3GPP TDocs (written contributions) at meeting
Meeting: C3-56 - 2009-11-09 to 2009-11-13, Beijing
meeting id: C3-56 (click id for more info on this meeting)Click on the Tdoc to open its file.
TDoc | Title | Source | Remarks |
---|---|---|---|
C3_092010 | Title * : Completion of IMS Restoration Procedures | - | - |
C3‑091602 | Draft Agenda for CT3#56 | CT3 Chairman | Approved |
C3‑091603 | Allocation of documents to agenda items (at deadline) | CT3 Chairman | Noted |
C3‑091604 | Allocation of documents to agenda items (start of Day1) | CT3 Chairman | Noted |
C3‑091605 | Allocation of documents to agenda items (start of Day2) | CT3 Chairman | Noted |
C3‑091606 | Allocation of documents to agenda items (start of Day3) | CT3 Chairman | Noted |
C3‑091607 | Allocation of documents to agenda items (start of Day4) | CT3 Chairman | Noted |
C3‑091608 | Allocation of documents to agenda items (start of Day5) | CT3 Chairman | Noted |
C3‑091609 | Allocation of documents to agenda items (end of Day5) | CT3 Chairman | Noted |
C3‑091610 | Draft Report from CT3#55 | MCC | Approved |
C3‑091611 | Latest Version of 3GPP Workplan | MCC | Noted |
C3‑091612 | Status of CT3 specifications following CT#45 meeting | MCC | Approved |
C3‑091613 | Meeting Calendar for 2009 and 2010 | MCC | Revised in C3-091771 |
C3‑091614 | Re-LS on endorsement of ETSI TISPAN ES 283 012^^ | ETSI TISPAN | Noted |
C3‑091615 | Reply to LS on IMS media plane security | 3GPP TSG CT WG1 | Noted |
C3‑091616 | Reply LS on Diameter Roaming Interfaces | 3GPP TSG CT4 | Postponed |
C3‑091617 | Reply LS on IMS media plane security | 3GPP TSG CT4 | Noted |
C3‑091618 | LS on eCALL data transfer | 3GPP TSG CT4 | Revised in C3-091770 |
C3‑091619 | LS on removing the table mapping access types from 29.275 | CT4 | Noted |
C3‑091620 | Interworking ISUP OLI parameter | Alcatel-Lucent | Revised in C3-091821 |
C3‑091621 | Interworking ISUP OLI parameter | Alcatel-Lucent | Revised in C3-091822 |
C3‑091622 | GTT-Voice <> GTT-IP interworking | Alcatel-Lucent | Noted |
C3‑091623 | Mandatory features in TrGW | Alcatel-Lucent | Revised in C3-091812 |
C3‑091624 | Specification clean-up | Alcatel-Lucent | Revised in C3-091813 |
C3‑091625 | Report the UE time zone information to the PCRF | Huawei | Revised in C3-091841 |
C3‑091626 | PCC Support for CSG(R9 29.212) | Huawei | Revised in C3-091912 |
C3‑091627 | PCC Support for CSG(R9 29.215) | Huawei | Postponed |
C3‑091628 | Correction for the missing Charging-Rule-Base-Name | Huawei | Revised in C3-091842 |
C3‑091629 | Correction for the missing Charging-Rule-Base-Name(R8 29.212) | Huawei | Revised in C3-091843 |
C3‑091630 | Correction for the missing Charging-Rule-Base-Name(R9 29.212) | Huawei | Revised in C3-091844 |
C3‑091631 | AF procedure for the Specific-Action | Huawei | Revised in C3-091930 |
C3‑091632 | AF procedure for the Specific-Action | Huawei | merged with 1670 into 1848 |
C3‑091633 | AF procedure for the Specific-Action | Huawei | merged with 1671 into 1849 |
C3‑091634 | QCI change during an MS-Initiated EPS Bearer Modification Procedure(R8 29.212) | Huawei | Revised in C3-091856 |
C3‑091635 | QCI change during an MS-Initiated EPS Bearer Modification Procedure(R9 29.212) | Huawei | Revised in C3-091857 |
C3‑091636 | Message flow of PCRF failure reselection for the redirect DRA (R9 29.816) | Huawei | Revised in C3-091887 |
C3‑091637 | Cleaning of the Editor's Notes | Huawei | Revised in C3-091858 |
C3‑091638 | Cleaning of the Editor's Notes | Huawei | Revised in C3-091859 |
C3‑091639 | Cleaning of the Editor's Notes | Huawei | Agreed |
C3‑091640 | Cleaning of the Editor's Notes | Huawei | Agreed |
C3‑091641 | LS on setting of IP-CAN type value | TSG SA WG2 | Noted |
C3‑091642 | Reply LS on IMS emergency session support in non-3GG access | TSG SA WG2 | Noted |
C3‑091643 | Proposed Schedule for CT3#56 | CT3 Chairman | Revised in C3-091774 |
C3‑091644 | Status of CT3 Work Items | CT3 Chairman | Revised in C3-092015 |
C3‑091645 | Abbreviations Tidy-Up | LM Ericsson | Revised in C3-091814 |
C3‑091646 | Non-Call Related Procedure Alignment | LM Ericsson | Agreed |
C3‑091647 | Use of IP Interface Type | LM Ericsson | Revised in C3-091815 |
C3‑091648 | Traffic Policing | LM Ericsson | Revised in C3-091816 |
C3‑091649 | Mapping for Communication Barring Service | LM Ericsson | Revised in C3-091823 |
C3‑091650 | Mapping for Communication Barring Service | LM Ericsson | Revised in C3-091824 |
C3‑091651 | Mandatory Features in the CS-TrGW | LM Ericsson | Agreed |
C3‑091652 | Non-Call Related Procedure Alignment | LM Ericsson | Agreed |
C3‑091653 | Traffic Policing | LM Ericsson | Revised in C3-091809 |
C3‑091654 | Reference Tidy-Up | LM Ericsson | Revised in C3-091830 |
C3‑091655 | Miscellaneous Corrections | LM Ericsson | Revised in C3-091831 |
C3‑091656 | Mapping of CPC | LM Ericsson | Withdrawn |
C3‑091657 | Customized Ringing Signal (CRS) modification | Ericsson,Telecom Italia | Revised in C3-091794 |
C3‑091658 | Completing the Personal Network Management (PNM) supplementary service | Ericsson,Telecom Italia | Revised in C3-091795 |
C3‑091659 | Aligning existing supplementary services | Ericsson,Telecom Italia | Revised in C3-091796 |
C3‑091660 | Completing the Flexible Alerting (FA) supplementary service | Ericsson,Telecom Italia | Revised in C3-091797 |
C3‑091661 | Completing the Closed User Group (CUG) supplementary service | Ericsson,Telecom Italia | Revised in C3-091798 |
C3‑091662 | Completing the Three-Party (3PTY) and Conference (CONF) supplementary services | Ericsson,Telecom Italia | Revised in C3-091799 |
C3‑091663 | Completing the Anonymous Communication Rejection (ACR) supplementary service | Ericsson,Telecom Italia | Revised in C3-091800 |
C3‑091664 | Completing Completion of Communications to Busy Subscriber (CCBS) and Completion of Communications by No Reply (CCNR) supplementary services | Ericsson,Telecom Italia | Revised in C3-091801 |
C3‑091665 | Completing Message Waiting Indication (MWI) supplementary service | Ericsson,Telecom Italia | Agreed |
C3‑091666 | Completing the Terminating Identification Presentation (TIP) and Terminating Identification Restriction (TIR) needs to be completed. | Ericsson,Telecom Italia | Revised in C3-091802 |
C3‑091667 | Completing the Communication Barring (CB) supplementary service | Ericsson,Telecom Italia | Revised in C3-091803 |
C3‑091668 | Completing Explicit Communication Transfert (ECT) | Ericsson | Revised in C3-091804 |
C3‑091669 | Completing Communication DIVersion (CDIV) supplementary services | Ericsson,Telecom Italia | Revised in C3-091805 |
C3‑091670 | PCEF-Initiated IP-CAN session modification flows | Ericsson | Revised in C3-091848 |
C3‑091671 | PCEF-Initiated IP-CAN session modification flows | Ericsson | Revised in C3-091849 |
C3‑091672 | 3GPP-RAT-Type support for backward compatibility | Ericsson | Revised in C3-091860 |
C3‑091673 | 3GPP-RAT-Type support for backward compatibility | Ericsson | Revised in C3-091861 |
C3‑091674 | Usage monitoring support in the flows | Ericsson | Agreed |
C3‑091675 | Clarifications in Time of Day Procedures | Ericsson | Withdrawn |
C3‑091676 | Clarifications in Time of Day Procedures | Ericsson | Withdrawn |
C3‑091677 | Completion of IMS Restoration Procedures | Ericsson | Revised in C3-091987 |
C3‑091678 | Requirements for HOLD service over II-NNI | Telecom Italia | Revised in C3-091806 |
C3‑091679 | Requirements for CW service over II-NNI | Telecom Italia | Revised in C3-091793 |
C3‑091680 | Aligning references to P-Asserted-Service | Ericsson, Orange | Revised in C3-091788 |
C3‑091681 | Aligning references to P-Asserted-Service | Ericsson, Orange | Revised in C3-091787 |
C3‑091682 | Filling of the table about major capabilities on II-NNI | Orange, Nokia Siemens Networks | Revised in C3-091807 |
C3‑091683 | IMS entities involved in the modification of the format of the Request-URI | Orange | Revised in C3-091792 |
C3‑091684 | Deletion of an editors note on OIR service | Orange | Revised in C3-091808 |
C3‑091685 | Annex A header updated | Orange | Revised in C3-091790 |
C3‑091686 | Annex A header updated | Orange | Revised in C3-091789 |
C3‑091687 | Bandwidth policing | Nokia Siemens Networks,^^Alcatel-Lucent | merged with C3-091653 into C3-091809 |
C3‑091688 | Bandwidth policing | Nokia Siemens Networks,^^Alcatel-Lucent | merged with C3-091648 into C3-091816 |
C3‑091689 | Handling of RTCP | Nokia Siemens Networks,^^Alcatel-Lucent | Revised in C3-091810 |
C3‑091690 | Handling of RTCP | Nokia Siemens Networks,^^Alcatel-Lucent | Revised in C3-091817 |
C3‑091691 | Media Inactivity Detection | Nokia Siemens Networks,^^Alcatel-Lucent | Revised in C3-091811 |
C3‑091692 | Media Inactivity Detection | Nokia Siemens Networks,^^Alcatel-Lucent | Revised in C3-091818 |
C3‑091693 | Mapping of ISUP Cause values in CPG or ACM to SIP reason header in provisional responses | Nokia Siemens Networks | Revised in C3-091829 |
C3‑091694 | Interworking of text telephony at the MGCF | Nokia Siemens Networks | Noted |
C3‑091695 | V-AF Subscription to Notification of Signalling Path Status | Nokia Siemens Networks | Agreed |
C3‑091696 | V-AF Subscription to Notification of Signalling Path Status | Nokia Siemens Networks | Agreed |
C3‑091697 | CW and NDUB interaction added | Ericsson, Research in Motion | Revised in C3-091828 |
C3‑091698 | Corrections on setting of IP-CAN Type value | Qualcomm Europe | Revised in C3-091862 |
C3‑091699 | Corrections on setting of IP-CAN Type value | Qualcomm Europe | Revised in C3-091863 |
C3‑091700 | PCC/QoS rule modification failure handling | Qualcomm Europe | merged into C3-091900 |
C3‑091701 | PCC/QoS rule modification failure handling | Qualcomm Europe | merged into C3-091901 |
C3‑091702 | EPC-based non-3GPP Annex | Qualcomm Europe | Revised in C3-091864 |
C3‑091703 | EPC-based non-3GPP Annex | Qualcomm Europe | Revised in C3-091865 |
C3‑091704 | Resolve editors note on MCC/MNC AVP | Qualcomm Europe | Revised in C3-091866 |
C3‑091705 | Resolve editors note on MCC/MNC AVP | Qualcomm Europe | Revised in C3-091867 |
C3‑091706 | Multimedia Priority Service (MPS) | Telcordia Technologies, NCS, AT&T | Noted |
C3‑091707 | Multimedia Priority Service (MPS) | Telcordia Technologies, NCS, | Revised in C3-091893 |
C3‑091708 | Multimedia Priority Service (MPS) | Telcordia Technologies, NCS, AT&T | Withdrawn |
C3‑091709 | Multimedia Priority Service (MPS) | Telcordia Technologies, NCS, AT&T | Withdrawn |
C3‑091710 | Mapping of From header at O-MGCF | Deutsche Telekom | Revised in C3-091825 |
C3‑091711 | Mapping of From header at O-MGCF | Deutsche Telekom | Revised in C3-091826 |
C3‑091712 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for HR | Alcatel-Lucent | Revised in C3-091850 |
C3‑091713 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for HR | Alcatel-Lucent | Revised in C3-091851 |
C3‑091714 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for VA | Alcatel-Lucent | Revised in C3-091852 |
C3‑091715 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for VA | Alcatel-Lucent | Revised in C3-091853 |
C3‑091716 | Use of QoS Information AVP V-PCRF Acceptable QoS Offer | Alcatel-Lucent | replaced by C3-091868 |
C3‑091717 | Use of QoS Information AVP V-PCRF Acceptable QoS Offer | Alcatel-Lucent | replaced by C3-091869 |
C3‑091718 | V-PCRF Handling of BBERF CCR/CCA Messages | Alcatel-Lucent | Revised in C3-091919 |
C3‑091719 | V-PCRF Handling of BBERF CCR/CCA Messages | Alcatel-Lucent | Revised in C3-091920 |
C3‑091720 | Charge-Rule Report AVP at Command Level | Alcatel-Lucent | Withdrawn |
C3‑091721 | Charge-Rule Report AVP at Command Level | Alcatel-Lucent | Withdrawn |
C3‑091722 | Supported Features for Rel-9 Gx and Gxx | Camiant | Revised in C3-091873 |
C3‑091723 | Supported Features for Rel-9 Rx | Camiant | Revised in C3-091874 |
C3‑091724 | Rx request handling | Camiant | Revised in C3-091845 |
C3‑091725 | Rx request handling | Camiant | Revised in C3-091846 |
C3‑091726 | Rx request handling | Camiant | Revised in C3-091847 |
C3‑091727 | Supported-Features for S9 | Camiant | Agreed |
C3‑091728 | Supported-Features for S9 | Camiant | Revised in C3-091875 |
C3‑091729 | Deferred session linking handling in roaming scenario | ZTE | Revised in C3-091854 |
C3‑091730 | Deferred session linking handling in roaming scenario | ZTE | Revised in C3-091855 |
C3‑091731 | Clarification of the Event-Report-Indication AVP | ZTE | Revised in C3-091870 |
C3‑091732 | Clarification of the Event-Report-Indication AVP | ZTE | Revised in C3-091871 |
C3‑091733 | Bearer control mode selection over S9 | ZTE | Revised in C3-091876 |
C3‑091734 | Bearer control mode selection over S9 | ZTE | Revised in C3-091877 |
C3‑091735 | Deferred session linking handling in home routed case | ZTE | Withdrawn |
C3‑091736 | Deferred session linking handling in home routed case | ZTE | Withdrawn |
C3‑091737 | Deferred session linking handling in visited access case | ZTE | Revised in C3-091878 |
C3‑091738 | Deferred session linking handling in visited access case | ZTE | Revised in C3-091879 |
C3‑091739 | Session linking handling of MUPSAP in home routed case | ZTE | Agreed |
C3‑091740 | Session linking handling of MUPSAP in visited access case | ZTE | Revised in C3-091884 |
C3‑091741 | PCEF-initiated IP-CAN session modification, AF located in HPLMN | ZTE | merged into C3-091848 |
C3‑091742 | PCEF-initiated IP-CAN session modification, AF located in HPLMN | ZTE | merged into C3-091849 |
C3‑091743 | PCEF-initiated IP-CAN session modification, AF located in the VPLMN | ZTE | merged into C3-091848 |
C3‑091744 | PCEF-initiated IP-CAN session modification, AF located in the VPLMN | ZTE | merged into C3-091848 |
C3‑091745 | Adding the missed AVP in the RAA command of S9 | ZTE | Agreed |
C3‑091746 | Adding the missed AVP in the RAA command of S9 | ZTE | Agreed |
C3‑091747 | Correction to the clause of S9 re-use AVPs | ZTE | replaced by C3-091880 |
C3‑091748 | Correction to the clause of S9 re-use AVPs | ZTE | replaced by C3-091881 |
C3‑091749 | Correction to applicability of the PDN-Connection-ID AVP | ZTE | Revised in C3-091885 |
C3‑091750 | Clarification of the MBMS-HC-Indicator AVP | ZTE | Agreed |
C3‑091751 | Add missed re-used AVPs in Table 20.5.1 | ZTE | replaced by C3-091890 |
C3‑091752 | Details on failure detection | NEC | Revised in C3-091886 |
C3‑091753 | Requirement on emergency and priority services handling and configurability for the operator | NEC | Revised in C3-091888 |
C3‑091754 | Details on PCRF session state restoration | NEC | Revised in C3-091889 |
C3‑091755 | Adding details to graceful termination of bearer services | NEC | Revised in C3-091891 |
C3‑091756 | PCC/QoS rule modification failure handling | Nokia Siemens Networks | Revised in C3-091900 |
C3‑091757 | Failure detection | Nokia Siemens Networks | Revised in C3-091892 |
C3‑091758 | Soft recovery | Nokia Siemens Networks | Revised in C3-091895 |
C3‑091759 | Actions for solution 2 | Nokia Siemens Networks | Revised in C3-091906 |
C3‑091760 | P-CSCF Restoration procedure | Ericsson | Withdrawn |
C3‑091761 | P-CSCF Restoration procedure | Ericsson | Revised in C3-091882 |
C3‑091762 | P-CSCF Restoration procedure | Ericsson | Withdrawn |
C3‑091763 | P-CSCF Restoration procedure | Ericsson | Withdrawn |
C3‑091764 | P-CSCF failover procedures | Ericsson | Revised in C3-091883 |
C3‑091765 | Support interworking of Call Forwarding information | Ericsson | merged into C3-091827 |
C3‑091766 | Clarification for Editors Notes on strict termination | NEC | Revised in C3-091907 |
C3‑091767 | Providing an eCall indication to the PSAP | Qualcomm Europe, Orange Edata | Noted |
C3‑091768 | Principles for PCC/QoS rule modification failure handling | Ericsson | Noted |
C3‑091769 | Revised WID on CT1 aspects of SRVCC support for IMS Emergency Calls | Ericsson | Revised in C3-091904 |
C3‑091770 | LS on eCALL data transfer | 3GPP TSG CT4 | Noted |
C3‑091771 | Meeting Calendar for 2009 and 2010 | MCC | Revised in C3-091897 |
C3‑091772 | IMS entities involved in the modification of the format of the Request-URI | Orange | Revised in C3-091791 |
C3‑091773 | Supported Features for Rel-8 Gx | Camiant | Agreed |
C3‑091774 | Proposed Schedule for CT3#56 | CT3 Chairman | Revised in C3-091872 |
C3‑091775 | A friendly reminder | CT3 Chairman | Noted |
C3‑091776 | Destination Realm | NTT DOCOMO | Revised in C3-091922 |
C3‑091777 | Destination Realm | NTT DOCOMO | Revised in C3-091923 |
C3‑091778 | IP-SM-GW enhancements for CPM-SMS Interworking | Ericsson, ST-Ericsson | Revised in C3-091948 |
C3‑091779 | Discussion on Enabling of IP Flows | ZTE | Noted |
C3‑091780 | Correction to the Enabling of IP Flows in 29.213 | ZTE | Revised in C3-091908 |
C3‑091781 | Correction to the Enabling of IP Flows in 29.213 | ZTE | Revised in C3-091909 |
C3‑091782 | Correction to the Enabling of IP Flows in 29.213 | ZTE | Revised in C3-091910 |
C3‑091783 | Correction to the Enabling of IP Flows in 29.214 | ZTE | Withdrawn |
C3‑091784 | Correction to the Enabling of IP Flows in 29.214 | ZTE | Withdrawn |
C3‑091785 | Correction to the Enabling of IP Flows in 29.214 | ZTE | Withdrawn |
C3‑091786 | Response LS on eCall data transfer | - | Revised in C3-091947 |
C3‑091787 | Aligning references to P-Asserted-Service | Ericsson, Orange | Withdrawn |
C3‑091788 | Aligning references to P-Asserted-Service | Ericsson, Orange | Revised in C3-091971 |
C3‑091789 | Annex A header updated | Orange | Revised in C3-091955 |
C3‑091790 | Annex A header updated | Orange | Revised in C3-091956 |
C3‑091791 | IMS entities involved in the modification of the format of the Request-URI | Orange | Postponed |
C3‑091792 | IMS entities involved in the modification of the format of the Request-URI | Orange | Postponed |
C3‑091793 | Requirements for CW service over II-NNI | Telecom Italia, Ericsson | Revised in C3-091972 |
C3‑091794 | Customized Ringing Signal (CRS) modification | Ericsson,Telecom Italia | Agreed |
C3‑091795 | Completing the Personal Network Management (PNM) supplementary service | Ericsson,Telecom Italia | Revised in C3-091959 |
C3‑091796 | Aligning existing supplementary services | Ericsson,Telecom Italia | Agreed |
C3‑091797 | Completing the Flexible Alerting (FA) supplementary service | Ericsson,Telecom Italia | Agreed |
C3‑091798 | Completing the Closed User Group (CUG) supplementary service | Ericsson,Telecom Italia | Agreed |
C3‑091799 | Completing the Three-Party (3PTY) and Conference (CONF) supplementary services | Ericsson,Telecom Italia | Revised in C3-091980 |
C3‑091800 | Completing the Anonymous Communication Rejection (ACR) supplementary service | Ericsson,Telecom Italia | Revised in C3-091960 |
C3‑091801 | Completing Completion of Communications to Busy Subscriber (CCBS) and Completion of Communications by No Reply (CCNR) supplementary services | Ericsson,Telecom Italia | Revised in C3-091961 |
C3‑091802 | Completing the Terminating Identification Presentation (TIP) and Terminating Identification Restriction (TIR) needs to be completed. | Ericsson,Telecom Italia | Agreed |
C3‑091803 | Completing the Communication Barring (CB) supplementary service | Ericsson,Telecom Italia | Revised in C3-091962 |
C3‑091804 | Completing Explicit Communication Transfert (ECT) | Ericsson | Revised in C3-091963 |
C3‑091805 | Completing Communication DIVersion (CDIV) supplementary services | Ericsson,Telecom Italia | Revised in C3-091964 |
C3‑091806 | Requirements for HOLD service over II-NNI | Telecom Italia, Ericsson | Revised in C3-091965 |
C3‑091807 | Filling of the table about major capabilities on II-NNI | Orange, Nokia Siemens Networks | Revised in C3-091966 |
C3‑091808 | Deletion of an editors note on OIR service | Orange | Revised in C3-091967 |
C3‑091809 | Traffic Policing | LM Ericsson | Revised in C3-091997 |
C3‑091810 | RTCP Handling | Nokia Siemens Networks,^^Alcatel-Lucent | Agreed |
C3‑091811 | Media Inactivity Detection | Nokia Siemens Networks,^^Alcatel-Lucent | Agreed |
C3‑091812 | Mandatory features in TrGW | Alcatel-Lucent | Revised in C3-091977 |
C3‑091813 | Specification clean-up | Alcatel-Lucent | Revised in C3-091978 |
C3‑091814 | Abbreviations Tidy-Up | LM Ericsson | Agreed |
C3‑091815 | Use of IP Interface Type | LM Ericsson | Agreed |
C3‑091816 | Traffic Policing | LM Ericsson | Revised in C3-091998 |
C3‑091817 | Handling of RTCP | Nokia Siemens Networks,^^Alcatel-Lucent | Revised in C3-091958 |
C3‑091818 | Media Inactivity Detection | Nokia Siemens Networks,^^Alcatel-Lucent | Agreed |
C3‑091819 | Correction of CPC parameter mapping | Ericsson | Revised in C3-091949 |
C3‑091820 | Correction of CPC parameter mapping | Ericsson | Revised in C3-091950 |
C3‑091821 | Interworking ISUP OLI parameter | Alcatel-Lucent | Revised in C3-091953 |
C3‑091822 | Interworking ISUP OLI parameter | Alcatel-Lucent | Revised in C3-091974 |
C3‑091823 | Mapping for Communication Barring Service | LM Ericsson | Agreed |
C3‑091824 | Mapping for Communication Barring Service | LM Ericsson | Agreed |
C3‑091825 | Mapping of From header at O-MGCF | Deutsche Telekom | Revised in C3-091951 |
C3‑091826 | Mapping of From header at O-MGCF | Deutsche Telekom | Revised in C3-091952 |
C3‑091827 | Support interworking of Call Forwarding information | Alcatel-Lucent, Ericsson | Revised in C3-091954 |
C3‑091828 | CW and NDUB interaction added | Ericsson, Research in Motion | Revised in C3-091957 |
C3‑091829 | Mapping of ISUP Cause values in CPG or ACM to SIP reason header in provisional responses | Nokia Siemens Networks | Revised in C3-091969 |
C3‑091830 | Reference Tidy-Up | LM Ericsson | Agreed |
C3‑091831 | Miscellaneous Corrections | LM Ericsson | Agreed |
C3‑091832 | IMS Breakout Session | - | Withdrawn |
C3‑091833 | IMS Breakout Session | - | Withdrawn |
C3‑091834 | IMS Breakout Session | - | Withdrawn |
C3‑091835 | IMS Breakout Session | - | Withdrawn |
C3‑091836 | IMS Breakout Session | - | Withdrawn |
C3‑091837 | IMS Breakout Session | - | Withdrawn |
C3‑091838 | IMS Breakout Session | - | Withdrawn |
C3‑091839 | IMS Breakout Session | - | Withdrawn |
C3‑091840 | IMS Breakout Session | - | Withdrawn |
C3‑091841 | Report the UE time zone information to the PCRF | Huawei | Revised in C3-091929 |
C3‑091842 | Correction for the missing Charging-Rule-Base-Name | Huawei | Agreed |
C3‑091843 | Correction for the missing Charging-Rule-Base-Name | Huawei | Agreed |
C3‑091844 | Correction for the missing Charging-Rule-Base-Name | Huawei | Agreed |
C3‑091845 | Rx request handling | Camiant | Agreed |
C3‑091846 | Rx request handling | Camiant | Agreed |
C3‑091847 | Rx request handling | Camiant | Agreed |
C3‑091848 | PCEF-Initiated IP-CAN session modification flows | Ericsson, ZTE, Huawei | Agreed |
C3‑091849 | PCEF-Initiated IP-CAN session modification flows | Ericsson, ZTE, Huawei | Agreed |
C3‑091850 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for HR | Alcatel-Lucent | Revised in C3-091913 |
C3‑091851 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for HR | Alcatel-Lucent | Revised in C3-091914 |
C3‑091852 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for VA | Alcatel-Lucent | Revised in C3-091917 |
C3‑091853 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for VA | Alcatel-Lucent | Revised in C3-091918 |
C3‑091854 | Deferred session linking handling in roaming scenario | ZTE | Agreed |
C3‑091855 | Deferred session linking handling in roaming scenario | ZTE | Agreed |
C3‑091856 | QCI change during an MS-Initiated EPS Bearer Modification Procedure | Huawei | Agreed |
C3‑091857 | QCI change during an MS-Initiated EPS Bearer Modification Procedure | Huawei | Agreed |
C3‑091858 | Cleaning of the Editor's Notes | Huawei | Agreed |
C3‑091859 | Cleaning of the Editor's Notes | Huawei | Agreed |
C3‑091860 | 3GPP-RAT-Type support for backward compatibility | Ericsson | Agreed |
C3‑091861 | 3GPP-RAT-Type support for backward compatibility | Ericsson | Agreed |
C3‑091862 | Corrections on setting of IP-CAN Type value | Qualcomm Europe | Agreed |
C3‑091863 | Corrections on setting of IP-CAN Type value | Qualcomm Europe | Agreed |
C3‑091864 | EPC-based non-3GPP Annex | Qualcomm Europe | Revised in C3-091931 |
C3‑091865 | EPC-based non-3GPP Annex | Qualcomm Europe | Revised in C3-091932 |
C3‑091866 | Resolve editors note on MCC/MNC AVP | Qualcomm Europe | Agreed |
C3‑091867 | Resolve editors note on MCC/MNC AVP | Qualcomm Europe | Agreed |
C3‑091868 | Use of QoS Information AVP V-PCRF Acceptable QoS Offer | Alcatel-Lucent | Postponed |
C3‑091869 | Use of QoS Information AVP V-PCRF Acceptable QoS Offer | Alcatel-Lucent | Postponed |
C3‑091870 | Clarification of the Event-Report-Indication AVP | ZTE | Agreed |
C3‑091871 | Clarification of the Event-Report-Indication AVP | ZTE | Agreed |
C3‑091872 | Proposed Schedule for CT3#56 | CT3 Chairman | Revised in C3-091896 |
C3‑091873 | Supported Features for Rel-9 Gx and Gxx | Camiant | Revised in C3-092006 |
C3‑091874 | Supported Features for Rel-9 Rx | Camiant | Revised in C3-092009 |
C3‑091875 | Supported-Features for S9 | Camiant | Revised in C3-092007 |
C3‑091876 | Bearer control mode selection over S9 | ZTE | Agreed |
C3‑091877 | Bearer control mode selection over S9 | ZTE | Agreed |
C3‑091878 | Deferred session linking handling in visited access case | ZTE | Revised in C3-091933 |
C3‑091879 | Deferred session linking handling in visited access case | ZTE | Revised in C3-091934 |
C3‑091880 | Use of Access Network charging network | ZTE | Agreed |
C3‑091881 | Use of Access Network charging network | ZTE | Agreed |
C3‑091882 | P-CSCF Restoration procedure | Ericsson | Revised in C3-091915 |
C3‑091883 | P-CSCF failover procedures | Ericsson | Agreed |
C3‑091884 | Session linking handling of MUPSAP in visited access case | ZTE | Revised in C3-091928 |
C3‑091885 | Correction to applicability of the PDN-Connection-ID AVP | ZTE | Revised in C3-091927 |
C3‑091886 | Details on failure detection | NEC | Revised in C3-091936 |
C3‑091887 | Message flow of PCRF failure reselection for the redirect DRA | Huawei | Revised in C3-091935 |
C3‑091888 | Requirement on emergency and priority services handling and configurability for the operator | NEC | Agreed |
C3‑091889 | Details on PCRF session state restoration | NEC | Agreed |
C3‑091890 | Remove re-used AVPs in Table 20.5.1 | ZTE | Agreed |
C3‑091891 | Adding details to graceful termination of bearer services | NEC | Agreed |
C3‑091892 | Failure detection | Nokia Siemens Networks | Revised in C3-091924 |
C3‑091893 | Multimedia Priority Service (MPS) | Telcordia Technologies, NCS, | Revised in C3-091905 |
C3‑091894 | Exception Sheet for MPS (Multimedia Priority service) | Telcordia Technologies, NCS, | - |
C3‑091895 | Soft recovery | Nokia Siemens Networks | Revised in C3-091937 |
C3‑091896 | Proposed Schedule for CT3#56 | CT3 Chairman | Noted |
C3‑091897 | Meeting Calendar for 2009 and 2010 | MCC | Noted |
C3‑091898 | Expected terminal behavior for Text Telphony | - | Revised in C3-091968 |
C3‑091899 | LS on GTT-IP interworking with PSTN/ | alcatel-lucent | Revised in C3-091971 |
C3‑091900 | PCC/QoS rule modification failure handling | Nokia Siemens Networks, Ericsson, Qualcomm Europe, Alcatel-Lucent | Revised in C3-091990 |
C3‑091901 | PCC/QoS rule modification failure handling | Nokia Siemens Networks | Revised in C3-091991 |
C3‑091902 | Mapping of access network codes | Nokia Siemens Networks | Revised in C3-091992 |
C3‑091903 | Mapping of access network codes | Nokia Siemens Networks | Revised in C3-091993 |
C3‑091904 | Revised WID on CT1 aspects of SRVCC support for IMS Emergency Calls | Ericsson | Endorsed |
C3‑091905 | Multimedia Priority Service (MPS) | Telcordia Technologies, NCS, | - |
C3‑091906 | Actions for solution 2 | Nokia Siemens Networks | Revised in C3-091925 |
C3‑091907 | Clarification for Editors Notes on strict termination | NEC | Revised in C3-091941 |
C3‑091908 | Correction to the Enabling of IP Flows in 29.213 | ZTE | Agreed |
C3‑091909 | Correction to the Enabling of IP Flows in 29.213 | ZTE | Agreed |
C3‑091910 | Correction to the Enabling of IP Flows in 29.213 | ZTE | Agreed |
C3‑091911 | Updated WID for IMS Media Plane Security | Vodafone | Revised in C3-091921 |
C3‑091912 | PCC Support for CSG(R9 29.212) | Huawei | Revised in C3-091946 |
C3‑091913 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for HR | Alcatel-Lucent | Agreed |
C3‑091914 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for HR | Alcatel-Lucent | Agreed |
C3‑091915 | P-CSCF Restoration procedure | Ericsson | Agreed |
C3‑091916 | LS to 3GPP CT3, CT4 on Consent of ITU-T H.248.1v3Amd.2 and ITU-T H.248.72 | ITU-T Study Group 16 | Postponed |
C3‑091917 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for VA | Alcatel-Lucent | Revised in C3-091942 |
C3‑091918 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for VA | Alcatel-Lucent | Revised in C3-091943 |
C3‑091919 | V-PCRF Handling of BBERF CCR/CCA Messages | Alcatel-Lucent | Agreed |
C3‑091920 | V-PCRF Handling of BBERF CCR/CCA Messages | Alcatel-Lucent | Agreed |
C3‑091921 | Updated WID for IMS Media Plane Security | Vodafone | Endorsed |
C3‑091922 | Destination Realm | NTT DOCOMO, Ericsson, Huawei, Alcatel-Lucent | Revised in C3-091994 |
C3‑091923 | Destination Realm | NTT DOCOMO | Revised in C3-091995 |
C3‑091924 | Failure detection | Nokia Siemens Networks | Agreed |
C3‑091925 | Actions for solution 2 | Nokia Siemens Networks | Agreed |
C3‑091926 | Rel-9 Work Item Exception for P-CSCF restoration procedures | Ericsson | Revised in C3-092011 |
C3‑091927 | Correction to applicability of the PDN-Connection-ID AVP | ZTE | Agreed |
C3‑091928 | Session linking handling of MUPSAP in visited access case | ZTE | Agreed |
C3‑091929 | Report the UE time zone information to the PCRF | Huawei | Agreed |
C3‑091930 | AF procedure for the Specific-Action | Huawei | Agreed |
C3‑091931 | EPC-based non-3GPP Annex | Qualcomm Europe | Revised in C3-091944 |
C3‑091932 | EPC-based non-3GPP Annex | Qualcomm Europe | Revised in C3-091945 |
C3‑091933 | Deferred session linking handling in visited access case | ZTE | Agreed |
C3‑091934 | Deferred session linking handling in visited access case | ZTE | Agreed |
C3‑091935 | Message flow of PCRF failure reselection for the redirect DRA (R9 29.816) | Huawei | Agreed |
C3‑091936 | Details on failure detection | NEC | Agreed |
C3‑091937 | Soft recovery | Nokia Siemens Networks | Agreed |
C3‑091938 | Reference to Reason Header in Responses | Deutsche Telekom, Nokia Siemens Networks | Agreed |
C3‑091939 | Reference to Reason Header in Responses | Nokia Siemens Networks | Agreed |
C3‑091940 | Procedures for support of ISDN fallback^^ | ETSI TISPAN WG3 | Postponed |
C3‑091941 | Clarification for Editors Notes on strict termination | NEC | Agreed |
C3‑091942 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for VA | Alcatel-Lucent | Revised in C3-091988 |
C3‑091943 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for VA | Alcatel-Lucent | Revised in C3-091989 |
C3‑091944 | EPC-based non-3GPP Annex | Qualcomm Europe | Agreed |
C3‑091945 | EPC-based non-3GPP Annex | Qualcomm Europe | Agreed |
C3‑091946 | PCC Support for CSG | Huawei | Agreed |
C3‑091947 | Response LS on eCall data transfer | Qualcomm | Withdrawn |
C3‑091948 | New WID "IP-SM-GW enhancements for CPM-SMS Interworking" | Ericsson, ST Ericsson, Acision | Revised in C3-092005 |
C3‑091949 | Correction of CPC parameter mapping | Ericsson | Revised in C3-091975 |
C3‑091950 | Correction of CPC parameter mapping | Ericsson | Revised in C3-091976 |
C3‑091951 | Mapping of From header at O-MGCF | Deutsche Telekom, Ericsson | Agreed |
C3‑091952 | Mapping of From header at O-MGCF | Deutsche Telekom, Ericsson | Agreed |
C3‑091953 | Interworking ISUP OLI parameter | Alcatel-Lucent | Revised in C3-091973 |
C3‑091954 | Support interworking of Call Forwarding information | Alcatel-Lucent, Ericsson | Agreed |
C3‑091955 | Annex A header updated | Orange | Revised in C3-092000 |
C3‑091956 | Annex A header updated | Orange | Revised in C3-091999 |
C3‑091957 | CW and NDUB interaction added | Ericsson, Research in Motion | Agreed |
C3‑091958 | Handling of RTCP | Nokia Siemens Networks,^^Alcatel-Lucent | Revised in C3-091979 |
C3‑091959 | Completing the Personal Network Management (PNM) supplementary service | Ericsson,Telecom Italia | Agreed |
C3‑091960 | Completing the Anonymous Communication Rejection (ACR) supplementary service | Ericsson,Telecom Italia | Revised in C3-091981 |
C3‑091961 | Completing Completion of Communications to Busy Subscriber (CCBS) and Completion of Communications by No Reply (CCNR) supplementary services | Ericsson,Telecom Italia | Revised in C3-091982 |
C3‑091962 | Completing the Communication Barring (CB) supplementary service | Ericsson,Telecom Italia | Revised in C3-092003 |
C3‑091963 | Completing Explicit Communication Transfert (ECT) | Ericsson | Agreed |
C3‑091964 | Completing Communication DIVersion (CDIV) supplementary services | Ericsson,Telecom Italia | Revised in C3-091983 |
C3‑091965 | Requirements for HOLD service over II-NNI | Telecom Italia, Ericsson | Revised in C3-091984 |
C3‑091966 | Filling of the table about major capabilities on II-NNI | Orange, Nokia Siemens Networks | Revised in C3-092001 |
C3‑091967 | Deletion of an editors note on OIR service | Orange | Agreed |
C3‑091968 | LS on expected MMTEL terminal behaviour for text telephony | Nokia Siemens Networks | Approved |
C3‑091969 | Mapping of ISUP Cause values in CPG or ACM to SIP reason header in provisional responses | Nokia Siemens Networks | Revised in C3-092004 |
C3‑091970 | LS on GTT-IP interworking with PSTN/ | alcatel-lucent | Revised in C3-091986 |
C3‑091971 | Aligning references to P-Asserted-Service | Ericsson, Orange | Agreed |
C3‑091972 | Requirements for CW service over II-NNI | Telecom Italia, Ericsson | Agreed |
C3‑091973 | Interworking ISUP OLI parameter | Alcatel-Lucent | Agreed |
C3‑091974 | Interworking ISUP OLI parameter | Alcatel-Lucent | Agreed |
C3‑091975 | Correction of CPC parameter mapping | Ericsson | Agreed |
C3‑091976 | Correction of CPC parameter mapping | Ericsson | Agreed |
C3‑091977 | Mandatory features in TrGW | Alcatel-Lucent | Agreed |
C3‑091978 | Specification clean-up | Alcatel-Lucent | Agreed |
C3‑091979 | Handling of RTCP | Nokia Siemens Networks,^^Alcatel-Lucent | Agreed |
C3‑091980 | Completing the Three-Party (3PTY) and Conference (CONF) supplementary services | Ericsson,Telecom Italia | Revised in C3-092002 |
C3‑091981 | Completing the Anonymous Communication Rejection (ACR) supplementary service | Ericsson,Telecom Italia | Agreed |
C3‑091982 | Completing Completion of Communications to Busy Subscriber (CCBS) and Completion of Communications by No Reply (CCNR) supplementary services | Ericsson,Telecom Italia | Agreed |
C3‑091983 | Completing Communication DIVersion (CDIV) supplementary services | Ericsson,Telecom Italia | Agreed |
C3‑091984 | Requirements for HOLD service over II-NNI | Telecom Italia, Ericsson | Agreed |
C3‑091985 | Update of SID on PCRF Failure and Restoration | NEC, Bridgewater Systems, Telecom Italia, Huawei, NTT DOCOMO, NTT, Alcatel-Lucent | Revised in C3-092008 |
C3‑091986 | LS on GTT-IP interworking with PSTN/ | alcatel-lucent | Approved |
C3‑091987 | Completion of IMS Restoration Procedures | Ericsson | Revised in C3-092010 |
C3‑091988 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for VA | Alcatel-Lucent | Agreed |
C3‑091989 | V-PCRF VPLMN Policy Enforcement Acceptable QoS Offer for VA | Alcatel-Lucent | Agreed |
C3‑091990 | PCC/QoS rule modification failure handling | Nokia Siemens Networks | Agreed |
C3‑091991 | PCC/QoS rule modification failure handling | Nokia Siemens Networks | Agreed |
C3‑091992 | Mapping of access network codes | Nokia Siemens Networks | Agreed |
C3‑091993 | Mapping of access network codes | Nokia Siemens Networks | Agreed |
C3‑091994 | Destination Realm | NTT DOCOMO, Ericsson, Huawei, Alcatel-Lucent | Agreed |
C3‑091995 | Destination Realm | NTT DOCOMO, Ericsson, Huawei, Alcatel-Lucent | Agreed |
C3‑091996 | Rel-9 Work Item Exception for Operational description of the Inter-IMS Network to Network Interface (II-NNI) | Orange | Revised in C3-092013 |
C3‑091997 | Traffic Policing | LM Ericsson, Nokia Siemens Networks, Alcatel-Lucent | Agreed |
C3‑091998 | Traffic Policing | LM Ericsson, Nokia Siemens Networks, Alcatel-Lucent | Revised in C3-092012 |
C3‑091999 | Annex A header updated | Orange | Agreed |
C3‑092000 | Annex A header updated | Orange | Agreed |
C3‑092001 | Filling of the table about major capabilities on II-NNI | Orange, Nokia Siemens Networks | Agreed |
C3‑092002 | Completing the Three-Party (3PTY) and Conference (CONF) supplementary services | Ericsson,Telecom Italia | Agreed |
C3‑092003 | Completing the Communication Barring (CB) supplementary service | Ericsson,Telecom Italia | Agreed |
C3‑092004 | Mapping of ISUP Cause values in CPG or ACM to SIP reason header in provisional responses | Nokia Siemens Networks | Revised in C3-092014 |
C3‑092005 | IP-SM-GW enhancements for CPM-SMS Interworking | Ericsson, ST-Ericsson | Agreed |
C3‑092006 | Supported Features for Rel-9 Gx and Gxx | Camiant | Agreed |
C3‑092007 | Supported-Features for S9 | Camiant | Agreed |
C3‑092008 | Update of SID on PCRF Failure and Restoration | NEC, Bridgewater Systems, Telecom Italia, Huawei, NTT DOCOMO, NTT, Alcatel-Lucent | Agreed |
C3‑092009 | Supported Features for Rel-9 Rx | Camiant | Agreed |
C3‑092010 | Completion of IMS Restoration Procedures | Ericsson | Agreed |
C3‑092011 | Rel-9 Work Item Exception for P-CSCF restoration procedures | Ericsson | Agreed |
C3‑092012 | Traffic Policing | LM Ericsson, Nokia Siemens Networks, Alcatel-Lucent | Agreed |
C3‑092013 | Rel-9 Work Item Exception for Operational description of the Inter-IMS Network to Network Interface (II-NNI) | Orange | Agreed |
C3‑092014 | Mapping of ISUP Cause values in CPG or ACM to SIP reason header in provisional responses | Nokia Siemens Networks | Agreed |
C3‑092015 | Status of CT3 Work Items | CT3 Chairman | Agreed |
C3‑092016 | TR 28.816 v0.3.0 | NEC | Agreed |
page generated from database: 2024-03-25 09:25:51