcomm Incorporated, MCC TF160 CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yesr1
revised No R5‑254925  
R5‑254505 Updates to RTT test case 19.1.7 Qualcomm India Pvt Ltd CR Agreement
6.6.6.1TS 34.229-1
Yes
Yeslate doc r2
revised No R5‑254963  
R5‑254506 Correction to SSAC test case 13.5.1 Qualcomm India Pvt Ltd CR Agreement
6.5.3.8Multilayer Procedures
Yes
Yeslate doc r1
revised No R5‑255062  
R5‑254507 Correction to USIM configuration for eCall over EPS capable UEs Qualcomm Incorporated, Rohde & Schwarz CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
Yes
revised No R5‑254920  
R5‑254508 Correction to USIM configuration 23 Qualcomm Incorporated, Rohde & Schwarz CR Agreement
6.4.1.4Test environment for SIG (Clause 6)
Yes
Yes
agreed No    
R5‑254509 Addition of UE capability for new three bands and new four bands NRCA combos within FR1 KDDI Corporation (TTC) CR Agreement
5.3.2.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254510 Core alignment for LTM PCell switch test cases 6.3.4.3 and 6.3.4.4 MediaTek Inc., Keysight Technologies CR Agreement
5.3.28.4TS 38.533
Yes
Yesr1
revised No R5‑255316  
R5‑254511 Addition of reference sensitivity TP analysis for new three bands and new four bands NRCA combos within FR1 KDDI Corporation (TTC) CR Agreement
5.3.2.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
revised No R5‑255241  
R5‑254512 Updates of test applicability for LTM FR1 test cases MediaTek Inc., Keysight Technologies CR Agreement
5.3.28.3TS 38.522
Yes
Yesr1
revised No R5‑255317  
R5‑254513 Addition of Inter-RAT cell reselection test case 6.2.3.36 Qualcomm Incorporated CR Agreement
6.5.3.1Idle Mode
Yes
Yesr1
revised No R5‑254923  
R5‑254514 Removing duplicate conditions for test case selection expression Qualcomm Sweden CR Agreement
6.4.5TS 38.523-2
Yes
Yeslate doc
agreed No    
R5‑254515 Addition of Inter-RAT cell reselection test case 6.2.3.37 Qualcomm Incorporated CR Agreement
6.5.3.1Idle Mode
Yes
Yesr1
revised No R5‑254924  
R5‑254516 Applicability updates for protection against improper interRAT reselection test cases Qualcomm Incorporated CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yes
revised No R5‑254926  
R5‑254517 Addition of reference sensitivity requirement for new 4DL CA combo within FR1 KDDI Corporation (TTC) CR Agreement
5.3.2.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254518 Discussion on test coverage for NG eCall alignment CEN cases 6 to 9 Qualcomm Incorporated discussion Discussion
6.3.29.14Discussion Papers, Work Plan, TC lists
Yes
Yesnoted, proposals are accepted.
noted No    
R5‑254519 Addition of eCall only mode test case 11.3.9 Qualcomm Incorporated CR Agreement
6.3.29.7TS 36.523-1
Yes
Yesr1
revised No R5‑254969  
R5‑254520 Addition of REFSENS TP analysis for Rel16 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yesr1
revised No R5‑255224  
R5‑254521 Applicability addition for EPS CEN test cases Qualcomm Incorporated CR Agreement
6.3.29.8TS 36.523-2
Yes
Yesr1
revised No R5‑254970  
R5‑254522 Addition of EPS CEN alignments test case 21.32 Qualcomm Incorporated CR Agreement
6.3.29.10TS 34.229-1
Yes
Yes
agreed No    
R5‑254523 Addition of REFSENS TP analysis for Rel17 NR CA configuration NTT DOCOMO INC. CR Agreement
5.3.2.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254524 Addition of applicability for EPS CEN test cases Qualcomm Incorporated CR Agreement
6.3.29.11TS 34.229-2
Yes
Yes
agreed No    
R5‑254525 WP UE Conformance – Multi-carrier enhancements for NR China Telecom, Huawei, HiSilicon Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254526 SR UE Conformance – Multi-carrier enhancements for NR China Telecom, Huawei, HiSilicon WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254527 Addition of REFSENS TP analysis for Rel18 HPUE NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.10.6TR 38.905 (NR Test Points Radio Transmission and Reception )
Yes
Yesr1
revised No R5‑255220  
R5‑254528 Addition of REFSENS TP analysis for Rel18 PC3 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.12.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yesr1
revised No R5‑255229  
R5‑254529 Addition of test frequencies for Rel16 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.1.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254530 Addition of test frequencies for Rel17 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.2.1.1Test frequencies (Clause 4.3.1)
Yes
Yesr1
revised No R5‑255204  
R5‑254531 Addition of test frequencies for Rel18 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.12.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254532 Addition of UE capability for Rel15 NR CA configuration NTT DOCOMO INC. CR Agreement
5.4.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254533 Addition of UE capability for Rel16 NR CA configuration NTT DOCOMO INC. CR Agreement
5.3.1.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254534 Addition of UE capability for Rel17 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.2.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254535 Addition of UE capability for Rel18 PC2 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.10.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254536 PRD21 CDS: PC3 NR-CA R16 CA_n3A-n28A-n77(2A) KDDI Corporation (TTC) other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
Yes
Yes
noted No    
R5‑254537 Addition of UE capability for Rel18 PC3 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.12.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254538 PRD21 CDS: PC3 NR-CA R17 Combos KDDI Corporation (TTC) other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
Yes
Yes
noted No    
R5‑254539 PRD21 CDS: PC3 NR-CA CA_n3A-n77(2A) KDDI Corporation (TTC) other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
Yes
Yes
noted No    
R5‑254540 Addition of new UAV Test Case 8.1.3.5.9 Test Case for event A4H1 reporting for Intra-Frequency Neighbour China Unicom CR Agreement
6.3.31.3TS 38.523-1
Yes
YesMediaTek, Huawei, QC and CATT 's offline comments r2
revised No R5‑255046  
R5‑254541 Addition of new UAV Test Case 8.1.3.5.10 Test Case for event A4H1 reporting for Inter-Frequency Neighbour China Unicom CR Agreement
6.3.31.3TS 38.523-1
Yes
YesETSI MCC: title header formats
revised No R5‑255059  
R5‑254542 Addition of new UAV Test Case 8.1.3.5.11 Test Case for event A4H1 reporting for Inter-Band Neighbour China Unicom CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes
revised No R5‑255060  
R5‑254543 Addition of event A4H1 configs for NR UAV in Table 4.6.3-142 China Unicom CR Agreement
6.3.31.1TS 38.508-1
Yes
Yesmerged into R5-244280
withdrawn Yes    
R5‑254544 Discussion on addition of test coverage for Rel-17 Search space set group switching Qualcomm Incorporated discussion Discussion
6.4.7Discussion Papers, Work Plan, TC lists
Yes
YesNoted, proposal accepted.
revised No R5‑254931  
R5‑254545 Default message content updates for SSSG switching Qualcomm Incorporated CR Agreement
6.4.1.2Default NG-RAN RRC messages and IEs (Clause 4.6)
Yes
Yesfirst agreed, than deferred.
withdrawn Yes    
R5‑254546 Updating message contents for NTN measurement accuracy test cases Huawei, HiSilicon CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑254547 Addition of applicability for ATG RRM test cases Huawei, HiSilicon CR Agreement
5.3.13.5TS 38.522
Yes
YesMerged into CMCC’s jumbo CR R5-253882.
withdrawn Yes    
R5‑254548 Addition of ATG CSI-RS based inter-frequency measurement accuracy test cases Huawei, HiSilicon CR Agreement
5.3.13.6TS 38.533
Yes
Yesr1
revised No R5‑255381  
R5‑254549 Addition of ATG L1 and CGI measurement reporting test cases Huawei, HiSilicon CR Agreement
5.3.13.6TS 38.533
Yes
Yes"RAN4 dependency: R4-2510543 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254550 Updating cell mapping for ATG RRM test cases Huawei, HiSilicon CR Agreement
5.3.13.6TS 38.533
Yes
Yesoverlap with R5-253889
agreed No    
R5‑254551 Updating message contents and test procedures for ATG CSI-RS based intra-frequency measurement accuracy test cases Huawei, HiSilicon CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254552 Correction to ATG L1-RSRP accuracy RRM test cases 19.6.4.x with TT Huawei, HiSilicon CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254553 Correction to ATG L1-SINR accuracy RRM test cases 19.6.5.x with TT Huawei, HiSilicon CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254554 TT analysis for ATG L1-RSRP accuracy RRM test cases 19.6.4.x Huawei, HiSilicon CR Agreement
5.3.13.7TR 38.903 (NR MU & TT analyses)
Yes
Yesr1
revised No R5‑255327  
R5‑254555 TT analysis for ATG L1-SINR accuracy RRM test cases 19.6.5.x Huawei, HiSilicon CR Agreement
5.3.13.7TR 38.903 (NR MU & TT analyses)
Yes
Yesr1
revised No R5‑255328  
R5‑254556 Correction to connection diagram used in 4T UL MIMO and TxD Tx test cases Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254557 Correction to connection diagram used in 4T UL MIMO and TxD Rx test cases Huawei, HiSilicon CR Agreement
5.3.19.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254558 Addition of max input level test cases for 4T UL MIMO and TxD Huawei, HiSilicon CR Agreement
5.3.19.3.2Rx Requirements (Clause 7)
Yes
Yesr2
revised No R5‑255259  
R5‑254559 Addition of wide band IM test cases for 4T UL MIMO and TxD Huawei, HiSilicon CR Agreement
5.3.19.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254560 Updating EPRE ratio of AP CSI-RS to SSS for Rel-18 Tx switching test cases Huawei, HiSilicon CR Agreement
5.3.22.5TS 38.533
Yes
Yesfor email agreement
for email agreement No    
R5‑254561 Updating message contents and test procedures for FeMG test cases Huawei, HiSilicon CR Agreement
5.3.32.4TS 38.533
Yes
Yes
revised No R5‑255314  
R5‑254562 Updating default configuration of RRC IEs for 2-step RACH RRM test cases Huawei, HiSilicon, Starpoint CR Agreement
5.4.1.3Test environment for RRM (Clause 7)
Yes
Yes
agreed No    
R5‑254563 Updating Timer 310 value for EN-DC RLM In-Sync test cases Huawei, HiSilicon, Starpoint CR Agreement
5.4.10.1EN-DC with all NR cells in FR1 (Clause 4)
Yes
Yes
withdrawn Yes    
R5‑254564 Updating message contents for Rel-15 measurement accuracy test cases Huawei, HiSilicon CR Agreement
5.4.10.1EN-DC with all NR cells in FR1 (Clause 4)
Yes
Yes
agreed No    
R5‑254565 Updating EPRE ratio of AP CSI-RS to SSS for Rel-16 and Rel-17 Tx switching test cases Huawei, HiSilicon CR Agreement
5.4.10.4NR Standalone in FR1 (Clause 6)
Yes
Yesr1
revised No R5‑255383  
R5‑254566 Updating message contents for NR-U measurement accuracy test cases Huawei, HiSilicon CR Agreement
5.4.10.8EN-DC Tests with NR PSCell under CCA and Other NR Cells in FR1 (Clause 10)
Yes
Yes
agreed No    
R5‑254567 Updating IE contents exceptions in Annex H for measurement accuracy test cases Huawei, HiSilicon CR Agreement
5.4.10.15Clauses 1-3, Annexes
Yes
Yes
agreed No    
R5‑254568 Updating reporting offset of AP L1-RSRP for Tx switching test cases Huawei, HiSilicon, MediaTek CR Agreement
5.4.10.15Clauses 1-3, Annexes
Yes
Yes
agreed No    
R5‑254569 Correction to LTE Cat 1bis RRM test case 5.1.19 and 5.1.20 Huawei, HiSilicon CR Agreement
5.5.1.4TS 36.521-3
Yes
Yesr1
revised No R5‑255344  
R5‑254570 Updating TT analysis for LTE Cat 1bis RRM test case 5.1.19 and 5.1.20 Huawei, HiSilicon CR Agreement
5.5.1.7.1TR 36.903 (E-UTRAN RRM TT analyses)
No
Yes
withdrawn Yes    
R5‑254571 Correction to LTE measurement reporting test case 8.1.3 Huawei, HiSilicon CR Agreement
5.5.1.4TS 36.521-3
Yes
Yesr2
revised No R5‑255413  
R5‑254572 Correction to V2X SIG test case 12.1.9.1.1 - UM RLC segmentation Huawei, HiSilicon CR Agreement
6.4.4.12NR Sidelink (clauses 12 & 13)
Yes
YesCR cover value : 19.0.0! r1
revised No R5‑254938  
R5‑254573 Correction to V2X SIG test case 12.1.9.2.2 - AM polling Huawei, HiSilicon CR Agreement
6.4.4.12NR Sidelink (clauses 12 & 13)
Yes
YesCR cover value : 19.0.0! r2
revised No R5‑254939  
R5‑254574 SR of FR2 FWA with 23dBm TRP for band n257 and n258 Huawei, HiSilicon WI status report Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254575 WP of FR2 FWA with 23dBm TRP for band n257 and n258 Huawei, HiSilicon Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254576 SR of Further RF requirements enhancement for NR and EN-DC in FR1 Huawei, HiSilicon WI status report Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254577 WP of Further RF requirements enhancement for NR and EN-DC in FR1 Huawei, HiSilicon Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254578 DCI format updates for SSSG switching Qualcomm Incorporated CR Agreement
6.4.1.5Other clauses, Annexes
Yes
Yesr1
revised No R5‑255066  
R5‑254579 Addition of PICS for SSSG switching Qualcomm Incorporated CR Agreement
6.4.2TS 38.508-2
Yes
Yesr1
revised No R5‑254933  
R5‑254580 Addition of test case for Search Space Set Group Switching Qualcomm Incorporated CR Agreement
6.4.4.3.1.2MAC
Yes
Yesr2
revised No R5‑255068  
R5‑254581 Revised WID on UE Conformance - NR sidelink enhancement CATT WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yesis endorsed
agreed No    
R5‑254582 WP UE Conformance - NR sidelink enhancement CATT Work Plan Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254583 SR UE Conformance - NR sidelink enhancement CATT WI status report Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254584 Revised WID on UE Conformance - NR Sidelink Relay CATT WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yesis endorsed +3 months
agreed No    
R5‑254585 WP UE Conformance - NR Sidelink Relay CATT Work Plan Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254586 SR UE Conformance - NR Sidelink Relay CATT WI status report Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254587 WP UE Conformance - Enhancements of NR Multicast and Broadcast Services CATT Work Plan Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254588 SR UE Conformance - Enhancements of NR Multicast and Broadcast Services CATT WI status report Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254589 Addition of new test case 12.2.11.1 TDIA, CATT CR Agreement
6.3.5.3TS 38.523-1
Yes
Yes
agreed No    
R5‑254590 Addition of new test case 12.2.11.2 TDIA, CATT CR Agreement
6.3.5.3TS 38.523-1
Yes
Yesreissued as R5-254905 because of title change (TC number)
withdrawn Yes    
R5‑254591 Update of Table 4.6.1A-3 RRCReconfigurationSidelink TDIA, CATT CR Agreement
6.3.5.1TS 38.508-1
Yes
Yesr1
revised No R5‑254952  
R5‑254592 Addition of contents of PC5 RRC UEAssistanceInformationSidelink message TDIA, CATT CR Agreement
6.3.5.1TS 38.508-1
Yes
Yesr1
revised No R5‑254953  
R5‑254593 Update of Table 4.6.2-14A SIB12-IEs TDIA, CATT CR Agreement
6.3.5.1TS 38.508-1
Yes
YesTdoc! r1
revised No R5‑254954  
R5‑254594 Update of Table 4.6.6-7 SL-ConfigDedicatedNR TDIA, CATT CR Agreement
6.3.5.1TS 38.508-1
Yes
YesMotorola Mobility: unicast, groupcast and/or broadcast is not needed.
revised No R5‑254955  
R5‑254595 Update of Tables related to SL DRX configuration TDIA, CATT CR Agreement
6.3.5.1TS 38.508-1
Yes
Yes
agreed No    
R5‑254596 Addition of NR Sidelink Capabilities for NR Sidelink DRX testcases TDIA, CATT CR Agreement
6.3.5.2TS 38.508-2
Yes
YesTdoc! r1
revised No R5‑254956  
R5‑254597 Addition of test applicabilities for new sidelink enhancement testcases CATT, TDIA CR Agreement
6.3.5.4TS 38.523-2
Yes
Yesr1 resolve /aa !
revised No R5‑254957  
R5‑254598 Addition of new test case 9.1.6.3 NR SA FR1 Interruptions at NR sidelink discovery configuration CATT, TDIA CR Agreement
5.3.6.5TS 38.533
Yes
Yes
revised No R5‑255320  
R5‑254599 Addition of new test case 9.1.7.1 Selection / Reselection of relay UE TDIA, CATT CR Agreement
5.3.6.5TS 38.533
Yes
Yesr1
revised No R5‑255321  
R5‑254600 Correction of Table 4.6.6-2: SL-BWP-ConfigCommon TDIA, CATT CR Agreement
6.3.4.1TS 38.508-1
Yes
Yes
withdrawn Yes    
R5‑254601 Correction of test case 12.3.1.1.17 Sidelink Relay / L2 U2N / Remote UE / Sidelink RRC reconfiguration TDIA, CATT CR Agreement
6.3.4.3TS 38.523-1
Yes
Yes
agreed No    
R5‑254602 Correction of test case 12.3.1.2.11 Sidelink Relay / L2 U2N / Relay UE / RRC reconfiguration / Uu Relay RLC channel configuration TDIA, CATT CR Agreement
6.3.4.3TS 38.523-1
Yes
Yes
agreed No    
R5‑254603 Correction of test case 12.3.1.2.15 Sidelink Relay / L2 U2N / Relay UE / Sidelink RRC reconfiguration TDIA, CATT CR Agreement
6.3.4.3TS 38.523-1
Yes
Yes
agreed No    
R5‑254604 Addition of USIM Configurations for 5G ProSe TDIA, CATT CR Agreement
6.3.4.1TS 38.508-1
Yes
Yes
agreed No    
R5‑254605 Update of 38.508-1 table 4.7C.1.5-11 TDIA, CATT CR Agreement
6.3.4.1TS 38.508-1
Yes
Yes
agreed No    
R5‑254606 Update of NR sidelink U2N Relay test cases TDIA, CATT CR Agreement
6.3.4.3TS 38.523-1
Yes
Yes
agreed No    
R5‑254607 Update of RRC messages for MBS Multicast reception in RRC_INACTIVE TDIA, CATT CR Agreement
6.3.30.1TS 38.508-1
Yes
Yesr1
revised No R5‑255039  
R5‑254608 Update of test case 6.5.3.13 TDIA, CATT CR Agreement
6.3.21.3TS 38.523-1
Yes
Yes
agreed No    
R5‑254609 Addition of applicability for SSSG switching test cases Qualcomm Incorporated CR Agreement
6.4.5TS 38.523-2
Yes
Yesr2
revised No R5‑255073  
R5‑254610 Addition of applicability for new UAV test cases 8.1.3.5.9,8.1.3.5.10 and 8.1.3.5.11 China Unicom CR Agreement
6.3.31.4TS 38.523-2
Yes
Yesr1
revised No R5‑255061  
R5‑254611 Correction to NR eCall testcases 11.10, 11.11 and 11.12 ROHDE & SCHWARZ, Keysight, Anritsu Ltd, Qualcomm CR Agreement
6.3.29.13TS 34.229-5
Yes
Yesr1
revised No R5‑254979  
R5‑254612 Addition of new test case AMPR, ASEM and ASE for 4Tx UL MIMO Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
revised No R5‑255258  
R5‑254613 Addition of new test case AMPR, ASEM, ASE for 4Tx Tx Diversity Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255354  
R5‑254614 Power control for UL MIMO and TxD for UE supporting 4Tx Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254615 Adding test frequencies for CA configurations including band n71 Huawei, HiSilicon CR Agreement
5.3.35.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254616 Adding PICS for several CA configurations including band n71 Huawei, HiSilicon CR Agreement
5.3.35.2TS 38.508-2
Yes
Yesoverlap with R5-254799 r1
revised No R5‑255214  
R5‑254617 TP analysis for REFSENS for several CA configurations including band n71 Huawei, HiSilicon CR Agreement
5.3.35.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254618 Addition of new CA configurations including band n71 and n77 for transmitter characteristics Huawei, HiSilicon CR Agreement
5.3.35.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254619 Adding CA configurations CA_n28-n40-n77 and CA_n40-n71-n77 for RENSENS Huawei, HiSilicon CR Agreement
5.3.35.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254620 Addition of reference sensitivity for Rel-19 3CC EN-DC configurations including n71A-n77A Huawei, HiSilicon CR Agreement
5.3.35.5.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254621 Adding testing for NS_47 for power class 2 and 3 in AMPR for UL MIMO Huawei, HiSilicon CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes#107! r1
revised No R5‑255239  
R5‑254622 Correction of testing potints for NS_47 in AMPR for UL MIMO Huawei, HiSilicon CR Agreement
5.4.19TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254623 Addition of connecting diagram for Tx switching test cases Huawei, HiSilicon CR Agreement
5.3.22.1TS 38.508-1
Yes
Yes
revised No R5‑255207  
R5‑254624 Update of baseline implementation capabilities of FR1 NR CA for switching test cases Huawei, HiSilicon CR Agreement
5.3.22.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254625 Addition of applicability of FR1 time mask for switching test cases Huawei, HiSilicon CR Agreement
5.3.22.4TS 38.522
Yes
Yes
agreed No    
R5‑254626 Updating time mask test cases for switching across three and four uplink bands Huawei, HiSilicon CR Agreement
5.3.22.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254627 Adding testing for CA_n8A-n78A for Power Class 2 UE in maximum output power Huawei, HiSilicon CR Agreement
5.3.10.3.1Tx Requirements (Clause 6)
Yes
Yeshad wrong WIC r1
revised No R5‑255249  
R5‑254628 TP analysis for REFSENS for CA_n8A_n78A for PC2 UE Huawei, HiSilicon CR Agreement
5.3.10.6TR 38.905 (NR Test Points Radio Transmission and Reception )
Yes
Yeshad wrong WIC r1
revised No R5‑255222  
R5‑254629 Updating additional spurious emissions test case for message contents Huawei, HiSilicon CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254630 Correction of NR SA FR2-FR2 event triggered reporting using MUSIM gap with shorter MGRP test case 7.6.2.21 with TT Huawei, HiSilicon CR Agreement
5.4.10.5NR standalone with at least one NR cell in FR2 (Clause7)
Yes
Yes
agreed No    
R5‑254631 TT analysis for RRM TC 7.6.2.21 NR SA FR2-FR2 event triggered reporting using MUSIM gap with shorter MGRP Huawei, HiSilicon CR Agreement
5.4.18TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254632 Addition of REFSENS for Rel17 PC3 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.2.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254633 Discussion on the optimization of Out-of-band Blocking (OOBB) testing Huawei, Hisilicon discussion Approval
5.4.20Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No    
R5‑254634 Addition of REFSENS for Rel18 PC2 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.10.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254635 Updating frequency range for MU for CSI reporting test cases Ericsson CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No    
R5‑254636 Correction of editors note in NR-U test case 7.3F Ericsson CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254637 On out of band blocking Ericsson, Verizon discussion Endorsement
5.4.20Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No    
R5‑254638 Addition of eRedCap test case 5.2.2.1.23, 2Rx FDD FR1 PDSCH performance for eRedCap Ericsson CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yesr1
revised No R5‑255355  
R5‑254639 Addition of eRedCap test case 6.2.2.1.2.5 Ericsson CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yesr1
revised No R5‑255357  
R5‑254640 Addition of MU and TT for new eRedCap test cases Ericsson CR Agreement
5.3.15.4.4Clauses 1-4, Annexes
Yes
Yes
agreed No    
R5‑254641 Addition of test case 5.3.3.1.6 4RX FDD FR1 PDCCH antenna performance for 3 MHz channel bandwidth Ericsson CR Agreement
5.3.37.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yesr1
revised No R5‑255411  
R5‑254642 Addition of new eRedCap test cases in 38.522 Ericsson CR Agreement
5.3.15.5TS 38.522
Yes
Yes
agreed No    
R5‑254643 Addition of new test case in 38.522 Ericsson CR Agreement
5.3.14.5TS 38.522
Yes
Yes
agreed No    
R5‑254644 Addition of applicability of RedCap test case 5.3.1.2.1 Ericsson CR Agreement
5.4.9TS 38.522
Yes
YesWIC was changed r1
revised No R5‑255339  
R5‑254645 WP for UE Conformance - NR PC2 RedCap UE China Telecom Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254646 Status Report for UE Conformance - NR PC2 RedCap UE China Telecom WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254647 Addition of delta TIBc and MOP for Rel16 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.1.3.1Tx Requirements (Clause 6)
Yes
Yesoverlap with R5-254791 r1
revised No R5‑255261  
R5‑254648 Addition of delta TIBc for Rel17 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.2.3.1Tx Requirements (Clause 6)
Yes
Yesoverlap with R5-254791 r1
revised No R5‑255262  
R5‑254649 Addition of delta TIBc and MOP for Rel18 PC3 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.12.3.1Tx Requirements (Clause 6)
Yes
Yesoverlap with R5-254791 r1
revised No R5‑255263  
R5‑254650 Addition of MOP for Rel18 PC2 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.10.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254651 Adding UTRA_ACLR applicablity for ACLR requirements for PC3 vivo CR Agreement
5.5.1.6TS 36.521-2
Yes
Yes
agreed No    
R5‑254652 Removing Editor notes for UTRA_ACLR applicablity for PC3 vivo CR Agreement
5.5.1.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254653 Update applicability for test case 11.3.5 Ericsson CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No    
R5‑254654 Update to FR1 CA Configurations for R17 PC2 band combo NTT DOCOMO INC. CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
YesWIC was inverted r1
revised No R5‑255270  
R5‑254655 Update to FR1 CA Configurations for R1 PC2 and PC1.5 band combos NTT DOCOMO INC. CR Agreement
5.3.10.3.3Clauses 1-5, Annexes
Yes
Yes
revised No R5‑255251  
R5‑254656 Resubmission of R5-253188 for correction to the PICS parameter pc_nrMIMO_CB_PUSCH Keysight Technologies UK CR Agreement
6.4.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254657 WP UE Conformance - Enhanced NR support for high speed train scenario in frequency range 2 (FR2) Samsung Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254658 SR UE Conformance - Enhanced NR support for high speed train scenario in frequency range 2 (FR2) Samsung WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254659 WP UE Conformance - NR MIMO Evolution for Downlink and Uplink Samsung, Huawei, China Telecom Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254660 SR UE Conformance - NR MIMO Evolution for Downlink and Uplink Samsung, Huawei, China Telecom WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254661 WP UE Conformance - NR support for high speed train scenario in frequency range 2 Samsung, Nokia Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254662 SR UE Conformance - NR support for high speed train scenario in frequency range 2 Samsung, Nokia WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254663 PRD21 CDS: NR CA PC3 R15 Combo NTT DOCOMO INC. other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
No
reserved No    
R5‑254664 PRD21 CDS: NR CA PC3 R16 Combos NTT DOCOMO INC. other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
No
reserved No    
R5‑254665 PRD21 CDS: NR CA PC3 R17 Combos NTT DOCOMO INC. other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
No
reserved No    
R5‑254666 PRD21 CDS: NR CA PC2 R17 Combos NTT DOCOMO INC. other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
No
reserved No    
R5‑254667 PRD21 CDS: NR CA PC3 R18 Combos NTT DOCOMO INC. other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
No
reserved No    
R5‑254668 PRD21 CDS: NR CA PC2 R18 Combos NTT DOCOMO INC. other Information
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
No
reserved No    
R5‑254669 Corrections to assumed PUSCH PHR MAC Test case Lenovo, Motorola Mobility, MCC TF160 CR Agreement
6.3.14.3TS 38.523-1
Yes
Yes"---- WI code inconsistency ----: 3GU: NR_MC_enh-UEConTest CR coversheet: NR_cov_enh2-UEConTest"
revised No R5‑255000  
R5‑254670 Corrections to assumed RACH Msg1 repetition Test case Lenovo, Motorola Mobility, MCC TF160 CR Agreement
6.3.14.3TS 38.523-1
Yes
Yes"---- WI code inconsistency ----: 3GU: NR_MC_enh-UEConTest CR coversheet: NR_cov_enh2-UEConTest"
agreed No    
R5‑254671 Corrections to MT-SDT 4-Step RACH MAC Test case Lenovo, Motorola Mobility, MCC TF160 CR Agreement
6.3.19.3TS 38.523-1
Yes
Yes/ ETSI MCC: table number fix.
revised No R5‑254950  
R5‑254672 Corrections to DPC PHR MAC Test case Lenovo, Motorola Mobility, MCC TF160 CR Agreement
6.3.14.3TS 38.523-1
Yes
Yes
agreed No    
R5‑254673 New WID on UE Conformance - Multi-carrier enhancements for NR Phase 3 Lenovo, Motorola Mobility WID new Information
4.1New Work Item proposals - for intro only
Yes
Yesfor information. Vodafone asked to be added.
revised No R5‑254916  
R5‑254674 Test Tolerance update for HD-FDD UE Timing Advance Adjustment Accuracy Test 7.2.9,13.4.2.1 and 13.4.2.2. Qualcomm Korea CR Agreement
5.5.1.4TS 36.521-3
Yes
Yes"---- WI code inconsistency ----: 3GU: TEI18_Test CR coversheet: TEI18_Test, LTE_NBIOT_eMTC_NTN_req-UEConTest" r1
revised No R5‑255419  
R5‑254675 Test Tolerance update in Annex F for NB-NTN UE Timing Advance Adjustment Accuracy test cases. Qualcomm Korea CR Agreement
5.5.1.4TS 36.521-3
Yes
Yes"---- Spec # inconsistency ----: 3GU: 36.521-3 CR coversheet: 38.521-3 ---- WI code inconsistency ----: 3GU: TEI18_Test CR coversheet: TEI18_Test, LTE_NBIOT_eMTC_NTN_req-UEConTest" r1
revised No R5‑255420  
R5‑254676 Test Tolerance analysis update for UE Timing Advance Adjustment Accuracy Test 7.2.9,13.4.2.1 and 13.4.2.2. Qualcomm Korea CR Agreement
5.5.1.7.1TR 36.903 (E-UTRAN RRM TT analyses)
Yes
Yes"---- WI code inconsistency ----: 3GU: TEI18_Test CR coversheet: TEI18_Test, LTE_NBIOT_eMTC_NTN_req-UEConTest" pending discussions
withdrawn Yes    
R5‑254677 Test Tolerance update for intra-frequency RACH-less Handover for Satellite Access test 14.2.1.8. Qualcomm Korea CR Agreement
5.3.30.6TS 38.533
Yes
YesWIC changed r1
revised No R5‑255363  
R5‑254678 Test Tolerance update for RACH-based Hard Satellite switching for Satellite Access test 14.2.2.4. Qualcomm Korea CR Agreement
5.3.30.6TS 38.533
Yes
YesWIC changed r1
revised No R5‑255364  
R5‑254679 Test Tolerance update for RACH-less Soft Satellite switching for Satellite Access test 14.2.2.5. Qualcomm Korea CR Agreement
5.3.30.6TS 38.533
Yes
YesWIC changed r1
revised No R5‑255365  
R5‑254680 Test Tolerance update in Annex F for NR NTN handover and Satellite switching test cases. Qualcomm Korea CR Agreement
5.3.30.6TS 38.533
Yes
YesWIC changed r1
revised No R5‑255366  
R5‑254681 Test Tolerance analysis for intra-frequency RACH-less Handover for Satellite Access test 14.2.1.8. Qualcomm Korea CR Agreement
5.3.30.7TR 38.903 (NR MU & TT analyses)
Yes
YesWIC changed r1
revised No R5‑255367  
R5‑254682 Test Tolerance analysis for intra-frequency RACH-based Hard Satellite switching for Satellite Access test 14.2.2.4. Qualcomm Korea CR Agreement
5.3.30.7TR 38.903 (NR MU & TT analyses)
Yes
YesWIC changed r1
revised No R5‑255368  
R5‑254683 Test Tolerance analysis for intra-frequency RACH-less Soft Satellite switching for Satellite Access test 14.2.2.5. Qualcomm Korea CR Agreement
5.3.30.7TR 38.903 (NR MU & TT analyses)
Yes
YesWIC changed r1
revised No R5‑255369  
R5‑254684 Core alignment for NR-NTN CBW change test case. Qualcomm Korea CR Agreement
5.3.4.6TS 38.533
Yes
Yesr1
revised No R5‑255289  
R5‑254685 Core alignment and update for NR-NTN Cell reselection test cases. Qualcomm Korea CR Agreement
5.3.4.6TS 38.533
Yes
Yes Discussing with R&S to remove the Overlap with CR R5-254157. r5
revised No R5‑255414  
R5‑254686 Core alignment for NR-NTN DCI-based BWP switch test case. Qualcomm Korea CR Agreement
5.3.4.6TS 38.533
Yes
Yesr1
revised No R5‑255290  
R5‑254687 Annex H update for NR-NTN idle mode test case. Qualcomm Korea CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑254688 Core alignment for NR-NTN RRC-based BWP switch test case. Qualcomm Korea CR Agreement
5.3.4.6TS 38.533
Yes
Yesr1
revised No R5‑255291  
R5‑254689 Additional of A-MPR test case for NS 205 in TS 38.521-2 China Unicom CR Agreement
5.3.42.1.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255231  
R5‑254690 Additional of A-MPR test case for NS 205 in TS 38.905 China Unicom CR Agreement
5.3.42.3TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yescl. aff. r1
revised No R5‑255230  
R5‑254691 Updating TT analysis for LTE Cat 1bis RRM test case 5.1.19 and 5.1.20 Huawei, HiSilicon CR Agreement
5.5.1.7.1TR 36.903 (E-UTRAN RRM TT analyses)
Yes
Yes
withdrawn Yes    
R5‑254692 Corrections to testcase 7.1.1.14.2.3 Nokia CR Agreement
6.3.13.3TS 38.523-1
Yes
Yes
withdrawn Yes    
R5‑254693 Update test cases 7.11 Ericsson CR Agreement
6.6.6.5TS 34.229-5
Yes
Yes
agreed No    
R5‑254694 Handling of test frequency tables containing too many BW combinations. Ericsson discussion Endorsement
4.2.15GS
Yes
Yesr2 RAN4 has duplicated this. Deferred. Decision: we will replicate the frequency tables in FORGE to upload JSON files. RAN5 Vice Chair RF: we will need to review the outcome.
revised No R5‑255096  
R5‑254695 Test Frequency Calculation Tool, updates and way forward. Ericsson discussion Information
5.3.2.11Discussion Papers, Work Plan, TC lists
Yes
Yesr1
revised No R5‑255385  
R5‑254696 Discussion on Modernization of Specification Format and Procedures for 6G Ericsson, CATT, CMCC discussion Information
4.2.46G spec modernization & RAN5 aspects
Yes
Yesr1 Qualcomm: maybe set up a reflector. RAN5 Chair: this was decided. ->ETSI MCC
revised No R5‑255006  
R5‑254697 Test tolerance analysis for FR2 inter-frequency SSB-based L1-RSRP measurement test case 7.6.22.1 Ericsson CR Agreement
5.3.28.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
withdrawn Yes    
R5‑254698 Correction of FR2 inter-frequency SSB-based L1-RSRP measurement test case 7.6.22.1 including test tolerance Ericsson CR Agreement
5.3.28.4TS 38.533
Yes
Yes
withdrawn Yes    
R5‑254699 Annex F correction for L1-RSRP event-triggered reporting test cases 7.6.22.1 Ericsson CR Agreement
5.3.28.4TS 38.533
Yes
Yes
withdrawn Yes    
R5‑254700 Correction of CADC fast measurement test cases 6.6.9.x Ericsson CR Agreement
5.3.28.4TS 38.533
Yes
Yes
withdrawn Yes    
R5‑254701 Correction of NR SA FR2 PDCCH-order RACH test cases 7.3.2.4.x Ericsson CR Agreement
5.3.28.4TS 38.533
Yes
Yes"Depending on RAN4 CR R4-2511487 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254702 Correction of FR1 NR SA RACH-based LTM PSCell switch test case 6.3.5.1 Ericsson CR Agreement
5.3.28.4TS 38.533
Yes
Yesr1
revised No R5‑255318  
R5‑254703 Correction of NR FR2 SA RACH-based LTM PSCell switch test case 7.3.5.1 Ericsson CR Agreement
5.3.28.4TS 38.533
Yes
Yesr1
revised No R5‑255319  
R5‑254704 Applicability correction of mobility enhancements test cases Ericsson CR Agreement
5.3.28.3TS 38.522
No
Yeslate doc
withdrawn Yes    
R5‑254705 Test tolerance analysis for MG enhancement NR SA FR2 event-triggered reporting test cases Ericsson CR Agreement
5.3.32.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254706 Correction of event-triggered reporting test cases 7.6.19.x including test tolerance Ericsson CR Agreement
5.3.32.4TS 38.533
Yes
Yesr1
revised No R5‑255330  
R5‑254707 Annex F correction for event-triggered reporting test cases 7.6.19.x Ericsson CR Agreement
5.3.32.4TS 38.533
Yes
Yes
agreed No    
R5‑254708 Applicability correction of measurement gap enhancement test cases Ericsson CR Agreement
5.3.32.3TS 38.522
No
Yeslate doc
withdrawn Yes    
R5‑254709 Correction of NR SA FR2 event-triggered reporting with concurrent Type-2 measurement gap and NCSG test case 7.6.18.1 Ericsson CR Agreement
5.3.32.4TS 38.533
Yes
Yes
agreed No    
R5‑254710 Correction of SA event-triggered reporting for concurrent measurement gaps with Pre-MG in FR2 test cases 7.6.17.x Ericsson CR Agreement
5.3.32.4TS 38.533
Yes
Yes
agreed No    
R5‑254711 Correction of E-UTRAN - NR SA FR2 event-triggered reporting without gap with interruption test case 8.4.3.1 Ericsson CR Agreement
5.3.32.4TS 38.533
Yes
Yes
agreed No    
R5‑254712 Correction of ATG radio link monitoring test cases 19.4.1.x Ericsson CR Agreement
5.3.13.6TS 38.533
Yes
Yes
withdrawn Yes    
R5‑254713 Correction of ATG SA event-triggered reporting test cases 19.5.1.x Ericsson CR Agreement
5.3.13.6TS 38.533
Yes
Yes
revised No R5‑255310  
R5‑254714 Correction of ATG SA event-triggered reporting test cases 19.5.2.x Ericsson CR Agreement
5.3.13.6TS 38.533
Yes
Yes
revised No R5‑255311  
R5‑254715 Addition of new NR RSTD measurement reporting delay test cases for RedCap UE Ericsson CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No    
R5‑254716 Addition of new NR RSTD measurement accuracy test cases for RedCap UE Ericsson CR Agreement
5.3.27.2TS 37.571-1
Yes
Yesr1
revised No R5‑255334  
R5‑254717 E-UTRA - NR SA FR1 E-UTRA cell re-selection to higher-priority NR target cell for 2 Rx UE test case correction Ericsson CR Agreement
5.4.10.14E-UTRA - NR inter-RAT with E-UTRA serving cell (Clause 18)
Yes
Yeschanged to NR_redcap_plus_ARCH-UEConTest r3
revised No R5‑255323  
R5‑254718 Applicability of E-UTRA - NR SA FR1 E-UTRA cell re-selection to higher-priority NR target cell for 2 Rx UE test case Ericsson CR Agreement
5.4.9TS 38.522
Yes
Yeschanged to NR_redcap_plus_ARCH-UEConTest r1
revised No R5‑255340  
R5‑254719 Editorial correction of FR2 SA event-triggered reporting test without gap under non-DRX test case 7.6.2.10 Ericsson CR Agreement
5.3.8.4TS 38.533
Yes
Yes
agreed No    
R5‑254720 Update REGISTER with feature-param for text Ericsson CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
withdrawn Yes    
R5‑254721 Update INVITE with feature-param for text Ericsson CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
withdrawn Yes    
R5‑254722 Addition of new test case 6.2.17 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.6TS 37.579-7
Yes
Yesblock agreed on Thu r1
revised No R5‑255026  
R5‑254723 Update to LTE based 5G broadcast PBCH detection performance test cases. Qualcomm Korea CR Agreement
5.3.31.3TS 36.521-1
Yes
Yes
agreed No    
R5‑254724 Update to LTE based 5G broadcast PMCH decoding performance test cases. Qualcomm Korea CR Agreement
5.3.31.3TS 36.521-1
Yes
Yes
agreed No    
R5‑254725 Addition of PICS for NR NTN enhancements Qualcomm Incorporated CR Agreement
6.3.25.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254726 Addition of NR NTN enhancements test case 9.4.1.5 Qualcomm Incorporated CR Agreement
6.3.25.4TS 38.523-1
Yes
Yesr1
revised No R5‑254947  
R5‑254727 Applicability updates for NR NTN Enhancements test cases Qualcomm Incorporated CR Agreement
6.3.25.5TS 38.523-2
Yes
Yesr1
revised No R5‑255089  
R5‑254728 Correction of MAC test case 7.1.4.12 Qualcomm Incorporated CR Agreement
6.5.3.2.1MAC
No
Yeslate doc
withdrawn Yes    
R5‑254729 Correction to test procedure of 6.6.2.2EB A-SEM for cat 1bis Anritsu CR Agreement
5.5.1.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254730 Removal of Annex K.1 Anritsu CR Agreement
5.5.1.5TS 36.521-4
Yes
Yes
agreed No    
R5‑254731 Correction to test requirement of n26 in reference sensitivity Anritsu CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254732 Updated procedure to skip interferer overlapping with PCC in Rx TCs for 3CC later Anritsu, R&S, Keysight CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yesoverlap with R5-254381 r1
revised No R5‑255398  
R5‑254733 Update of Annex C for valid CORESET 0 Anritsu CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yesreissued as R5-255242 because of wrong spec
withdrawn Yes    
R5‑254734 Editorial corrections to 6.5B.3.3.2 Anritsu CR Agreement
5.4.6.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254735 Correction to cell mapping of LTE SCC for intra-band contiguous CA Anritsu CR Agreement
5.4.10.15Clauses 1-3, Annexes
Yes
Yes
agreed No    
R5‑254736 Definition of UL Mid CBW for n8 Anritsu CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254737 Correction to test frequencies of n105 Anritsu CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254738 Update of test frequencies for intra-band non-contiguous EN-DC in demod test cases Anritsu CR Agreement
5.4.1.2Test environment for RF (Clauses 5)
Yes
Yes
agreed No    
R5‑254739 Update of test frequencies for intra-band non-contiguous EN-DC in demod test cases Anritsu CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No    
R5‑254740 Correction to applicable release of 16Tx or 32Tx PMI reporting Anritsu CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No    
R5‑254741 Correction to applicable release of 16Tx or 32Tx PMI reporting Anritsu CR Agreement
5.4.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254742 Correction to applicable release of 16Tx or 32Tx PMI reporting Anritsu CR Agreement
5.4.9TS 38.522
Yes
Yes
agreed No    
R5‑254743 Correction to A-MPR for NS_03N NS_04N NS_05N Anritsu CR Agreement
5.4.8TS 38.521-5
Yes
Yes
agreed No    
R5‑254744 Clarification of LCRB in Figure 5.3.1-1 Anritsu CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yesr1
revised No R5‑255399  
R5‑254745 Correction to interferer offset of ACS for shared spectrum channel access Anritsu CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yes"Depending on RAN4 CR R4-2509858 Document was sent FOR E-MAIL AGREEMENT "
for email agreement No    
R5‑254746 Update of RMCs for FR1-NTN TRx testing with SCS 15 kHz and 30 kHz Anritsu CR Agreement
5.3.4.4TS 38.521-5
Yes
Yesr1
revised No R5‑255397  
R5‑254747 Cleanup of Reference sensitivity for 2DL CA Anritsu, Keysight Technologies UK Ltd CR Agreement
5.3.1.3.2Rx Requirements (Clause 7)
Yes
Yesoverlapping with R5-254051 r1
revised No R5‑255255  
R5‑254748 Addition of reference sensitivity requirements for Rel-16 2DL CA Anritsu, Huawei, HiSilicon, NTT DOCOMO INC. CR Agreement
5.3.1.3.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255223  
R5‑254749 Addition of reference sensitivity requirements for Rel-17 2DL CA Anritsu, Huawei, HiSilicon, NTT DOCOMO INC. CR Agreement
5.3.2.3.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255256  
R5‑254750 Addition of reference sensitivity requirements for Rel-17 2DL CA for PC2 Anritsu, Huawei, HiSilicon CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yesthe contents of this CR was moved to R5-254752r1
withdrawn Yes    
R5‑254751 Addition of reference sensitivity requirements for Rel-18 2DL CA Anritsu, Huawei, HiSilicon, NTT DOCOMO INC. CR Agreement
5.3.12.3.2Rx Requirements (Clause 7)
Yes
Yesoverlap with R5-254791 r1
revised No R5‑255228  
R5‑254752 Addition of reference sensitivity requirements for Rel-18 2DL CA for HPUE Anritsu, NTT DOCOMO INC., Huawei, HiSilicon CR Agreement
5.3.10.3.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255221  
R5‑254753 Addition of reference sensitivity requirements for Rel-19 2DL CA Anritsu, Huawei, HiSilicon CR Agreement
5.3.35.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254754 Cleanup of Reference sensitivity for 2CC FR1 EN-DC Anritsu, Keysight Technologies UK Ltd, KDDI Corporation, ZTE CR Agreement
5.3.1.5.2Rx Requirements (Clause 7)
Yes
Yesoverlap with R5-254330 (ZTE), R5-254083, R5-254315, R5-254330, R5-254336 r1
revised No R5‑255396  
R5‑254755 Addition of reference sensitivity requirements for Rel-15 FR1 2CC EN-DC Anritsu, Huawei, HiSilicon CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254756 Addition of reference sensitivity requirements for Rel-16 FR1 2CC EN-DC Anritsu, Huawei, HiSilicon CR Agreement
5.3.1.5.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255280  
R5‑254757 Addition of reference sensitivity requirements for Rel-18 FR1 2CC EN-DC for HPUE Anritsu, KDDI Corporation CR Agreement
5.3.10.4.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254758 Addition of reference sensitivity requirements for Rel-19 FR1 2CC EN-DC Anritsu, Huawei, HiSilicon CR Agreement
5.3.35.5.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254759 Addition of reference sensitivity requirements for Rel-15 FR1 3CC EN-DC Anritsu, KDDI Corporation CR Agreement
5.4.6.2Rx Requirements (Clause 7)
No
Yeslate doc
withdrawn Yes    
R5‑254760 Addition of reference sensitivity requirements for Rel-16 FR1 3CC EN-DC Anritsu, KDDI Corporation CR Agreement
5.3.1.5.2Rx Requirements (Clause 7)
No
Yeslate doc
withdrawn Yes    
R5‑254761 Addition of reference sensitivity requirements for Rel-18 FR1 3CC EN-DC for HPUE Anritsu, KDDI Corporation CR Agreement
5.3.10.4.2Rx Requirements (Clause 7)
Yes
Yeslate doc
agreed No    
R5‑254762 Correcting applicability of PUR test case 22.1.6 MediaTek Inc. CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
YesTdoc? merged r2
revised Yes R5‑255065  
R5‑254763 Applicability addition for LTE based 5G broadcast demod cases. Qualcomm Korea CR Agreement
5.3.31.4TS 36.521-2
Yes
Yes
agreed No    
R5‑254764 Correction of ENDC test case 8.2.5.2.1 Qualcomm Incorporated CR Agreement
6.4.4.4.2.5RRC Reconfiguration / Radio Link Failure (clause 8.2.5)
Yes
Yes
agreed No    
R5‑254765 Addition of new test case 6.9.1 Samsung R&D Institute UK, Ericsson, FirstNet, Element CR Agreement
6.3.24.6TS 37.579-7
Yes
Yesblock agreed on Thu r1
revised No R5‑255077  
R5‑254766 Updating V2X Tx test cases for intra-band concurrent operation Huawei, HiSilicon CR Agreement
5.3.7.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254767 Updating TP analysis for V2X Rx test cases Huawei, HiSilicon CR Agreement
5.3.7.7TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yeslate doc
agreed No    
R5‑254768 Updating V2X Rx test cases for intra-band concurrent operation Huawei, HiSilicon CR Agreement
5.3.7.3.2Rx Requirements (Clause 7)
Yes
Yeslate doc
agreed No    
R5‑254769 Adding test frequencies for V2X intra-band concurrent operation Huawei, HiSilicon CR Agreement
4.5.2RF group docs for WG review/verdict - original A.I. retained
Yes
Yeslate doc r1 TF160 agreed.
revised No R5‑255358  
R5‑254770 Updating test applicability for V2X test cases Huawei, HiSilicon CR Agreement
5.3.7.4TS 38.522
Yes
Yeslate doc
agreed No    
R5‑254771 Addition of transmit modulation quality test cases for 4Tx UL-MIMO Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
revised No R5‑255244  
R5‑254772 Addition of time alignment for 4Tx UL-MIMO Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
revised No R5‑255245  
R5‑254773 Addition of transmit modulation quality test cases for 4Tx Tx diversity Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255382  
R5‑254774 Update of Annex E for 4Tx UL-MIMO and Tx diversity Huawei, HiSilicon CR Agreement
5.3.19.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254775 Correcting the MPR test requirements for band n40 and n97 Huawei, HiSilicon, OPPO CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
YesR5 r1
revised No R5‑255269  
R5‑254776 Correcting spurious emission co-existence minimum requirements Huawei, HiSilicon, OPPO CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254777 Adding TP analysis for NS_06 for n14 PC2 Huawei, HiSilicon, China Unicom CR Agreement
5.3.9.5TR 38.905 (NR Test Points Radio Transmission and Reception )
Yes
YesCR cover value : NR_n28_PC2_40MHz_CBW-UEConTest!!!! r1
revised No R5‑255216  
R5‑254778 Addition of AMPR NS_06 testing for n14 PC2 Huawei, HiSilicon, China Unicom CR Agreement
5.3.9.3.1Tx Requirements (Clause 6)
Yes
YesXXX r1
revised No R5‑255219  
R5‑254779 Adding n28 PC2 to UL-MIMO MOP and MPR test cases Huawei, HiSilicon CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
Yesoverlap with R5-253904
withdrawn Yes    
R5‑254780 Adding n28 PC2 to TxD MOP and MPR test cases Huawei, HiSilicon CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
Yesoverlap with R5-253906
withdrawn Yes    
R5‑254781 Adding TP analysis for NS_18 for n28 PC2 Huawei, HiSilicon, Ericsson CR Agreement
5.3.34.5TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yesr1
revised No R5‑255234  
R5‑254782 Addition of AMPR NS_18 testing for n28 PC2 Huawei, HiSilicon, Ericsson CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255232  
R5‑254783 Addition of AMPR NS_18 testing for n28 PC2 UL-MIMO test cases Huawei, HiSilicon CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255233  
R5‑254784 Addition of AMPR NS_18 testing for n28 PC2 TxD test cases Huawei, HiSilicon CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254785 Addition of AMPR and Spurious emission of CA_n40A-n41A Huawei, HiSilicon, CMCC CR Agreement
5.3.1.3.1Tx Requirements (Clause 6)
Yes
Yescover: 18! r1
revised No R5‑255257  
R5‑254786 Addition of AMPR TP analysis for CA_n40A-n41A Huawei, HiSilicon, CMCC CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254787 Addition of spurious emission TP analysis information for CA_n40A-n41A Huawei, HiSilicon, CMCC CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yesr1
revised No R5‑255225  
R5‑254788 Jumbo CR for updating clause 5 for Rel-15 configurations Huawei, HiSilicon CR Agreement
5.4.6.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254789 Jumbo CR for updating clause 5 for Rel-16 configurations Huawei, HiSilicon CR Agreement
5.3.1.5.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254790 Jumbo CR for updating clause 5 for Rel-19 configurations Huawei, HiSilicon CR Agreement
5.3.35.5.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254791 Jumbo CR for deltaTIB and deltaRIB Huawei, HiSilicon, CMCC CR Agreement
5.3.35.3.1Tx Requirements (Clause 6)
Yes
Yesoverlap with R5-254647, R5-254748 r1 w/d???
revised No R5‑255260  
R5‑254792 Jumbo CR for deltaTIB and deltaRIB Huawei, HiSilicon, KDDI CR Agreement
5.3.35.5.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254793 Adding test frequencies for several EN-DC configurations including band n40 Huawei, HiSilicon CR Agreement
5.4.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254794 Adding PICS for several EN-DC configurations including band n40 Huawei, HiSilicon CR Agreement
5.4.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254795 Completing several EN-DC configurations including band n40 Huawei, HiSilicon CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254796 TP analysis for spurious emission for several EN-DC configurations including band n40 Huawei, HiSilicon CR Agreement
5.4.19TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254797 TP analysis for REFSENS for several EN-DC configurations including band n40 Huawei, HiSilicon CR Agreement
5.4.19TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254798 Adding test frequencies for CA and EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.35.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No    
R5‑254799 Adding PICS for new CA and EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.35.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254800 Adding TP analysis for multiple Rel-19 CA configurations Huawei, HiSilicon CR Agreement
5.3.35.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254801 Adding a few Rel-19 CA configurations Huawei, HiSilicon CR Agreement
5.3.35.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254802 Adding TP analysis for multiple Rel-19 ENDC configurations Huawei, HiSilicon CR Agreement
5.3.35.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254803 Adding Rel-19 ENDC configurations including n40-n71 Huawei, HiSilicon CR Agreement
5.3.35.5.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254804 Update general principle for ENDC REFSENS test for 4CC to 6CC Huawei, HiSilicon CR Agreement
5.3.35.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No    
R5‑254805 Updating REFSENS test cases with 5CC and 6CC Huawei, HiSilicon CR Agreement
5.3.35.5.2Rx Requirements (Clause 7)
Yes
Yes
agreed No    
R5‑254806 Introducing ENDC configurations without changes in Clause 6 and 7 Huawei, HiSilicon discussion Information
5.3.35.11Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No    
R5‑254807 WP of Rel-17 Power Class 2 UE for NR inter-band CA/DC with or without SUL configurations with x (6>=x>2) bands DL and y (y=1, 2) bands UL Huawei, HiSilicon Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254808 SR of Rel-17 Power Class 2 UE for NR inter-band CA/DC with or without SUL configurations with x (6>=x>2) bands DL and y (y=1, 2) bands UL Huawei, HiSilicon WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254809 WP of Rel-17 NR CA and DC; and NR and LTE DC Configurations Huawei, HiSilicon Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254810 SR of Rel-17 NR CA and DC; and NR and LTE DC Configurations Huawei, HiSilicon WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254811 WP of Rel-18 NR CA and DC; and NR and LTE DC Configurations Huawei, HiSilicon Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254812 SR of Rel-18 NR CA and DC; and NR and LTE DC Configurations Huawei, HiSilicon WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254813 WP of Rel-19 NR CA and DC; and NR and LTE DC Configurations Huawei, HiSilicon Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254814 SR of Rel-19 NR CA and DC; and NR and LTE DC Configurations Huawei, HiSilicon WI status report Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254815 Correction of mobility management test case 9.1.5.1.8 Qualcomm Incorporated CR Agreement
6.4.4.5.3MM Registration & De-registration (clauses 9.1.5 & 9.1.6)
No
Yeslate doc
withdrawn Yes    
R5‑254816 Update to applicability of the test case for variable Tx-Rx spacing for NR NTN bands EchoStar CR Agreement
5.3.4.5TS 38.522
Yes
Yes
agreed No    
R5‑254817 Updates to TC 6.6.3 Beam Correspondence in RRC_INACTIVE and initial access Apple AB Denmark CR Agreement
5.3.18.4.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255393  
R5‑254818 Addition of UE Beamlock_IDLE test function Apple CR Agreement
5.3.18.3TS 38.509
Yes
YesCR impact tick box for ME shall be set and none of the other tick boxes for UICC apps, RAN or CN shall be set for TS 38.509 r1
revised No R5‑255392  
R5‑254819 Impact of beam correspondence test method without UE beam lock Apple Distribution Intl Ltd discussion Endorsement
5.3.18.9Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No    
R5‑254820 Editorial correction to test purpose in Aerial UE Test Case Qualcomm Sweden CR Agreement
6.5.3.3.3RRC Part 3 (clause 8.3)
Yes
Yes+LTE_Aerial-UEConTest!
revised No R5‑254927  
R5‑254821 Update to UE capability test case 8.1.5.1.1 Qualcomm Incorporated CR Agreement
6.4.4.4.1.5RRC Others (clause 8.1.5)
Yes
Yes
agreed No    
R5‑254822 Update to UE capability test cases 8.2.1.1.1, 8.2.1.1.2 Qualcomm Incorporated CR Agreement
6.4.4.4.2.1RRC UE Capability / Others (clause 8.2.1)
Yes
Yes
agreed No    
R5‑254823 Addition of DCI based Active BWP Switch test case for ATG QUALCOMM Europe Inc. - Spain CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254824 Addition of RRC based Active BWP Switch test case for ATG QUALCOMM Europe Inc. - Spain CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254825 Addition of UE specific CBW change test case for ATG QUALCOMM Europe Inc. - Spain CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254826 Addition of Pathloss reference signal switching delay test case for ATG QUALCOMM Europe Inc. - Spain CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254827 Update to Annex E for ATG test cases QUALCOMM Europe Inc. - Spain CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No    
R5‑254828 Update to FR2 multi-Rx common sections QUALCOMM Europe Inc. - Spain CR Agreement
5.3.29.7TS 38.533
No
Yes
withdrawn Yes    
R5‑254829 Update to Annex E for FR2 multi-Rx test cases QUALCOMM Europe Inc. - Spain CR Agreement
5.3.29.7TS 38.533
Yes
Yes
agreed No    
R5‑254830 Update to FR2 multi-Rx test cases QUALCOMM Europe Inc. - Spain CR Agreement
5.3.29.7TS 38.533
No
Yes
withdrawn Yes    
R5‑254831 Core alignment for NR-NTN RLM test cases QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑254832 Core alignment for NR-NTN RRM SIB19 config QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑254833 Update to Annex F for NR-NTN pathloss RS switch test case QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑254834 Completion of NR-NTN timing advance test case 14.3.2.1 QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑254835 Completion of NR-NTN timing accuracy test case 14.3.1.1 QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.6TS 38.533
Yes
Yesr1
revised No R5‑255292  
R5‑254836 Completion of NR-NTN re-establishment test cases QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑254837 Completion of NR-NTN pathloss RS switch delay test 14.4.5.1 including TT QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑254838 Core alignment for NR-NTN Handover test cases QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.6TS 38.533
Yes
YesEditor’s note overlap with R5-254883 r2
revised No R5‑255293  
R5‑254839 Clean-up CR for NR-NTN measurement test cases QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No    
R5‑254840 Update to applicability of gap-based RRM FR2 tests QUALCOMM Europe Inc. - Spain CR Agreement
5.4.10.3EN-DC with at least 1 NR Cell in FR2 (Clause5)
Yes
Yesr1
revised No R5‑255417  
R5‑254841 Completion of NR-U SFTD measurement test case 12.5.1.1 QUALCOMM Europe Inc. - Spain CR Agreement
5.4.10.10E-UTRA Standalone Tests with at Least One NR Cell under CCA (Clause 12)
Yes
Yes
agreed No    
R5‑254842 Update to r18 NR-NTN test applicability QUALCOMM Europe Inc. - Spain CR Agreement
5.3.30.5TS 38.522
Yes
Yes
agreed No    
R5‑254843 Update to NR-NTN test applicability QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.5TS 38.522
Yes
Yesr2
revised No R5‑255362  
R5‑254844 Update to applicability of gap-based RRM FR2 tests QUALCOMM Europe Inc. - Spain CR Agreement
5.4.9TS 38.522
Yes
Yescoversheet: NR_NTN_solutions_plus_CT-UEConTest" r1
revised No R5‑255418  
R5‑254845 Applicability update for NR-U test cases QUALCOMM Europe Inc. - Spain CR Agreement
5.4.9TS 38.522
Yes
Yes
agreed No    
R5‑254846 Correction to SIB19 configuration for NR-NTN test cases QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.1TS 38.508-1
Yes
Yes
agreed No    
R5‑254847 Addition of PICS for FR2 multi-Rx test cases QUALCOMM Europe Inc. - Spain CR Agreement
5.3.29.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254848 Update to supportedGapPattern related PICS QUALCOMM Europe Inc. - Spain CR Agreement
5.4.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254849 Addition of PICS to control independentGapConfig in MRDC QUALCOMM Europe Inc. - Spain CR Agreement
5.4.2TS 38.508-2
Yes
Yes
agreed No    
R5‑254850 Addition of TT analysis for NR-NTN pathloss RS switch test case 14.4.5.1 QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No    
R5‑254851 TT analysis separation for NR-U and legacy SCell activation and deactivation tests QUALCOMM Europe Inc. - Spain CR Agreement
5.4.18TR 38.903 (NR MU & TT analyses)
Yes
Yesr1
revised No R5‑255331  
R5‑254852 Discussion on multi-Rx measurement uncertainty QUALCOMM Europe Inc. - Spain discussion Endorsement
5.3.29.10Discussion Papers, Work Plan, TC lists
Yes
Yes"[Pre-Meeting] No FR2 MU Declaration. Draft shared on time in RRM TT folder but not as part of FR2 MU drafts. Will be treated depending on availabilty of time after FR2 MU1 Tdocs. 8/25: Moderator (Apple) - Concerns raised by Keysight that MU element/value in Prop1 is not relevant to RRM test. Moreover Annex A changes proposed apply to RF, RRM, Demod not just RRM. 8/26 Moderator (Apple) - Discussion Paper can be noted. Proposal not endorsed convenor: revised based on further offline discussions Revised to: R5-254852r1."
revised No R5‑255346  
R5‑254853 Transmit EIRP density and A-MPR updates for band 254 Keysight Technologies UK Ltd CR Agreement
5.5.1.5TS 36.521-4
Yes
Yesr1
revised No R5‑255409  
R5‑254854 UE additional maximum output power reduction updates Keysight Technologies UK Ltd CR Agreement
5.5.1.5TS 36.521-4
Yes
Yes
agreed No    
R5‑254855 Transmit power density and A-MPR updates for band n254 Keysight Technologies UK Ltd CR Agreement
5.4.8TS 38.521-5
Yes
Yesr2
revised No R5‑255408  
R5‑254856 Add missing in-band blocking requirement for n259 intra-band contiguous CA Apple Inc CR Agreement
5.3.18.4.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255275  
R5‑254857 SR of NR RF requirements enhancement for frequency range 2 (FR2), Phase 3 Apple Inc, Nokia WI status report Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254858 WP for NR RF requirements enhancement for frequency range 2 (FR2), Phase 3 Apple Inc, Nokia Work Plan Information
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
No
Yes
noted No    
R5‑254859 Proposed followup for TRP TRS OTA conformance efforts Apple Inc discussion Agreement
5.4.12TS 38.561
Yes
Yesgroup ok to send LS
noted No    
R5‑254860 Applicability updates REFSENS power level test for XR UEs Apple Inc CR Agreement
5.3.16.4TS 38.522
Yes
Yesis Rel-19! reissued as R5-254893.
withdrawn Yes    
R5‑254861 Discussion on Addition of FR2 RF testability issue list to specification Apple Inc discussion Agreement
5.4.20Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No    
R5‑254862 Addition of FR2 RF testability issue list to specification Apple Inc CR Agreement
5.4.5.3Clauses 1-5, Annexes
Yes
Yesr1
revised No R5‑255394  
R5‑254863 Applicability updates for 2AoA spherical coverage test Apple Inc CR Agreement
5.3.29.6TS 38.522
Yes
YesWrong spec in both 3GU and coversheet, should be 38.522. reissued as R5-254892
withdrawn Yes    
R5‑254864 Updates to 2AoA spherical coverage test Apple Inc CR Agreement
5.3.29.4.2Rx Requirements (Clause 7)
Yes
Yesr1
revised No R5‑255273  
R5‑254865 Updates to Annexes for 2AoA spherical coverage test Apple Inc CR Agreement
5.3.29.4.3Clauses 1-5, Annexes
Yes
Yes
agreed No    
R5‑254866 Introduction of minimum conformance requirements for additional spurious emissions tests Apple Inc CR Agreement
5.3.42.1.1Tx Requirements (Clause 6)
Yes
Yes
agreed No    
R5‑254867 Inputs to 6G Spec Modernization efforts Apple Inc discussion Agreement
4.2.46G spec modernization & RAN5 aspects
Yes
Yes
noted No    
R5‑254868 Evaluation and optimization of OOB measurement points and test procedure Apple Inc discussion Agreement
5.4.20Discussion Papers, Work Plan, TC lists
No
Yes
withdrawn Yes    
R5‑254869 WP UE Conformance Test Aspects - Solutions for NR to support non-terrestrial networks (NTN) QUALCOMM Europe Inc. - Italy Work Plan Approval
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
No
No
reserved No    
R5‑254870 SR UE Conformance Test Aspects - Solutions for NR to support non-terrestrial networks (NTN) QUALCOMM Europe Inc. - Italy WI status report Approval
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254871 WP - UE Conformance - NR NTN (Non-Terrestrial Networks) enhancements QUALCOMM Europe Inc. - Italy Work Plan Approval
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
No
No
reserved No    
R5‑254872 SR - UE Conformance - NR NTN (Non-Terrestrial Networks) enhancements QUALCOMM Europe Inc. - Italy WI status report Approval
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254873 WP - UE Conformance - New bands and bandwidth allocation for LTE based 5G terrestrial broadcast QUALCOMM Europe Inc. - Italy Work Plan Approval
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
No
No
reserved No    
R5‑254874 SR - UE Conformance - New bands and bandwidth allocation for LTE based 5G terrestrial broadcast QUALCOMM Europe Inc. - Italy WI status report Approval
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254875 WP - UE Conformance - Requirement for NR frequency range 2 (FR2) multi-Rx chain DL reception QUALCOMM Europe Inc. - Italy Work Plan Approval
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
No
No
reserved No    
R5‑254876 SR - UE Conformance - Requirement for NR frequency range 2 (FR2) multi-Rx chain DL reception QUALCOMM Europe Inc. - Italy WI status report Approval
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yes
noted No    
R5‑254877 Minimum test time analysis for FR1 PDSCH absolute phy layer tput test cases QUALCOMM Europe Inc. - Italy discussion Endorsement
5.3.26.7Discussion Papers, Work Plan, TC lists
Yes
YesR5-255281
noted No    
R5‑254878 Annex G update for FR1 PDSCH absolute phy layer tput test cases QUALCOMM Europe Inc. - Italy CR Agreement
5.3.26.3.4Clauses 1-4, Annexes
Yes
Yes
agreed No    
R5‑254879 Addition of missing aperiodic CQI triggering parameters for PDSCH abs ph layer tput test cases QUALCOMM Europe Inc. - Italy CR Agreement
5.3.26.3.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yesr1
revised No R5‑255415  
R5‑254880 Test frequency and BW addition for LTE based 5G broadcast bands QUALCOMM Europe Inc. - Italy CR Agreement
5.3.31.1TS 36.508
Yes
Yes
agreed No    
R5‑254881 AIML status update QUALCOMM Europe Inc. - Italy discussion Information
4.2.3AI/ML Testability & Interoperability
Yes
Yes
noted No    
R5‑254882 Discussion on distance based CHO test cases for NR-NTN QUALCOMM Europe Inc. - Italy discussion Endorsement
5.3.4.9Discussion Papers, Work Plan, TC lists
Yes
Yes
agreed No    
R5‑254883 update to distance based CHO test cases for NR-NTN QUALCOMM Europe Inc. - Italy CR Agreement
5.3.4.6TS 38.533
Yes
Yes
revised No R5‑255286  
R5‑254884 update to NR-NTN specific common clause QUALCOMM Europe Inc. - Italy CR Agreement
7.3.3Other open issues from joint sessions - original A.I. retained
Yes
Yesr1 deferred closing joint r2
revised No R5‑255097  
R5‑254885 Update to PDSCH RMC for PDCCH test cases QUALCOMM Europe Inc. - Italy CR Agreement
5.4.7.4Clauses 1-4, Annexes
Yes
Yesr1
revised No R5‑255416  
R5‑254886 Correction to MDT IRAT test case 8.1.6.2.4 Keysight Technologies UK CR Agreement
6.4.4.4.1.6RRC SON and MDT support for NR (clause 8.1.6)
Yes
Yeslate doc
agreed No    
R5‑254887 Correction to SDT test case 8.1.5.13.1 Keysight Technologies UK CR Agreement
6.3.8.3TS 38.523-1
Yes
Yesex:TEI17_Test, NR_SmallData_INACTIVE-UEConTest new: NR_FR1_lessthan_5MHz_BW-UEConTest r1
revised No R5‑254998  
R5‑254888 Correction to SDT test case 8.1.5.13.4 Keysight Technologies UK CR Agreement
6.3.8.3TS 38.523-1
Yes
Yesex:TEI17_Test, NR_SmallData_INACTIVE-UEConTest new: NR_FR1_lessthan_5MHz_BW-UEConTest r1
revised No R5‑254999  
R5‑254889 Correction to UE-CapabilityRequestFilterCommon IE Keysight Technologies UK CR Agreement
6.4.1.2Default NG-RAN RRC messages and IEs (Clause 4.6)
Yes
Yes
agreed No    
R5‑254890 Candidate nomination for RAN5 Chair ETSI Secretariat other Presentation
1.1Welcoming brief by the host
Yes
Yes
noted No    
R5‑254891 Candidate nomination for RAN5 Vice Chair ETSI Secretariat other Presentation
1.1Welcoming brief by the host
Yes
Yes
noted No    
R5‑254892 Applicability updates for 2AoA spherical coverage test Apple Inc CR Agreement
5.3.29.6TS 38.522
Yes
YesAI??
agreed No    
R5‑254893 Applicability updates REFSENS power level test for XR UEs Apple Inc CR Agreement
5.3.16.4TS 38.522
Yes
Yes
agreed No    
R5‑254894 Corrected incorrect RB allocations for additional MOP TC Qualcomm Technologies Ireland CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255271  
R5‑254895 Corrected incorrect K2 value for Tx on off test case Qualcomm Technologies Ireland CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yesr1
revised No R5‑255402  
R5‑254896 Correction to N_RB_alloc numbers in Table 6.1A-1a Apple CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
withdrawn Yes    
R5‑254897 Update to 5GS session management test case 10.1.8.1 Qualcomm Incorporated, ROHDE & SCHWARZ CR Agreement
6.4.4.8.4SM NSAC (clauses 10.1.8)
Yes
Yeslate doc
agreed No    
R5‑254898 LS on NB-IoT NTN OTA Testing CTIA Cart OTA WG LS in Information
3Incoming Liaison Statements
Yes
Yespresented by Keysight Noted.
noted No    
R5‑254899 RAN5 Leadership Team WG Chairman other Information
2.1Live Reports
Yes
Yes
noted No   R5‑253704
R5‑254900 Remove applicability for NR IDC TC 8.2.6.5.1 CMCC CR Agreement
6.3.20.5TS 38.523-2
Yes
Yeslate doc
agreed No    
R5‑254901 Candidate specs for release upgrade after RAN5#108 CATT other Information
7.6Docs still needing agreement/endorsement/approval (e.g. Outgoing LS, Reports, New Specs, Info for certification bodies etc.)
Yes
Yes
revised No R5‑255103  
R5‑254902 Revised WID on UE Conformance - Alignment of eCall over IMS with CEN Qualcomm Sweden WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yesis endorsed
agreed No   R5‑254189
R5‑254903 Addition of new NR IMS data channel test case 7.45 - MT Video call with precondition and BDC success Huawei, HiSilicon CR Agreement
6.3.28.8TS 34.229-5
Yes
Yes
agreed No    
R5‑254904 Correction to NR5GC testcase 11.4.1a ROHDE & SCHWARZ, MediaTek CR Agreement
6.4.4.11.4Emergency Services (clause 11.4)
Yes
Yeslate doc NR_NTN_enh_plus_CT-UEConTest-> NR_UE_pow_sav_enh_plus_CT-UEConTest
revised No R5‑254941  
R5‑254905 Addition of new test case 12.1.12.1 TDIA, CATT CR Agreement
6.3.5.3TS 38.523-1
Yes
Yes
agreed No    
R5‑254906 MCC TF160 Status Report MCC TF160 report Approval
7.6Docs still needing agreement/endorsement/approval (e.g. Outgoing LS, Reports, New Specs, Info for certification bodies etc.)
Yes
Yes2026 task list endorsed!
approved No   R5‑253971
R5‑254907 reply to LS on requesting test Specification and procedures for NR-NR DC between FR1-FR2 devices in 3GPP 38.521-3 TSG WG RAN5 LS out Approval
7.6Docs still needing agreement/endorsement/approval (e.g. Outgoing LS, Reports, New Specs, Info for certification bodies etc.)
No
Yes
approved No    
R5‑254908 New WID on UE Conformance - Introduction of another IoT-NTN S-band (MSS band 2000-2020 MHz UL and 2180-2200 MHz DL) MediaTek Inc., China Telecom, EchoStar WID new Endorsement
7.5.1Final version of Work Item Proposals
Yes
Yesis endorsed
agreed No   R5‑253742
R5‑254909 New WID on UE Conformance - Channel raster enhancement China Telecom, Huawei WID new Endorsement
7.5.1Final version of Work Item Proposals
Yes
YesOrange was added. Is endorsed
agreed No   R5‑253960
R5‑254910 New WID on UE Conformance -Low-power wake-up signal and receiver for NR vivo, Apple WID new Endorsement
7.5.1Final version of Work Item Proposals
Yes
Yesresubmitted at the next meeting
noted No   R5‑254130
R5‑254911 New WID on UE Conformance - Enhanced requirements and conductive test methodology for NR NTN and IoT NTN Xiaomi, China Unicom, Samsung WID new Endorsement
7.5.1Final version of Work Item Proposals
Yes
Yesis endorsed
agreed No   R5‑254199
R5‑254912 New WID on UE Conformance – Additional NR bands for NR features in Rel-19 ZTE Corporation, Huawei, China Telecom WID new Endorsement
7.5.1Final version of Work Item Proposals
Yes
Yesis endorsed
agreed No   R5‑254337
R5‑254913 New WID on UE Conformance – FR1 TRP (Total Radiated Power), TRS (Total Radiated Sensitivity) and MIMO OTA (Over the Air) testing enhancement Phase 3 Apple Inc, Vivo WID new Endorsement
4.1New Work Item proposals - for intro only
No
Yes
noted No   R5‑254431
R5‑254914 UE Conformance - core and perf requirements for IoT NTN TDD mode Iridium Satellite LLC WID new Endorsement
4.1New Work Item proposals - for intro only
Yes
YesNoted.
noted No   R5‑254043
R5‑254915 New WID on UE Conformance - Evolution of NR duplex operation: Sub-band full duplex (SBFD) Huawei, HiSilicon, CMCC WID new Endorsement
7.5.1Final version of Work Item Proposals
Yes
Yesis endorsed
agreed No   R5‑254453
R5‑254916 New WID on UE Conformance - Multi-carrier enhancements for NR Phase 3 Lenovo, Motorola Mobility WID new Information
4.1New Work Item proposals - for intro only
Yes
YesNoted.
noted No   R5‑254673
R5‑254917 Add generic test procedure for Emergency call and RTT Ericsson CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
Yes
agreed No   R5‑254154
R5‑254918 Addition of signalling test frequencies and conditions for variable Tx-Rx spacing for NB-IoT for NTN band 253, 254 and 255 EchoStar, Viasat CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
Yes
agreed No   R5‑254251
R5‑254919 Addition of test frequencies and updates to support protocol test coverage for NB-IoT inband in NTN NR EchoStar, Viasat CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
Yes
agreed No   R5‑254269
R5‑254920 Correction to USIM configuration for eCall over EPS capable UEs Qualcomm Incorporated, Rohde & Schwarz CR Agreement
6.5.1Routine Maintenance for TS 36.508
Yes
Yes
agreed No   R5‑254507
R5‑254921 Addition of applicability and PICS for protocol test coverage for NB-IoT inband in NTN NR EchoStar CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yes
agreed No   R5‑254270
R5‑254922 Correction of Inter-RAT cell reselection test case 6.2.3.6 Qualcomm Incorporated CR Agreement
6.5.3.1Idle Mode
Yes
Yes
agreed No   R5‑254495
R5‑254923 Addition of Inter-RAT cell reselection test case 6.2.3.36 Qualcomm Incorporated CR Agreement
6.5.3.1Idle Mode
Yes
Yes
agreed No   R5‑254513
R5‑254924 Addition of Inter-RAT cell reselection test case 6.2.3.37 Qualcomm Incorporated CR Agreement
6.5.3.1Idle Mode
Yes
Yes
agreed No   R5‑254515
R5‑254925 Correction to applicability of interRAT test cases Qualcomm Incorporated, MCC TF160 CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yes
agreed No   R5‑254504
R5‑254926 Applicability updates for protection against improper interRAT reselection test cases Qualcomm Incorporated CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yes
agreed No   R5‑254516
R5‑254927 Editorial correction to test purpose in Aerial UE Test Case Qualcomm Sweden CR Agreement
6.5.3.3.3RRC Part 3 (clause 8.3)
Yes
Yesrev!
revised No R5‑254987 R5‑254820
R5‑254928 Correction to EMM test case 9.2.3.3.1 Keysight Technologies UK CR Agreement
6.5.3.4EPS Mobility Management
Yes
Yes
agreed No   R5‑254201
R5‑254929 Corrections to NB-IoT UP PUR test case 22.1.6 MCC TF 160 CR Agreement
6.5.3.11Others (TS 36.523-1 clauses not covered by other AIs under AI 6.5.3, e.g. eMBMS, Home (e)NB, MBMS in LTE, D2D, SC-PTM, NB-IoT, CIoT...)
Yes
Yes
agreed No   R5‑253997
R5‑254930 Proposal for new test case related to UE mobility in inter-system upon receiving the 5GMM cause value #15 in the REGISTRATION REJECT message NTT DOCOMO INC. discussion Endorsement
6.4.7Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No   R5‑254208
R5‑254931 Discussion on addition of test coverage for Rel-17 Search space set group switching Qualcomm Incorporated discussion Discussion
6.4.7Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No   R5‑254544
R5‑254932 Update to SOR-CMCI PICS MediaTek Inc. CR Agreement
6.4.2TS 38.508-2
Yes
Yes
agreed No   R5‑253793
R5‑254933 Addition of PICS for SSSG switching Qualcomm Incorporated CR Agreement
6.4.2TS 38.508-2
Yes
Yes
agreed No   R5‑254579
R5‑254934 Update the feMIMO test case 7.1.1.3.17.X - Multi-TRP Huawei, HiSilicon CR Agreement
6.4.4.3.1.2MAC
Yes
Yes
agreed No   R5‑254106
R5‑254935 Corrections to N3Access MM test cases MCC TF160 CR Agreement
6.4.4.65GS Non-3GPP Access Mobility Management (clause 9.2)
Yes
Yes
agreed No   R5‑254220
R5‑254936 Addition of new test case 9.3.1.7 related to Inter-system mobility registration update / Rejected / No suitable cells in tracking area / 5GC to EPC NTT DOCOMO, INC CR Agreement
6.4.4.75GS Inter-system Mobility (clause 9.3)
Yes
Yes
agreed No   R5‑254203
R5‑254937 Void EPS fallback test case 11.1.5 Ericsson CR Agreement
6.4.4.11.1EPS Fallback (clause 11.1)
Yes
Yes
agreed No   R5‑254098
R5‑254938 Correction to V2X SIG test case 12.1.9.1.1 - UM RLC segmentation Huawei, HiSilicon CR Agreement
6.4.4.12NR Sidelink (clauses 12 & 13)
Yes
Yes
agreed No   R5‑254572
R5‑254939 Correction to V2X SIG test case 12.1.9.2.2 - AM polling Huawei, HiSilicon CR Agreement
6.4.4.12NR Sidelink (clauses 12 & 13)
Yes
Yes
agreed No   R5‑254573
R5‑254940 Correction to applicability conditions MediaTek Inc. CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No   R5‑253769
R5‑254941 Correction to NR5GC testcase 11.4.1a ROHDE & SCHWARZ, MediaTek CR Agreement
6.4.4.11.4Emergency Services (clause 11.4)
Yes
Yes
agreed No   R5‑254904
R5‑254942 Addition of PIXIT for testing of flexible Tx-Rx separation for NR NTN bands EchoStar, MCC TF160 CR Agreement
6.3.3.6TS 38.523-3
Yes
Yes
agreed No   R5‑254267
R5‑254943 Addition of new System information config for NTN-TN scenarios QUALCOMM JAPAN LLC. CR Agreement
6.3.25.1TS 38.508-1
Yes
Yes
agreed No   R5‑254284
R5‑254944 Addition of new NR NTN enh 6.7.1.10 Test case for skipping TN measurements QUALCOMM JAPAN LLC. CR Agreement
6.3.25.4TS 38.523-1
Yes
Yes
agreed No   R5‑254281
R5‑254945 Typo Correction to NR NTN Enh TC 6.7.1.9 QUALCOMM JAPAN LLC. CR Agreement
6.3.25.4TS 38.523-1
Yes
Yes
agreed No   R5‑254282
R5‑254946 Updates to Test case 8.1.3.1.27 QUALCOMM JAPAN LLC. CR Agreement
6.3.25.4TS 38.523-1
Yes
Yes
agreed No   R5‑254283
R5‑254947 Addition of NR NTN enhancements test case 9.4.1.5 Qualcomm Incorporated CR Agreement
6.3.25.4TS 38.523-1
Yes
Yes
agreed No   R5‑254726
R5‑254948 PRD21 CDS PC2 for NR FR1 FDD single band NTT DOCOMO INC. other discussion
7.4.4PRD21: Status Updates and Completion Declaration Statements (CDS) for NR bands, NR band CBW extensions, 5G NR CADC configurations for all Power Classes
No
No
reserved No    
R5‑254949 Update the applicability for SONMDT TC 8.1.6.1.2.14 CMCC CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No    
R5‑254950 Corrections to MT-SDT 4-Step RACH MAC Test case Lenovo, Motorola Mobility, MCC TF160 CR Agreement
6.3.19.3TS 38.523-1
Yes
Yes
agreed No   R5‑254671
R5‑254951 Update eRedCap UE Test applicability for Legacy test cases Huawei, HiSilicon, China Unicom CR Agreement
6.3.3.1TS 38.508-1
Yes
Yes
not pursued No   R5‑254114
R5‑254952 Update of Table 4.6.1A-3 RRCReconfigurationSidelink TDIA, CATT CR Agreement
6.3.5.1TS 38.508-1
Yes
Yes
agreed No   R5‑254591
R5‑254953 Addition of contents of PC5 RRC UEAssistanceInformationSidelink message TDIA, CATT CR Agreement
6.3.5.1TS 38.508-1
Yes
Yes
agreed No   R5‑254592
R5‑254954 Update of Table 4.6.2-14A SIB12-IEs TDIA, CATT CR Agreement
6.3.5.1TS 38.508-1
Yes
Yes
agreed No   R5‑254593
R5‑254955 Update of Table 4.6.6-7 SL-ConfigDedicatedNR TDIA, CATT CR Agreement
6.3.5.1TS 38.508-1
Yes
Yes
agreed No   R5‑254594
R5‑254956 Addition of NR Sidelink Capabilities for NR Sidelink DRX testcases TDIA, CATT CR Agreement
6.3.5.2TS 38.508-2
Yes
Yes
agreed No   R5‑254596
R5‑254957 Addition of test applicabilities for new sidelink enhancement testcases CATT, TDIA CR Agreement
6.3.5.4TS 38.523-2
Yes
Yes
agreed No   R5‑254597
R5‑254958 Introduction of SOR-SNPN-SI-LS IE for Rel-18 eNPN test cases China Telecom CR Agreement
6.3.21.1TS 38.508-1
Yes
Yeslate doc
agreed No    
R5‑254959 Correction to the title and applicability of NB-IoT NTN test cases and correction of related PIXIT names MediaTek CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yeslate doc 2. WIC!?
revised No R5‑255064  
R5‑254960 Correction to P-Access-Network-Info header for RedCap UEs Qualcomm Incorporated, Keysight CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
agreed No   R5‑254501
R5‑254962 Revised WID on UE Conformance - High power UE (power class 2) for NR FR1 FDD single band China Unicom WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yesr1
revised No R5‑255093  
R5‑254963 Updates to RTT test case 19.1.7 Qualcomm India Pvt Ltd CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
agreed No   R5‑254505
R5‑254964 Correction of test case 10.6 MediaTek Inc., StarPoint CR Agreement
6.6.6.5TS 34.229-5
Yes
Yes
agreed No   R5‑253796
R5‑254965 Update applicability for test cases 7.1, 7.2, 7.5, 7.7, 7.9 and 7.10 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No   R5‑253726
R5‑254966 Update applicability for test cases 7.4a, 7.6a, 7.8, 7.12, 7.13, 7.18 and 7.19 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No   R5‑253727
R5‑254967 Update applicability for test cases 7.24, 7.24a, 7.24b, 7.25, 7.27, 7.28, 7.30, 7.31, 7.32 and 7.34 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No   R5‑253728
R5‑254968 Update applicability for test cases 7.29 Ericsson CR Agreement
6.6.6.2TS 34.229-2
Yes
Yes
agreed No   R5‑253740
R5‑254969 Addition of eCall only mode test case 11.3.9 Qualcomm Incorporated CR Agreement
6.3.29.7TS 36.523-1
Yes
Yes
agreed No   R5‑254519
R5‑254970 Applicability addition for EPS CEN test cases Qualcomm Incorporated CR Agreement
6.3.29.8TS 36.523-2
Yes
Yes
agreed No   R5‑254521
R5‑254971 Updates to eCall over IMS procedures Qualcomm Incorporated CR Agreement
6.3.29.10TS 34.229-1
Yes
Yes
agreed No   R5‑254498
R5‑254972 Addition of eCall test case 11.17 for CEN alignments Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yes
agreed No   R5‑254178
R5‑254973 Addition of eCall test case 11.19 for CEN alignments Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yes
agreed No   R5‑254179
R5‑254974 Corrrection to eCALL test case 11.13 Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yes
withdrawn Yes   R5‑254180
R5‑254975 Corrrection to eCALL test case 11.15 Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yes
agreed No   R5‑254181
R5‑254976 Corrrection to eCALL test case 11.16 Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yes
agreed No   R5‑254182
R5‑254977 Corrrection to eCALL test case 11.18 Qualcomm Sweden CR Agreement
6.3.29.13TS 34.229-5
Yes
Yes
withdrawn Yes   R5‑254183
R5‑254978 Updates to NR eCall over IMS procedures Qualcomm Incorporated CR Agreement
6.3.29.13TS 34.229-5
Yes
Yes
agreed No   R5‑254499
R5‑254979 Correction to NR eCall testcases 11.10, 11.11 and 11.12 ROHDE & SCHWARZ, Keysight, Anritsu Ltd, Qualcomm CR Agreement
6.3.29.13TS 34.229-5
Yes
Yes
agreed No   R5‑254611
R5‑254980 Addition of applicablity for new NR NGeCall CEN alignment Test Cases Qualcomm Sweden CR Agreement
6.3.29.11TS 34.229-2
Yes
Yes
agreed No   R5‑254184
R5‑254981 Addition of EPC IMS DC TC 8.18 MediaTek Inc. CR Agreement
6.3.28.5TS 34.229-1
Yes
Yes
agreed No   R5‑253754
R5‑254982 Addition of new LTE IMS data channel test case 12.36 - MO Video call with precondition and BDC failure Huawei, HiSilicon CR Agreement
6.3.28.5TS 34.229-1
Yes
Yes
agreed No   R5‑254115
R5‑254983 Addition of new LTE IMS data channel test case 12.37 - MO Video call with precondition and BDC success Huawei, HiSilicon CR Agreement
6.3.28.5TS 34.229-1
Yes
Yes
agreed No   R5‑254116
R5‑254984 Addition of new NR IMS data channel test case 7.43 - MO Video call with precondition and BDC failure Huawei, HiSilicon CR Agreement
6.3.28.8TS 34.229-5
Yes
Yes
agreed No   R5‑254118
R5‑254985 Addition of new NR IMS data channel test case 7.44 - MO Video call with precondition and BDC success Huawei, HiSilicon CR Agreement
6.3.28.8TS 34.229-5
Yes
Yes
agreed No   R5‑254119
R5‑254986 Correct the MTSI media capability for data channel Ericsson CR Agreement
6.3.28.6TS 34.229-2
Yes
Yes
agreed No   R5‑253815
R5‑254987 Editorial correction to test purpose in Aerial UE Test Case Qualcomm Sweden CR Agreement
6.5.3.3.3RRC Part 3 (clause 8.3)
Yes
Yes
agreed No   R5‑254927
R5‑254988 Update to the IE ReferenceLocation ZTE Corporation, CMCC, MCC TF160, QUALCOMM JAPAN LLC. CR Agreement
6.3.7.1TS 38.508-1
Yes
Yes
agreed No   R5‑254024
R5‑254989 Corrections to ATG TC 8.1.4.4.8 ZTE Corporation, CMCC, MCC TF160 CR Agreement
6.3.7.3TS 38.523-1
Yes
Yes
agreed No   R5‑254025
R5‑254990 Corrections to ATG TC 7.1.1.10.5 ZTE Corporation, CMCC, MCC TF160 CR Agreement
6.3.7.3TS 38.523-1
Yes
Yes
agreed No   R5‑254026
R5‑254991 Correction to MAC test case 7.1.1.6.8 for 3MHz Bandwidth Anritsu EMEA Ltd CR Agreement
6.3.8.3TS 38.523-1
Yes
Yesthis TC belongs to the open WI "NR_XR_enh_plus_CT1-UEConTest"
agreed No   R5‑254038
R5‑254992 Correction to MAC test case 7.1.1.6.6 for 3MHz Bandwidth Anritsu EMEA Ltd CR Agreement
6.3.8.3TS 38.523-1
Yes
Yes
agreed No   R5‑254041
R5‑254993 Update to default SIB4 message for NR channel BW less than 5MHz for FR1 MediaTek Inc., Nokia CR Agreement
6.3.8.1TS 38.508-1
Yes
Yes
agreed No   R5‑253749
R5‑254994 Update to Idle mode TC for NR channel BW less than 5MHz for FR1 MediaTek Inc., Nokia CR Agreement
6.3.8.3TS 38.523-1
Yes
Yes
agreed No   R5‑253750
R5‑254995 Update to default SIB24 message for NR channel BW less than 5MHz for FR1 MediaTek Inc., Nokia CR Agreement
6.3.8.6TS 36.508
Yes
Yes
agreed No   R5‑253751
R5‑254996 Correction to MAC test case 7.1.1.6.2 for 3MHz Bandwidth Anritsu EMEA Ltd CR Agreement
6.3.8.3TS 38.523-1
Yes
Yes
agreed No   R5‑254042
R5‑254997 Correction to MAC test case 7.1.1.8.1 for 3MHz Bandwidth Anritsu EMEA Ltd CR Agreement
6.3.8.3TS 38.523-1
Yes
Yes
agreed No   R5‑254100
R5‑254998 Correction to SDT test case 8.1.5.13.1 Keysight Technologies UK CR Agreement
6.3.8.3TS 38.523-1
Yes
Yes
agreed No   R5‑254887
R5‑254999 Correction to SDT test case 8.1.5.13.4 Keysight Technologies UK CR Agreement
6.3.8.3TS 38.523-1
Yes
Yes
agreed No   R5‑254888
R5‑255000 Corrections to assumed PUSCH PHR MAC Test case Lenovo, Motorola Mobility, MCC TF160 CR Agreement
6.3.14.3TS 38.523-1
Yes
Yes
agreed No   R5‑254669
R5‑255001 Addition of new test case 6.5.3.12 SNPN Selection in Manual Mode / Automatically Selecting equivalent SNPN China Telecom CR Agreement
6.3.21.3TS 38.523-1
Yes
Yes
agreed No   R5‑253962
R5‑255002 Addition of new test case 6.3.3.16 Steering of Roaming in SNPN / After registration / Security check successful / Access for localized services in SNPN China Telecom CR Agreement
6.3.21.3TS 38.523-1
No
Yesreissued as R5-255003 because of TC number change
withdrawn Yes   R5‑253963
R5‑255003 Addition of new test case 6.3.3.5 Steering of Roaming in SNPN / After registration / Security check successful / Access for localized services in SNPN China Telecom CR Agreement
6.3.21.3TS 38.523-1
Yes
Yes
revised No R5‑255004  
R5‑255004 Addition of test applicability for new R18 NPN test cases China Telecom Corporation Ltd. CR Agreement
6.3.21.4TS 38.523-2
Yes
Yes
agreed No   R5‑254491
R5‑255006 Discussion on Modernization of Specification Format and Procedures for 6G Ericsson, CATT, CMCC discussion Information
4.2.46G spec modernization & RAN5 aspects
Yes
Yes
noted No   R5‑254696
R5‑255007 Addition of SIB23 and related scheduling information for SLPP test cases CATT CR Agreement
6.3.22.1TS 38.508-1
Yes
Yes
agreed No   R5‑253842
R5‑255008 Addition of default SL-PRS resource pool configuration CATT CR Agreement
6.3.22.1TS 38.508-1
Yes
Yes
agreed No   R5‑253843
R5‑255009 Addition of SLPP default message contents and test condition CATT CR Agreement
6.3.22.2TS 37.571-2
Yes
Yes
agreed No   R5‑253844
R5‑255010 Addition of new SLPP abort procedure test cases CATT CR Agreement
6.3.22.2TS 37.571-2
Yes
Yes
agreed No   R5‑253845
R5‑255011 Addition of new SLPP error handling procedure test cases CATT CR Agreement
6.3.22.2TS 37.571-2
Yes
Yes
agreed No   R5‑253846
R5‑255012 Addition of test applicabilities for new SLPP abort and error handling procedure test cases CATT CR Agreement
6.3.22.3TS 37.571-3
Yes
Yes
agreed No   R5‑253847
R5‑255013 Addition of sidelink positioning related information and assistance data CATT CR Agreement
6.3.22.5TS 37.571-5
Yes
Yes
agreed No   R5‑253848
R5‑255014 Update of test case 8.1.6.1.2.14 for SON_MDT CMCC CR Agreement
6.4.4.4.1.6RRC SON and MDT support for NR (clause 8.1.6)
Yes
Yes
agreed No   R5‑253923
R5‑255015 Addition of new test case 8.1.6.1.2.14A for SONMDT CMCC CR Agreement
6.4.4.4.1.6RRC SON and MDT support for NR (clause 8.1.6)
Yes
Yes
withdrawn Yes   R5‑253924
R5‑255016 Addition of applicability for new SONMDT TC 8.1.6.1.2.14A CMCC CR Agreement
6.4.5TS 38.523-2
Yes
Yes
withdrawn Yes   R5‑253925
R5‑255017 Addition of new test 8.1.5.10.11 for R18 IDC enhancement CMCC CR Agreement
6.3.20.4TS 38.523-1
Yes
Yes
agreed No   R5‑253919
R5‑255018 Addition of new test 8.1.5.10.12 for R18 IDC enhancement CMCC CR Agreement
6.3.20.4TS 38.523-1
Yes
Yes
agreed No   R5‑253921
R5‑255019 Addition of applicability for new NR IDC TC 8.1.5.10.11 and 8.1.5.10.12 CMCC CR Agreement
6.3.20.5TS 38.523-2
Yes
Yes
agreed No   R5‑253920
R5‑255020 Addition of new test case 6.1.1.22 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.2TS 37.579-2
Yes
Yes
agreed No   R5‑254291
R5‑255021 Addition of new test case 6.6.1 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.2TS 37.579-2
Yes
Yes
agreed No   R5‑254292
R5‑255022 Addition of new test case 6.6.2 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.2TS 37.579-2
Yes
Yes
agreed No   R5‑254293
R5‑255023 Addition of new test case 6.6.3 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.2TS 37.579-2
Yes
Yes
agreed No   R5‑254294
R5‑255024 Addition of new PICs Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.3TS 37.579-4
Yes
Yes
agreed No   R5‑254297
R5‑255025 Addition of new test case 6.2.16 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.6TS 37.579-7
Yes
Yes
agreed No   R5‑254298
R5‑255026 Addition of new test case 6.2.17 Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.6TS 37.579-7
Yes
Yes
agreed No   R5‑254722
R5‑255027 Corrections to testcase 7.1.1.3.20 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yes
agreed No   R5‑253779
R5‑255028 Corrections to testcase 7.1.1.3.20a Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yes
agreed No   R5‑253780
R5‑255029 Editorial correction to testcase 7.1.1.3.21 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yesreissued as R5-255030 because of title change
withdrawn Yes   R5‑253781
R5‑255030 Corrections to testcase 7.1.1.3.21 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yes
agreed No    
R5‑255031 Corrections to testcase 7.1.1.5.7 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yes
agreed No   R5‑253782
R5‑255032 Corrections to testcase 7.1.1.5.8 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yes
agreed No   R5‑253783
R5‑255033 New testcase 7.1.1.5.9 Nokia CR Agreement
6.3.10.4TS 38.523-1
Yes
Yes
agreed No   R5‑253784
R5‑255034 Update to RRC IEs for Further NR mobility enhancements MediaTek Inc. CR Agreement
6.3.23.1TS 38.508-1
Yes
Yes
agreed No   R5‑254060
R5‑255035 Addition of new LTM Test Case 7.1.1.3.29 for LTM cell switch 4 step contention free random access procedure Qualcomm Sweden CR Agreement
6.3.23.3TS 38.523-1
Yes
Yes
agreed No   R5‑254173
R5‑255036 Addition of Applicability of new LTM Test Cases Qualcomm Sweden CR Agreement
6.3.23.4TS 38.523-2
Yes
Yes
agreed No   R5‑254174
R5‑255037 Update to TC 8.5.4.1 for Further measurement gap enhancements MediaTek Inc. CR Agreement
6.3.27.4TS 36.523-1
Yes
Yes
agreed No   R5‑253752
R5‑255038 Addition of PICS for Further measurement gap enhancements MediaTek Inc. CR Agreement
6.3.27.5TS 36.523-2
Yes
Yes
agreed No   R5‑253753
R5‑255039 Update of RRC messages for MBS Multicast reception in RRC_INACTIVE TDIA, CATT CR Agreement
6.3.30.1TS 38.508-1
No
Yes
agreed No   R5‑254607
R5‑255040 Common configuration updates related to UAV QUALCOMM JAPAN LLC. CR Agreement
6.3.31.1TS 38.508-1
Yes
Yes
agreed No   R5‑254280
R5‑255041 Addition of new UAV Test Case 8.1.3.5.1 Test Case for event H1 reporting QUALCOMM JAPAN LLC. CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes
agreed No   R5‑254274
R5‑255042 Addition of new UAV Test Case 8.1.3.5.2 Test Case for event H2 reporting QUALCOMM JAPAN LLC. CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes
agreed No   R5‑254275
R5‑255043 Addition of new UAV Test Case 8.1.3.5.3 Test Case for event A3H1 reporting for Intra-Frequency Neighbour QUALCOMM JAPAN LLC. CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes
agreed No   R5‑254276
R5‑255044 Addition of new UAV Test Case 8.1.3.5.4 Test Case for event A3H1 reporting for Inter-Frequency Neighbour QUALCOMM JAPAN LLC. CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes
agreed No   R5‑254277
R5‑255045 Addition of new UAV Test Case 8.1.3.5.5 Test Case for event A3H1 reporting for Inter-Band Neighbour QUALCOMM JAPAN LLC. CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes
agreed No   R5‑254278
R5‑255046 Addition of new UAV Test Case 8.1.3.5.9 Test Case for event A4H1 reporting for Intra-Frequency Neighbour China Unicom CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes
agreed No   R5‑254540
R5‑255047 Addition of ATSSS Phase 3 TC 11.9.5 MediaTek Inc. CR Agreement
6.3.32.3TS 38.523-1
Yes
Yes
agreed No   R5‑253757
R5‑255048 Addition of ATSSS Phase 3 TC 11.9.6 MediaTek Inc. CR Agreement
6.3.32.3TS 38.523-1
Yes
Yes
agreed No   R5‑253758
R5‑255049 Addition of ATSSS Phase 3 TC 11.9.7 MediaTek Inc. CR Agreement
6.3.32.3TS 38.523-1
Yes
Yes
agreed No   R5‑253759
R5‑255050 Addition of ATSSS Phase 3 TC 11.9.8 MediaTek Inc. CR Agreement
6.3.32.3TS 38.523-1
Yes
Yes
agreed No   R5‑253760
R5‑255051 New testcase - 10.6.1.2 Nokia CR Agreement
6.3.32.3TS 38.523-1
No
Yes
agreed No   R5‑254031
R5‑255052 Applicability of testcase -10.6.1.2 Nokia CR Agreement
6.3.32.4TS 38.523-2
No
YesKeysight UK commented about the PDU.
agreed No   R5‑254032
R5‑255053 Corrections to NB-IoT CP PUR test case 22.1.5 MCC TF160 CR Agreement
6.5.3.11Others (TS 36.523-1 clauses not covered by other AIs under AI 6.5.3, e.g. eMBMS, Home (e)NB, MBMS in LTE, D2D, SC-PTM, NB-IoT, CIoT...)
Yes
Yes
agreed No   R5‑253996
R5‑255054 Correction to LTE DRX testcase 7.1.6.2 for CAT-M1 Anritsu EMEA Ltd CR Agreement
6.5.3.2.1MAC
Yes
Yes
agreed No   R5‑254039
R5‑255055 Correction to RRC test case 8.5.4.1 Keysight Technologies UK CR Agreement
6.5.3.3.1RRC Part 1 (clauses 8.1 and 8.5)
Yes
Yes
agreed No   R5‑254200
R5‑255056 Routine maintenance for TS 38.523-3 MCC TF160, Nokia CR Agreement
6.4.6TS 38.523-3
Yes
Yes
agreed No   R5‑253992
R5‑255057 Routine maintenance for TS 36.523-3 MCC TF160 CR Agreement
6.5.5Routine Maintenance for TS 36.523-3
Yes
Yes
agreed No   R5‑254000
R5‑255058 Corrections to testcase 7.1.1.14.2.1 Nokia Corporation CR Agreement
6.3.13.3TS 38.523-1
Yes
Yes
agreed No   R5‑253839
R5‑255059 Addition of new UAV Test Case 8.1.3.5.10 Test Case for event A4H1 reporting for Inter-Frequency Neighbour China Unicom CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes
agreed No   R5‑254541
R5‑255060 Addition of new UAV Test Case 8.1.3.5.11 Test Case for event A4H1 reporting for Inter-Band Neighbour China Unicom CR Agreement
6.3.31.3TS 38.523-1
Yes
Yes
agreed No   R5‑254542
R5‑255061 Addition of applicability for new UAV test cases 8.1.3.5.9,8.1.3.5.10 and 8.1.3.5.11 China Unicom CR Agreement
6.3.31.4TS 38.523-2
Yes
Yesmerged into Qualcomm's R5-254279
withdrawn Yes   R5‑254610
R5‑255062 Correction to SSAC test case 13.5.1 Qualcomm India Pvt Ltd CR Agreement
6.5.3.8Multilayer Procedures
Yes
Yes
agreed No   R5‑254506
R5‑255063 Correction to NB-IoT ECR capability MCC TF160 CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yes
agreed No   R5‑253998
R5‑255064 Correction to the title and applicability of NB-IoT NTN test cases and correction of related PIXIT names MediaTek CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yes
agreed No   R5‑254959
R5‑255065 Correcting applicability of PUR test case 22.1.6 MediaTek Inc. CR Agreement
6.5.4Routine Maintenance for TS 36.523-2
Yes
Yes
withdrawn Yes   R5‑254762
R5‑255066 DCI format updates for SSSG switching Qualcomm Incorporated CR Agreement
6.4.1.5Other clauses, Annexes
Yes
Yes
agreed No   R5‑254578
R5‑255067 Correction for 38523-1 TC 6.3.1.7 Xiaomi CR Agreement
6.4.4.2Idle Mode (Clause 6)
Yes
Yes
agreed No   R5‑254198
R5‑255068 Addition of test case for Search Space Set Group Switching Qualcomm Incorporated CR Agreement
6.4.4.3.1.2MAC
Yes
Yes
agreed No   R5‑254580
R5‑255069 Updates to NR RRC test case 8.1.5.1.1 MCC TF160 CR Agreement
6.4.4.4.1.5RRC Others (clause 8.1.5)
Yes
Yes
agreed No   R5‑253987
R5‑255070 Updates to EN-DC RRC test case 8.2.1.1.1 MCC TF160 CR Agreement
6.4.4.4.2.1RRC UE Capability / Others (clause 8.2.1)
Yes
Yes
agreed No   R5‑253988
R5‑255071 Updates to NE-DC RRC test case 8.2.1.1.2 MCC TF160 CR Agreement
6.4.4.4.2.1RRC UE Capability / Others (clause 8.2.1)
Yes
Yes
agreed No   R5‑253989
R5‑255072 Applicability update to Inter-system mobility registration update / Rejected / No suitable cells in tracking area / 5GC to EPC test case NTT DOCOMO, INC CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No   R5‑254204
R5‑255073 Addition of applicability for SSSG switching test cases Qualcomm Incorporated CR Agreement
6.4.5TS 38.523-2
Yes
Yes
agreed No   R5‑254609
R5‑255074 Addition of applicabilities for new MCX test cases Ericsson, FirstNet, Element, Samsung R&D Institute UK CR Agreement
6.3.24.3TS 37.579-4
Yes
Yes
agreed No   R5‑254296
R5‑255075 Addition of new test case 6.10.4 FirstNet, Ericsson, Element, Samsung R&D Institute UK CR Agreement
6.3.24.5TS 37.579-6
Yes
Yes
agreed No   R5‑254190
R5‑255076 Addition of new test case 6.9.4 FirstNet, Ericsson, Element, Samsung R&D Institute UK CR Agreement
6.3.24.6TS 37.579-7
Yes
Yes
agreed No   R5‑254191
R5‑255077 Addition of new test case 6.9.1 Samsung R&D Institute UK, Ericsson, FirstNet, Element CR Agreement
6.3.24.6TS 37.579-7
No
Yes
agreed No   R5‑254765
R5‑255078 Addition of new test case 6.6.3 FirstNet, Ericsson, Element, Samsung R&D Institute UK CR Agreement
6.3.24.5TS 37.579-6
Yes
Yes
agreed No   R5‑254172
R5‑255079 Correction of test case 17.20 MCC TF160 CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
agreed No   R5‑254003
R5‑255080 Correction of test case 17.19 MCC TF160 CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
agreed No   R5‑254002
R5‑255081 Correction of test case 19.1.8 MCC TF160 CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
agreed No   R5‑254005
R5‑255082 Extension and correction of feature tags in default message contents MCC TF160, Ericsson, Qualcomm CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
agreed No   R5‑254008
R5‑255083 Add generic procedure for emergency speech call and RTT Ericsson CR Agreement
6.6.6.1TS 34.229-1
Yes
Yes
agreed No   R5‑254160
R5‑255084 Correction of test case 10.17 MCC TF160 CR Agreement
6.6.6.5TS 34.229-5
Yes
Yes
agreed No   R5‑254010
R5‑255085 Correction of test case 7.35 MCC TF160 CR Agreement
6.6.6.5TS 34.229-5
Yes
Yes
agreed No   R5‑254014
R5‑255086 Correction of test case 7.36 MCC TF160 CR Agreement
6.6.6.5TS 34.229-5
Yes
Yes
agreed No   R5‑254015
R5‑255087 Correction of test case 11.13 MCC TF160, Qualcomm CR Agreement
6.3.29.13TS 34.229-5
Yes
Yes
agreed No   R5‑253978
R5‑255088 Correction of test case 11.18 MCC TF160, Qualcomm CR Agreement
6.3.29.13TS 34.229-5
Yes
Yes
agreed No   R5‑253980
R5‑255089 Applicability updates for NR NTN Enhancements test cases Qualcomm Incorporated CR Agreement
6.3.25.5TS 38.523-2
Yes
Yes
agreed No   R5‑254727
R5‑255090 Addition of applicability for new UAV test cases QUALCOMM JAPAN LLC., China Unicom CR Agreement
6.3.31.4TS 38.523-2
Yes
Yes
agreed No   R5‑254279
R5‑255091 Addition of new test case 6.10.3 Element, Ericsson, FirstNet, Samsung R&D Institute UK CR Agreement
6.3.24.5TS 37.579-6
Yes
Yes
agreed No   R5‑254437
R5‑255092 Correction to RRC NR NTN test cases 8.1.5.14.1 Anritsu EMEA Ltd CR Agreement
6.3.3.4TS 38.523-1
Yes
Yes
agreed No   R5‑254030
R5‑255093 Revised WID on UE Conformance - High power UE (power class 2) for NR FR1 FDD single band China Unicom WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yesis endorsed
agreed No   R5‑254962
R5‑255094 dummy China Unicom WID new Endorsement
7.5.1Final version of Work Item Proposals
No
NoNew WID on UE Conformance - High power UE (power class 2) for NR FR1 FDD single band
reserved No    
R5‑255095 Discussion of A-IoT Device Conformance Testing CMCC, Huawei discussion Endorsement
4.2.15GS
Yes
Yes
noted No   R5‑253927
R5‑255096 Handling of test frequency tables containing too many BW combinations. Ericsson discussion Endorsement
4.2.15GS
Yes
Yes
noted No   R5‑254694
R5‑255097 update to NR-NTN specific common clause QUALCOMM Europe Inc. - Italy CR Agreement
7.3.3Other open issues from joint sessions - original A.I. retained
No
Yes
agreed No   R5‑254884
R5‑255098 New WID on Conformance - Solutions for Ambient IoT (Internet of Things) in NR CMCC, Huawei WID new Information
7.5.1Final version of Work Item Proposals
Yes
Yesis noted
noted No   R5‑253928
R5‑255099 Applicability of E-UTRA - NR SA FR1 E-UTRA cell re-selection to higher-priority NR target cell for 2 Rx UE test case Ericsson CR Agreement
5.4.9TS 38.522
No
Yes
agreed No   R5‑255340
R5‑255101 Revised WID on UE Conformance Test Aspects - Expanded and improved NR positioning CATT WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
No
Yesis endorsed.
agreed No   R5‑253865
R5‑255102 Revised WID on UE Conformance - New Rel-19 NR licensed bands and extension of existing NR bands Huawei, HiSilicon, China Telecom WID revised Endorsement
7.5.2Active Work Items/ Study Item: work plans (wp), status reports (sr), Work Item Descriptions (wid)
Yes
Yesis endorsed
agreed No   R5‑254454
R5‑255103 Candidate specs for release upgrade after RAN5#108 CATT other Information
7.6Docs still needing agreement/endorsement/approval (e.g. Outgoing LS, Reports, New Specs, Info for certification bodies etc.)
No
Yes
noted No   R5‑254901
R5‑255200 Reply LS on E-UTRA uplink configurations for intra-band ENDC MSD TSG WG RAN5 LS out Approval
5.7Outgoing liaison statements for provisional approval
Yes
Yes
revised No    
R5‑255201 Addition of test frequencies for CA_n3A_n28A-n77(2A) within FR1 KDDI Corporation (TTC) CR Agreement
5.3.1.1.1Test frequencies (Clause 4.3.1)
Yes
Yestypo? Un-agree?
agreed No   R5‑254436
R5‑255202 Addition of test frequency for Rel-16 n71 related EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.1.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No   R5‑254474
R5‑255203 Addition of test frequencies for new three bands NR CA and new four bands NRCA combos within FR1 KDDI Corporation (TTC) CR Agreement
5.3.2.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No   R5‑254461
R5‑255204 Addition of test frequencies for Rel17 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.2.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No   R5‑254530
R5‑255205 Addition of test frequency for Rel-18 CA_8A-n77A Huawei, HiSilicon CR Agreement
5.3.12.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No   R5‑254479
R5‑255206 Addition of test frequency for Rel-19 NR CA and EN-DC configurations Huawei, HiSilicon CR Agreement
5.3.35.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No   R5‑254483
R5‑255207 Addition of connecting diagram for Tx switching test cases Huawei, HiSilicon CR Agreement
5.3.22.1TS 38.508-1
Yes
Yes
agreed No   R5‑254623
R5‑255208 Update of Test Equipment diagrams for 2Tx tests Huawei, HiSilicon CR Agreement
5.4.1.4Other clauses, Annexes
Yes
Yes
agreed No   R5‑254468
R5‑255209 Correction of p-max for FR2 default message contents Rohde & Schwarz CR Agreement
5.4.1.4Other clauses, Annexes
Yes
Yes
agreed No   R5‑254156
R5‑255210 Addition of RF baseline implementation capabilities for new PC2 R18 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.10.2TS 38.508-2
Yes
Yes
agreed No   R5‑253792
R5‑255211 Updates for a few three band combos with UL CA with PC2 n77 Verizon Finland CR Agreement
5.3.10.2TS 38.508-2
Yes
Yes
agreed No   R5‑253942
R5‑255212 Updates for PC2 n5 Verizon CR Agreement
5.3.36.2TS 38.508-2
Yes
Yes
agreed No   R5‑253938
R5‑255213 Updates for a few four band combos Verizon CR Agreement
5.3.35.2TS 38.508-2
Yes
Yes
agreed No   R5‑253944
R5‑255214 Adding PICS for several CA configurations including band n71 Huawei, HiSilicon CR Agreement
5.3.35.2TS 38.508-2
Yes
Yes
agreed No   R5‑254616
R5‑255215 Updates for CA_n48(A-B) Verizon Finland CR Agreement
5.3.2.2TS 38.508-2
Yes
Yes
agreed No   R5‑253945
R5‑255216 Adding TP analysis for NS_06 for n14 PC2 Huawei, HiSilicon, China Unicom CR Agreement
5.3.9.5TR 38.905 (NR Test Points Radio Transmission and Reception )
Yes
Yes
agreed No   R5‑254777
R5‑255217 Addition of reference sensitivity for new PC2 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.10.4.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑253798
R5‑255218 Addition of reference sensitivity TP analysis for new EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.10.6TR 38.905 (NR Test Points Radio Transmission and Reception )
Yes
Yes
agreed No   R5‑253797
R5‑255219 Addition of AMPR NS_06 testing for n14 PC2 Huawei, HiSilicon, China Unicom CR Agreement
5.3.9.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254778
R5‑255220 Addition of REFSENS TP analysis for Rel18 HPUE NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.10.6TR 38.905 (NR Test Points Radio Transmission and Reception )
Yes
Yes
agreed No   R5‑254527
R5‑255221 Addition of reference sensitivity requirements for Rel-18 2DL CA for HPUE Anritsu, NTT DOCOMO INC., Huawei, HiSilicon CR Agreement
5.3.10.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254752
R5‑255222 TP analysis for REFSENS for CA_n8A_n78A for PC2 UE Huawei, HiSilicon CR Agreement
5.3.10.6TR 38.905 (NR Test Points Radio Transmission and Reception )
Yes
Yes
agreed No   R5‑254628
R5‑255223 Addition of reference sensitivity requirements for Rel-16 2DL CA Anritsu, Huawei, HiSilicon, NTT DOCOMO INC. CR Agreement
5.3.1.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254748
R5‑255224 Addition of REFSENS TP analysis for Rel16 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No   R5‑254520
R5‑255225 Addition of spurious emission TP analysis information for CA_n40A-n41A Huawei, HiSilicon, CMCC CR Agreement
5.3.1.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No   R5‑254787
R5‑255226 Addition of Tx testing for Rel-18 CA_n8A-n77A Huawei, HiSilicon CR Agreement
5.3.12.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254481
R5‑255227 Addition of test point analysis for Rel-18 CA_n8A-n77A Huawei, HiSilicon CR Agreement
5.3.12.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No   R5‑254482
R5‑255228 Addition of reference sensitivity requirements for Rel-18 2DL CA Anritsu, Huawei, HiSilicon, NTT DOCOMO INC. CR Agreement
5.3.12.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254751
R5‑255229 Addition of REFSENS TP analysis for Rel18 PC3 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.12.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No   R5‑254528
R5‑255230 Additional of A-MPR test case for NS 205 in TS 38.905 China Unicom CR Agreement
5.3.42.3TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No   R5‑254690
R5‑255231 Additional of A-MPR test case for NS 205 in TS 38.521-2 China Unicom CR Agreement
5.3.42.1.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254689
R5‑255232 Addition of AMPR NS_18 testing for n28 PC2 Huawei, HiSilicon, Ericsson CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254782
R5‑255233 Addition of AMPR NS_18 testing for n28 PC2 UL-MIMO test cases Huawei, HiSilicon CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254783
R5‑255234 Adding TP analysis for NS_18 for n28 PC2 Huawei, HiSilicon, Ericsson CR Agreement
5.3.34.5TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No   R5‑254781
R5‑255235 Test points updates for BCS4 and 5 introduced additional ref sense requirements Verizon CR Agreement
5.3.35.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No   R5‑254052
R5‑255236 Updates for BCS4 and 5 introduced additional ref sense requirements Verizon Finland CR Agreement
5.3.35.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254051
R5‑255237 Addition of test point analysis for NS_UAV_44, NS_UAV_46 and NS_UAV_70 Nokia CR Agreement
5.3.33.6TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No   R5‑253868
R5‑255238 Addition of reference sensitivity TP analysis for new R15 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.4.19TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No   R5‑253811
R5‑255239 Adding testing for NS_47 for power class 2 and 3 in AMPR for UL MIMO Huawei, HiSilicon CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254621
R5‑255240 Introduction of General ON/OFF time mask for ATG UE CMCC CR Agreement
5.3.13.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑253878
R5‑255241 Addition of reference sensitivity TP analysis for new three bands and new four bands NRCA combos within FR1 KDDI Corporation (TTC) CR Agreement
5.3.2.10TR 38.905 (NR Test Points Radio Transmission and Reception)
Yes
Yes
agreed No   R5‑254511
R5‑255242 Update of Annex C for valid CORESET 0 Anritsu CR Agreement
5.4.1.4Other clauses, Annexes
Yes
Yes
agreed No    
R5‑255243 ATG Tx Tests - Corrections and updates Keysight Technologies UK Ltd, CMCC CR Agreement
5.3.13.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254069
R5‑255244 Addition of transmit modulation quality test cases for 4Tx UL-MIMO Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254771
R5‑255245 Addition of time alignment for 4Tx UL-MIMO Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
revised No R5‑255246 R5‑254772
R5‑255246 Addition of time alignment for 4Tx UL-MIMO Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑255245
R5‑255247 Updates of transmit part for PC2 n2 and PC2 n66 Verizon CR Agreement
5.3.9.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑253934
R5‑255248 Updates of Reference Sensitivity requirements for PC2 n2 Verizon CR Agreement
5.3.9.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑253936
R5‑255249 Adding testing for CA_n8A-n78A for Power Class 2 UE in maximum output power Huawei, HiSilicon CR Agreement
5.3.10.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254627
R5‑255250 Updates for some combos with UL high power support on n77 Verizon Finland CR Agreement
5.3.10.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No   R5‑253941
R5‑255251 Update to FR1 CA Configurations for R1 PC2 and PC1.5 band combos NTT DOCOMO INC. CR Agreement
5.3.10.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No   R5‑254655
R5‑255252 Updates of transmit part for PC2 n5 Verizon Finland CR Agreement
5.3.36.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑253935
R5‑255253 Updates of Reference Sensitivity requirements for PC2 n5 Verizon Finland CR Agreement
5.3.36.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑253937
R5‑255254 Update to Annex F MUTT for ATG UE CMCC CR Agreement
5.3.13.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No   R5‑253879
R5‑255255 Cleanup of Reference sensitivity for 2DL CA Anritsu, Keysight Technologies UK Ltd CR Agreement
5.3.1.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254747
R5‑255256 Addition of reference sensitivity requirements for Rel-17 2DL CA Anritsu, Huawei, HiSilicon, NTT DOCOMO INC. CR Agreement
5.3.2.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254749
R5‑255257 Addition of AMPR and Spurious emission of CA_n40A-n41A Huawei, HiSilicon, CMCC CR Agreement
5.3.1.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254785
R5‑255258 Addition of new test case AMPR, ASEM and ASE for 4Tx UL MIMO Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254612
R5‑255259 Addition of max input level test cases for 4T UL MIMO and TxD Huawei, HiSilicon CR Agreement
5.3.19.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254558
R5‑255260 Jumbo CR for deltaTIB and deltaRIB Huawei, HiSilicon, CMCC CR Agreement
5.3.35.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254791
R5‑255261 Addition of delta TIBc and MOP for Rel16 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.1.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254647
R5‑255262 Addition of delta TIBc for Rel17 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.2.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254648
R5‑255263 Addition of delta TIBc and MOP for Rel18 PC3 NR CA configurations NTT DOCOMO INC. CR Agreement
5.3.12.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254649
R5‑255264 Update to MOP UL MIMO TC for n28 PC2 40MHz CMCC, Huawei, HiSilicon CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑253904
R5‑255265 Update to MPR UL MIMO TC for n28 PC2 40MHz CMCC, Huawei, HiSilicon CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑253905
R5‑255266 Update to MOP TxD TC for n28 PC2 40MHz CMCC, Huawei, HiSilicon CR Agreement
5.3.34.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑253906
R5‑255268 Updates for UL n77 high power support on a few 3 TDD DL combos Verizon CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yes
agreed No   R5‑253940
R5‑255269 Correcting the MPR test requirements for band n40 and n97 Huawei, HiSilicon, OPPO CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254775
R5‑255270 Update to FR1 CA Configurations for R17 PC2 band combo NTT DOCOMO INC. CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yes
agreed No   R5‑254654
R5‑255271 Corrected incorrect RB allocations for additional MOP TC Qualcomm Technologies Ireland CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254894
R5‑255272 Correction of UTRA ACLR for UL MIMO test case ROHDE & SCHWARZ CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254384
R5‑255273 Updates to 2AoA spherical coverage test Apple Inc CR Agreement
5.3.29.4.2Rx Requirements (Clause 7)
No
Yes
agreed No   R5‑254864
R5‑255274 Update of Beam correspondence for PC6 in clause 6.6.1.3.5 SGS Wireless CR Agreement
5.3.5.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254212
R5‑255275 Add missing in-band blocking requirement for n259 intra-band contiguous CA Apple Inc CR Agreement
5.3.18.4.2Rx Requirements (Clause 7)
No
Yes
agreed No   R5‑254856
R5‑255276 Correction to clause 6.2A.3 Apple CR Agreement
5.4.5.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254428
R5‑255277 Addition of reference sensitivity for new PC2 R19 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.41.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254223
R5‑255278 Addition of reference sensitivity for new R16 EN-DC combos within FR1 KDDI Corporation CR Agreement
5.3.1.5.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑253813
R5‑255279 Corrections on UL Fc frequency for R16 EN-DC configurations for MSD test points ZTE Corporation, Tejet, SRTC CR Agreement
5.3.1.5.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254319
R5‑255280 Addition of reference sensitivity requirements for Rel-16 FR1 2CC EN-DC Anritsu, Huawei, HiSilicon CR Agreement
5.3.1.5.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254756
R5‑255281 Update description of Common test environment and NB-IoT Common contents of system information MediaTek Beijing Inc.,CMCC CR Agreement
5.3.25.1TS 36.508
Yes
Yes
agreed No   R5‑253772
R5‑255282 IoT NTN - Test frequencies definition update for bands 254 and bands 255 Keysight Technologies UK Ltd CR Agreement
5.5.1.1TS 36.508
Yes
Yes
agreed No   R5‑254062
R5‑255283 Addition of RF test frequencies and conditions for variable Tx-Rx spacing for NB-IoT for NTN bands 253, 254 and 255 EchoStar, Viasat CR Agreement
5.5.1.1TS 36.508
Yes
Yes
agreed No   R5‑254249
R5‑255284 Correction to Table 6.6.2.2A.2_1.4.1-3 NS number Apple CR Agreement
5.5.1.3.1Tx Requirements (Clause 6)
Yes
Yes"Revised from: R5-254425r1. wrong WIC was used to reserve on 3gu. "
withdrawn Yes   R5‑254425
R5‑255285 Correction to Table 8.2.1.4.2_A.4.5-2 reference table number Apple CR Agreement
5.5.1.3.3Clauses 1-5, 8-10, Annexes
Yes
Yes
withdrawn Yes   R5‑254426
R5‑255286 update to distance based CHO test cases for NR-NTN QUALCOMM Europe Inc. - Italy CR Agreement
5.3.4.6TS 38.533
No
Yes
agreed No   R5‑254883
R5‑255287 Corrections on channel bandwidths for NTN satellite band in FR2-NTN and sync raster for band n254 ZTE Corporation CR Agreement
5.3.30.4TS 38.521-5
Yes
Yes
agreed No   R5‑254325
R5‑255288 Split of power control test cases ROHDE & SCHWARZ, Keysight CR Agreement
5.3.4.4TS 38.521-5
Yes
Yes
agreed No   R5‑254378
R5‑255289 Core alignment for NR-NTN CBW change test case. Qualcomm Korea CR Agreement
5.3.4.6TS 38.533
No
Yes
agreed No   R5‑254684
R5‑255290 Core alignment for NR-NTN DCI-based BWP switch test case. Qualcomm Korea CR Agreement
5.3.4.6TS 38.533
No
Yes
agreed No   R5‑254686
R5‑255291 Core alignment for NR-NTN RRC-based BWP switch test case. Qualcomm Korea CR Agreement
5.3.4.6TS 38.533
No
Yes
agreed No   R5‑254688
R5‑255292 Completion of NR-NTN timing accuracy test case 14.3.1.1 QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No   R5‑254835
R5‑255293 Core alignment for NR-NTN Handover test cases QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.6TS 38.533
Yes
Yes
agreed No   R5‑254838
R5‑255294 Corrections to default RF test frequencies for n256 and addition of RF test frequencies to verify RF aspects of variable Tx-Rx spacing for NR NTN bands n255 and n256 EchoStar, Viasat CR Agreement
5.3.4.1TS 38.508-1
Yes
Yes
agreed No   R5‑254261
R5‑255295 Additional of applicability of RRM TC 14.1.11 and TC 14.1.12 in TS 38.522 China Unicom CR Agreement
5.3.30.5TS 38.522
Yes
Yes
agreed No   R5‑254141
R5‑255296 FR2 MU - PC3 update for OBW UL MIMO test in 38.521-2 Keysight Technologies UK Ltd CR Agreement
5.4.5.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑253806
R5‑255297 FR2 MU - PC3 MU update for OBW UL MIMO test in 38.521-2 Annex F Keysight Technologies UK Ltd CR Agreement
5.4.5.3Clauses 1-5, Annexes
Yes
Yes
agreed No   R5‑253807
R5‑255298 FR2 MU - PC3 update for OBW UL MIMO test in 38.903 Keysight Technologies UK Ltd CR Agreement
5.4.18TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No   R5‑253805
R5‑255301 Introduction of new test case 6.3.1.2.2 1Rx TDD Single PMI with 4TX TypeI-SinglePanel Codebook for eRedCap CAICT CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No   R5‑253950
R5‑255302 Introduction of new test case 6.3.2.1.10 2Rx FDD Single PMI with 4TX TypeI-SinglePanel Codebook for eRedCap CAICT CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No   R5‑253951
R5‑255303 Introduction of new test case 6.3.2.2.10 2Rx TDD Single PMI with 4TX TypeI-SinglePanel Codebook for eRedCap CAICT CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No   R5‑253952
R5‑255304 Introduction of measurement uncertainty and test tolerance for eRedCap PMI test cases CAICT CR Agreement
5.3.15.4.4Clauses 1-4, Annexes
Yes
Yes
agreed No   R5‑253953
R5‑255305 Introduction of Applicabilities for eRedCap PMI test cases CAICT CR Agreement
5.3.15.5TS 38.522
Yes
Yes
agreed No   R5‑253956
R5‑255306 Addition of RMC for eRedCap ROHDE & SCHWARZ, Keysight Technologies CR Agreement
5.3.15.4.4Clauses 1-4, Annexes
Yes
Yes
agreed No   R5‑254386
R5‑255307 Correction of RedCap PMI test cases CAICT CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No   R5‑253954
R5‑255308 Correction of SA and NSA 2Rx PMI with 4TX test cases CAICT CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No   R5‑253955
R5‑255309 Addition of Es value to the common test parameters in 5.5A.1.1 Keysight Technologies CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No   R5‑254214
R5‑255310 Correction of ATG SA event-triggered reporting test cases 19.5.1.x Ericsson CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No   R5‑254713
R5‑255311 Correction of ATG SA event-triggered reporting test cases 19.5.2.x Ericsson CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No   R5‑254714
R5‑255312 Addition of ATG transmit timing test case 19.3.1.1 ZTE Corporation CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No   R5‑254057
R5‑255313 Addition of ATG timing advance test case 19.3.3.1 ZTE Corporation CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No   R5‑254058
R5‑255314 Updating message contents and test procedures for FeMG test cases Huawei, HiSilicon CR Agreement
5.3.32.4TS 38.533
Yes
Yes
agreed No   R5‑254561
R5‑255315 Core sepc alignment for LTM test cases 6.3.4.1 and 6.3.4.2 MediaTek Inc., Keysight Technologies CR Agreement
5.3.28.4TS 38.533
Yes
Yes
agreed No   R5‑254493
R5‑255316 Core alignment for LTM PCell switch test cases 6.3.4.3 and 6.3.4.4 MediaTek Inc., Keysight Technologies CR Agreement
5.3.28.4TS 38.533
Yes
Yes
agreed No   R5‑254510
R5‑255317 Updates of test applicability for LTM FR1 test cases MediaTek Inc., Keysight Technologies CR Agreement
5.3.28.3TS 38.522
Yes
Yes
agreed No   R5‑254512
R5‑255318 Correction of FR1 NR SA RACH-based LTM PSCell switch test case 6.3.5.1 Ericsson CR Agreement
5.3.28.4TS 38.533
Yes
Yes
agreed No   R5‑254702
R5‑255319 Correction of NR FR2 SA RACH-based LTM PSCell switch test case 7.3.5.1 Ericsson CR Agreement
5.3.28.4TS 38.533
Yes
Yes
agreed No   R5‑254703
R5‑255320 Addition of new test case 9.1.6.3 NR SA FR1 Interruptions at NR sidelink discovery configuration CATT, TDIA CR Agreement
5.3.6.5TS 38.533
No
Yes
agreed No   R5‑254598
R5‑255321 Addition of new test case 9.1.7.1 Selection / Reselection of relay UE TDIA, CATT CR Agreement
5.3.6.5TS 38.533
No
Yes
agreed No   R5‑254599
R5‑255322 Editorial corrections for sections headers Rohde & Schwarz CR Agreement
5.4.10.4NR Standalone in FR1 (Clause 6)
Yes
Yes
agreed No   R5‑254157
R5‑255323 E-UTRA - NR SA FR1 E-UTRA cell re-selection to higher-priority NR target cell for 2 Rx UE test case correction Ericsson CR Agreement
5.4.10.14E-UTRA - NR inter-RAT with E-UTRA serving cell (Clause 18)
Yes
Yes
agreed No   R5‑254717
R5‑255324 Introduction of MU and TT for test case 19.2.3.3.1 NR SA FR1-FR1 RRC connection release with Redirection CAICT CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No   R5‑253958
R5‑255325 Test Tolerance analysis for RRM Inter-frequency RRC Re-establishment in FR1 for ATG Sporton International INC. CR Agreement
5.3.13.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No   R5‑253832
R5‑255326 TT analysis for new test case 19.2.3.3.1 NR SA FR1-FR1 RRC connection release with Redirection CAICT CR Agreement
5.3.13.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No   R5‑253959
R5‑255327 TT analysis for ATG L1-RSRP accuracy RRM test cases 19.6.4.x Huawei, HiSilicon CR Agreement
5.3.13.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No   R5‑254554
R5‑255328 TT analysis for ATG L1-SINR accuracy RRM test cases 19.6.5.x Huawei, HiSilicon CR Agreement
5.3.13.7TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No   R5‑254555
R5‑255329 Revised Test Tolerances analysis for A-TRS based SSB-less SCell activation test cases Nokia CR Agreement
5.3.20.6TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No   R5‑254369
R5‑255330 Correction of event-triggered reporting test cases 7.6.19.x including test tolerance Ericsson CR Agreement
5.3.32.4TS 38.533
Yes
Yes
agreed No   R5‑254706
R5‑255331 TT analysis separation for NR-U and legacy SCell activation and deactivation tests QUALCOMM Europe Inc. - Spain CR Agreement
5.4.18TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No   R5‑254851
R5‑255332 Addition of new UE Rx-Tx time difference reporting delay test case 15.2.16 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No   R5‑253854
R5‑255333 Introducing new NR RSTD measurement accuracy test case for PRS aggregation in FR2 CATT CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No   R5‑254445
R5‑255334 Addition of new NR RSTD measurement accuracy test cases for RedCap UE Ericsson CR Agreement
5.3.27.2TS 37.571-1
Yes
Yes
agreed No   R5‑254716
R5‑255335 Addition of test applicabilities for NR RSTD and UE Rx-Tx time difference test cases CATT CR Agreement
5.3.27.3TS 37.571-3
Yes
Yes
agreed No   R5‑253862
R5‑255336 Adding test applicability for new 4Tx test cases Huawei, HiSilicon CR Agreement
5.3.19.6TS 38.522
No
Yes
agreed No   R5‑254103
R5‑255337 Addition of applicability for test case 5.3.1.2.1 Keysight Technologies, Ericsson CR Agreement
5.4.9TS 38.522
Yes
Yes
agreed No   R5‑254244
R5‑255338 Update to applicability of 5G TCs CMCC, MediaTek CR Agreement
5.4.9TS 38.522
Yes
Yes
agreed No   R5‑253900
R5‑255339 Addition of applicability of RedCap test case 5.3.1.2.1 Ericsson CR Agreement
5.4.9TS 38.522
Yes
Yes
withdrawn Yes   R5‑254644
R5‑255340 Applicability of E-UTRA - NR SA FR1 E-UTRA cell re-selection to higher-priority NR target cell for 2 Rx UE test case Ericsson CR Agreement
5.4.9TS 38.522
Yes
Yes
revised No R5‑255099 R5‑254718
R5‑255341 Update to applicability of 5G ATG TCs CMCC, QUALCOMM Europe Inc. - Spain, ZTE Corporation, Ericsson, Keysight, Huawei, HiSilicon CR Agreement
5.3.13.5TS 38.522
Yes
Yes
agreed No   R5‑253882
R5‑255342 LTE based 5G broadcast RF Rx test cases added Qualcomm Technologies Ireland CR Agreement
5.3.31.3TS 36.521-1
Yes
Yes
agreed No   R5‑254432
R5‑255343 Corrections on test requirements for LTE V2X UE co-existence in 36.521-1 ZTE Corporation CR Agreement
5.5.1.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254335
R5‑255344 Correction to LTE Cat 1bis RRM test case 5.1.19 and 5.1.20 Huawei, HiSilicon CR Agreement
5.5.1.4TS 36.521-3
Yes
Yes
agreed No   R5‑254569
R5‑255345 Clarification on the applicability of re-positioning approach for QoQZ MU Keysight Technologies UK Ltd CR Agreement
5.4.18TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No   R5‑254045
R5‑255346 Discussion on multi-Rx measurement uncertainty QUALCOMM Europe Inc. - Spain discussion Endorsement
5.3.29.10Discussion Papers, Work Plan, TC lists
No
Yes
noted No   R5‑254852
R5‑255347 Completion of REL-18 test requirements (including MU/TT) and update of TS 38.561 TRP TRS tests TSG WG RAN5 LS out Approval
7.6Docs still needing agreement/endorsement/approval (e.g. Outgoing LS, Reports, New Specs, Info for certification bodies etc.)
No
Yes
approved No    
R5‑255348 Rel-19 NR TRP TRS test tolerance values with description TSG WG RAN5 LS out Approval
5.7Outgoing liaison statements for provisional approval
Yes
Yes
approved No    
R5‑255349 Correction of Test Equipment Reference Keysight Technologies UK Ltd, Spirent Communications, ETS-Lindgren CR Agreement
5.6.15TS 37.544
Yes
Yes
agreed No   R5‑254049
R5‑255350 Update of Measurement Performance requirements for ATG CMCC CR Agreement
5.3.13.6TS 38.533
Yes
Yes
agreed No   R5‑253887
R5‑255351 Addition of Annex F MU and TT for 4Tx test cases Huawei, HiSilicon CR Agreement
5.3.19.3.3Clauses 1-5, Annexes
Yes
Yes
agreed No   R5‑254452
R5‑255352 Test case 6.3C.3.2 update according to TP analysis update Keysight Technologies UK Ltd CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254081
R5‑255353 Addition of EVM equalizer spectrum flatness for CA (5UL to 8UL CA) Sporton International INC. CR Agreement
5.4.5.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑253835
R5‑255354 Addition of new test case AMPR, ASEM, ASE for 4Tx Tx Diversity Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254613
R5‑255355 Addition of eRedCap test case 5.2.2.1.23, 2Rx FDD FR1 PDSCH performance for eRedCap Ericsson CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No   R5‑254638
R5‑255356 Correction to applicabilities related to 2-layer MIMO capabilities Huawei, HiSilicon CR Agreement
5.4.9TS 38.522
Yes
Yes
agreed No   R5‑254473
R5‑255357 Addition of eRedCap test case 6.2.2.1.2.5 Ericsson CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No   R5‑254639
R5‑255358 Adding test frequencies for V2X intra-band concurrent operation Huawei, HiSilicon CR Agreement
4.5.2RF group docs for WG review/verdict - original A.I. retained
Yes
Yes
agreed No   R5‑254769
R5‑255359 Update of Rel-16 interferer CA test cases ROHDE & SCHWARZ CR Agreement
5.3.1.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254381
R5‑255360 Update of Rel-15 interferer CA test cases ROHDE & SCHWARZ CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254382
R5‑255361 Corrections to IoT-NTN RRM test cases Rohde & Schwarz CR Agreement
5.5.1.4TS 36.521-3
Yes
Yes
withdrawn Yes   R5‑254142
R5‑255362 Update to NR-NTN test applicability QUALCOMM Europe Inc. - Spain CR Agreement
5.3.4.5TS 38.522
No
Yes
agreed No   R5‑254843
R5‑255363 Test Tolerance update for intra-frequency RACH-less Handover for Satellite Access test 14.2.1.8. Qualcomm Korea CR Agreement
5.3.30.6TS 38.533
No
Yes
agreed No   R5‑254677
R5‑255364 Test Tolerance update for RACH-based Hard Satellite switching for Satellite Access test 14.2.2.4. Qualcomm Korea CR Agreement
5.3.30.6TS 38.533
No
Yes
agreed No   R5‑254678
R5‑255365 Test Tolerance update for RACH-less Soft Satellite switching for Satellite Access test 14.2.2.5. Qualcomm Korea CR Agreement
5.3.30.6TS 38.533
No
Yes
agreed No   R5‑254679
R5‑255366 Test Tolerance update in Annex F for NR NTN handover and Satellite switching test cases. Qualcomm Korea CR Agreement
5.3.30.6TS 38.533
No
Yes
agreed No   R5‑254680
R5‑255367 Test Tolerance analysis for intra-frequency RACH-less Handover for Satellite Access test 14.2.1.8. Qualcomm Korea CR Agreement
5.3.30.7TR 38.903 (NR MU & TT analyses)
No
Yes
agreed No   R5‑254681
R5‑255368 Test Tolerance analysis for intra-frequency RACH-based Hard Satellite switching for Satellite Access test 14.2.2.4. Qualcomm Korea CR Agreement
5.3.30.7TR 38.903 (NR MU & TT analyses)
No
Yes
agreed No   R5‑254682
R5‑255369 Test Tolerance analysis for intra-frequency RACH-less Soft Satellite switching for Satellite Access test 14.2.2.5. Qualcomm Korea CR Agreement
5.3.30.7TR 38.903 (NR MU & TT analyses)
No
Yes
agreed No   R5‑254683
R5‑255370 Addition of test tolerance analysis for intra-frequency HST FR2 cell re-selection test case Nokia CR Agreement
5.3.5.7TR 38.903 (NR MU & TT analyses)
Yes
Yes"Revised from: R5-254363r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254363
R5‑255371 Correction to A-TRS based SSB-less SCell Activation test cases including TT Nokia CR Agreement
5.3.20.5TS 38.533
Yes
Yes" Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254365
R5‑255372 Introduction of test channel bandwidths and test frequencies for band n110 Nokia CR Agreement
5.3.40.1.1Test frequencies (Clause 4.3.1)
Yes
Yes
agreed No   R5‑254087
R5‑255373 Demodulation test frequencies for band n110 Nokia CR Agreement
5.3.40.1.2Test environment for RF (Clauses 5)
Yes
Yes
agreed No   R5‑254089
R5‑255374 Addition of TT for test case 14.2.2.3.1. Keysight Technologies CR Agreement
5.3.4.6TS 38.533
Yes
No"Revised from: R5-254300r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254300
R5‑255375 Update Annex F MU and TT for 14.2.2.3.1 Test case Keysight Technologies CR Agreement
5.3.4.6TS 38.533
Yes
No"Revised from: R5-254301r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254301
R5‑255376 Addition of TT analysis for NR-NTN test 14.2.2.3.1 Keysight Technologies UK Ltd CR Agreement
5.3.4.7TR 38.903 (NR MU & TT analyses)
Yes
No"Revised from: R5-254299r3. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254299
R5‑255377 3CC intraband non-contiguous updates Keysight Technologies UK Ltd CR Agreement
5.3.2.3.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254076
R5‑255378 FR1 MUs up to 7.125GHz - RF single carrier UL SISO Tx tests update Keysight Technologies UK Ltd CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254072
R5‑255379 FR1 MUs up to 7.125GHz - RF single carrier UL SISO Rx tests update Keysight Technologies UK Ltd CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254073
R5‑255380 FR1 MUs up to 7.125GHz - RF single carrier UL SISO tests - MU and TT update in annex F Keysight Technologies UK Ltd CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yes
agreed No   R5‑254074
R5‑255381 Addition of ATG CSI-RS based inter-frequency measurement accuracy test cases Huawei, HiSilicon CR Agreement
5.3.13.6TS 38.533
Yes
Yes"Revised from: R5-254548r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254548
R5‑255382 Addition of transmit modulation quality test cases for 4Tx Tx diversity Huawei, HiSilicon CR Agreement
5.3.19.3.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254773
R5‑255383 Updating EPRE ratio of AP CSI-RS to SSS for Rel-16 and Rel-17 Tx switching test cases Huawei, HiSilicon CR Agreement
5.4.10.4NR Standalone in FR1 (Clause 6)
Yes
Yes"Revised from: R5-254565r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254565
R5‑255385 Test Frequency Calculation Tool, updates and way forward. Ericsson discussion Information
5.3.2.11Discussion Papers, Work Plan, TC lists
Yes
Yes
noted No   R5‑254695
R5‑255386 Introduction of new test case 6.3.1.1.2 1Rx FDD Single PMI with 4TX TypeI-SinglePanel Codebook for eRedCap CAICT CR Agreement
5.3.15.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No   R5‑253949
R5‑255387 Correction to TC5.6.5.1 with TT analysis Apple CR Agreement
5.3.8.4TS 38.533
Yes
Yes
agreed No   R5‑254416
R5‑255388 Annex F modification for some TCs Apple CR Agreement
5.3.8.4TS 38.533
Yes
Yes
agreed No   R5‑254424
R5‑255389 TT analysis for TC5.6.5.1 Apple CR Agreement
5.3.8.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
agreed No   R5‑254417
R5‑255390 TT analysis for TC7.6.2.9 Apple CR Agreement
5.3.8.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
withdrawn Yes   R5‑254421
R5‑255391 TT analysis for TC7.6.5.1 Apple CR Agreement
5.3.8.5TR 38.903 (NR MU & TT analyses)
Yes
Yes
withdrawn Yes   R5‑254423
R5‑255392 Addition of UE Beamlock_IDLE test function Apple CR Agreement
5.3.18.3TS 38.509
Yes
Yes
withdrawn Yes   R5‑254818
R5‑255393 Updates to TC 6.6.3 Beam Correspondence in RRC_INACTIVE and initial access Apple AB Denmark CR Agreement
5.3.18.4.1Tx Requirements (Clause 6)
Yes
Yes
withdrawn Yes   R5‑254817
R5‑255394 Addition of FR2 RF testability issue list to specification Apple Inc CR Agreement
5.4.5.3Clauses 1-5, Annexes
No
Yes
agreed No   R5‑254862
R5‑255396 Cleanup of Reference sensitivity for 2CC FR1 EN-DC Anritsu, Keysight Technologies UK Ltd, KDDI Corporation, ZTE CR Agreement
5.3.1.5.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254754
R5‑255397 Update of RMCs for FR1-NTN TRx testing with SCS 15 kHz and 30 kHz Anritsu CR Agreement
5.3.4.4TS 38.521-5
Yes
No"Revised from: R5-254746r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254746
R5‑255398 Updated procedure to skip interferer overlapping with PCC in Rx TCs for 3CC later Anritsu, R&S, Keysight CR Agreement
5.4.4.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254732
R5‑255399 Clarification of LCRB in Figure 5.3.1-1 Anritsu CR Agreement
5.4.4.3Clauses 1-5, Annexes
Yes
Yes"Revised from: R5-254744r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254744
R5‑255400 Addition of reference sensitivity for PC2 DC_66A_n41A ZTE Corporation CR Agreement
5.4.6.2Rx Requirements (Clause 7)
Yes
Yes
agreed No   R5‑254315
R5‑255401 Correction of Rel-16 UL Tx switching test cases ROHDE & SCHWARZ CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254387
R5‑255402 Corrected incorrect K2 value for Tx on off test case Qualcomm Technologies Ireland CR Agreement
5.4.4.1Tx Requirements (Clause 6)
Yes
Yes
agreed No   R5‑254895
R5‑255403 Updated the Test case 14.1.11 in TS 38.533 China Unicom CR Agreement
5.3.30.6TS 38.533
Yes
Yes"Revised from: R5-254138r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254138
R5‑255404 Updated the Test case 14.1.12 in TS 38.533 China Unicom CR Agreement
5.3.30.6TS 38.533
Yes
Yes"Revised from: R5-254139r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254139
R5‑255405 Confirmation of the 38.306 IE for the number of Tx ports capabiliy required in PMI test cases in 38.521-4 CAICT CR Agreement
5.4.2TS 38.508-2
Yes
Yes"Revised from: R5-253948r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑253948
R5‑255406 Confirmation of Applicability for PMI test cases CAICT CR Agreement
5.4.9TS 38.522
Yes
Yes"Revised from: R5-253957r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑253957
R5‑255407 Update on SUL test scenario Keysight Technologies CR Agreement
5.4.10.4NR Standalone in FR1 (Clause 6)
Yes
Yes"Revised from: R5-254391r2. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254391
R5‑255408 Transmit power density and A-MPR updates for band n254 Keysight Technologies UK Ltd CR Agreement
5.4.8TS 38.521-5
Yes
Yes
agreed No   R5‑254855
R5‑255409 Transmit EIRP density and A-MPR updates for band 254 Keysight Technologies UK Ltd CR Agreement
5.5.1.5TS 36.521-4
Yes
Yes
agreed No   R5‑254853
R5‑255410 Updates in Annex G.4 for mTT for 0.001% BLER Keysight Technologies CR Agreement
5.4.7.4Clauses 1-4, Annexes
Yes
Yes"Revised from: R5-254235r1. withdrawn since the N/A is not concluded for all ne's in the statistical limit table , group consensus to raise an AP to fix the issue across all tests and the complete stat limit table"
withdrawn Yes   R5‑254235
R5‑255411 Addition of test case 5.3.3.1.6 4RX FDD FR1 PDCCH antenna performance for 3 MHz channel bandwidth Ericsson CR Agreement
5.3.37.4.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
Yes
Yes
agreed No   R5‑254641
R5‑255412 Update of CSI-RS message for 6.3.2.1.7 and 6.3.2.2.8 Huawei, HiSilicon CR Agreement
5.4.7.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
No
Yes"Revised from: R5-254472r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254472
R5‑255413 Correction to LTE measurement reporting test case 8.1.3 Huawei, HiSilicon CR Agreement
5.5.1.4TS 36.521-3
Yes
Yes
agreed No   R5‑254571
R5‑255414 Core alignment and update for NR-NTN Cell reselection test cases. Qualcomm Korea CR Agreement
5.3.4.6TS 38.533
No
Yes"Revised from: R5-254685r5. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254685
R5‑255415 Addition of missing aperiodic CQI triggering parameters for PDSCH abs ph layer tput test cases QUALCOMM Europe Inc. - Italy CR Agreement
5.3.26.3.1Conducted Demod Performance and CSI Reporting Requirements (Clauses 5&6)
No
Yes"Revised from: R5-254879r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254879
R5‑255416 Update to PDSCH RMC for PDCCH test cases QUALCOMM Europe Inc. - Italy CR Agreement
5.4.7.4Clauses 1-4, Annexes
No
Yes"Revised from: R5-254885r1. Document was sent FOR E-MAIL AGREEMENT "
for email agreement No   R5‑254885
R5‑255417 Update to applicability of gap-based RRM FR2 tests QUALCOMM Europe Inc. - Spain CR Agreement
5.4.10.3EN-DC with at least 1 NR Cell in FR2 (Clause5)
No
Yes
agreed No   R5‑254840
R5‑255418 Update to applicability of gap-based RRM FR2 tests QUALCOMM Europe Inc. - Spain CR Agreement
5.4.9TS 38.522
No
Yes
agreed No   R5‑254844
R5‑255419 Test Tolerance update for HD-FDD UE Timing Advance Adjustment Accuracy Test 7.2.9,13.4.2.1 and 13.4.2.2. Qualcomm Korea CR Agreement
5.5.1.4TS 36.521-3
No
Yes
agreed No   R5‑254674
R5‑255420 Test Tolerance update in Annex F for NB-NTN UE Timing Advance Adjustment Accuracy test cases. Qualcomm Korea CR Agreement
5.5.1.4TS 36.521-3
No
Yes
withdrawn Yes   R5‑254675